MUN. AND ENV. ENG., INC. v. Slaughter Constr. Co.

961 So. 2d 889, 2007 WL 80502
CourtCourt of Civil Appeals of Alabama
DecidedJanuary 12, 2007
Docket2050007
StatusPublished
Cited by1 cases

This text of 961 So. 2d 889 (MUN. AND ENV. ENG., INC. v. Slaughter Constr. Co.) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MUN. AND ENV. ENG., INC. v. Slaughter Constr. Co., 961 So. 2d 889, 2007 WL 80502 (Ala. Ct. App. 2007).

Opinion

Alabama Municipal and Environmental Engineers, Inc. ("AME"), appeals from a judgment of the Baldwin Circuit Court in favor of Slaughter Construction Company, Inc. ("Slaughter"), following a bench trial. We reverse.

Pursuant to Ala. Code 1975, Title 39, the Utilities Board of the City of Bay Minette ("the Board") solicited bids for a one-year contract for the rehabilitation of existing manholes ("the contract").1 The Board hired AME to prepare the specifications for the contract ("the contract specifications"), and to gather, rank, and forward bids to the Board, along with a recommendation as to which company submitting a bid should be awarded the contract. The ultimate decision regarding which company should receive the contract rested solely with the Board.

The contract specifications did not call for the rehabilitation of a specific number of manholes; instead, the contract specifications allowed for the Board to determine if and when manholes required rehabilitation. The contract specifications allowed the contract period to be extended to up to three years from the bid date. The contract specifications called for the rehabilitation of manholes using a cementitious process, an epoxy process, or a fiberglass process, with the Board making the decision as to the process to be used on a manhole-by-manhole basis, after the award of the contract. Thus, the contract specifications required that companies submitting bids be able to work with all three types of materials, and the bids submitted had to include costs for all three.

Section 12 of the contract specifications concerned the rehabilitation of manholes using the epoxy process. Section 12.02 provided:

"12.02 QUALITY ASSURANCE

". . . .

"C. The manhole rehabilitation contractor shall provide evidence and preferences for having successfully installed resin based liners in at least 750 manholes and must have *Page 891 at least five (5) years experience in using the products specified in this specification. The product must also have been installed in at least 10,000 manholes during the last ten (10) years and have had at least 3000 manholes successfully installed for a period of five (5) years or longer. Certification of compliance with these requirements shall be included with the bid proposal."

On May 25, 2004, the day bids were due, AME received three bids. Staggs Environmental Construction ("Staggs") submitted a bid in the amount of $82,464; Slaughter submitted a bid in the amount of $89,200.04; and Suncoast Infrastructures, Inc., submitted a bid in the amount of $107,749.

On May 27, 2004, Slaughter sent a letter of protest to AME in which it complained that Staggs's bid did not comply with the contract specifications. Slaughter's letter stated:

"We write in regard to the bids which were received on the above referenced project in Bay Minette, AL on May 25th, 2004.

"Paragraph 12.02.C of the contract specifications which is under the heading of Manhole and Wet Well Rehabilitation (Epoxy/Resin Based) states as follows `The manhole rehabilitation contractor shall provide evidence and references for having successfully installed resin based liners in at least 750 manholes and must have at least five (5) years experience in using the products specified in this specification. The product must also have been installed in at least 10,000 manholes during the last ten (10) years and have had at least 3000 manholes successfully installed for a period of five (5) years or longer. Certification of compliance with these requirements shall be included with the bid proposal (emphasis added)'.

"Staggs Environmental Construction, Inc. (Staggs) submitted in its bid a certification letter written by Stephen's Technologies, Inc. (Stephens) which is somewhat vague and confusing as to whether Stephens actually meets the manufacturers product requirements of 10,000 manholes installed during the last ten (10) years. Stephens clearly indicates though in it's letter (and also Staggs by submitting the letter) that Staggs as the rehabilitation contractor does not meet the performance requirement of having installed liners in 750 manholes and five (5) years of experience as an applicator of the epoxy products.

"Staggs bid is therefore non-responsive because:

"1.)Staggs clearly will not be able to provide evidence and references for having successfully installed resin based liners in at least 750 manholes and having at least five (5) years experience. No other conclusion can be reached from Stagg's attempt via Stephen's letter to circumvent the experience requirements by substituting the presence of a factory supplied representative in lieu of the actual experience required of Staggs under the project specifications.

"2.) The Stephen's letter is inadequate as a certification of compliance of meeting the requirements of the bid specifications. It is vague in its declarations and doesn't specifically address meeting the requirements of paragraph 12.02C.

"The bid submitted by our firm, Slaughter Construction Company, Inc. includes a certification clearly referencing paragraph 12.02.C and certifies unambiguously *Page 892 that our product, SprayWall has been installed in at least 10,000 manholes during the last ten (10) years and has been installed in at least 3000 manholes during the last five (5) years. Additionally we stand ready as the contractor to provide evidence that we have successfully installed resin based liners in at least 750 manholes and that we have at least five (5) years experience in using the product as is required by specification paragraph 12.02C.

"The bid documents state that `The award of the Contract, if it be awarded, will be by the Owner to the lowest responsible Bidder whose Proposal shall comply with all the requirements necessary to render it formal.' Stagg's bid contains material deficiencies which are not informalities which can or should be waived. It is clearly non-responsive. The bid by our firm does comply in every aspect with the requirements of the bid and we request that we be awarded the contract as the lowest responsible bidder on this bid."

AME was not satisfied with the certification letter that Staggs submitted with its bid. AME undertook to determine whether Staggs did, in fact, possess the experience with epoxy-based liners for which the contract specifications called, as well as to obtain information on the epoxy product Staggs intended to use if awarded the contract. AME became satisfied that Staggs met the experience requirements of section 12.02C after reviewing a letter from Staggs dated June 22, 2004, indicating that it would use a subcontractor for the epoxy-based liners that met the experience requirements of section 12.02C. AME became satisfied that Staggs met the product requirements of section 12.02C after it became aware that Staggs would be using an epoxy that was manufactured by New Life Coatings.

Thereafter, AME sent the bid materials to the Board and recommended to the Board that it award the contract to Staggs as the lowest responsible bidder. The Board, after reviewing AME's recommendations, met on June 28, 2004, and decided to award the contract to Staggs. A representative of Slaughter appeared at the Board's August meeting to express its objections to the awarding of the contract to Staggs. The contract with Staggs was executed on August 20, 2004.

On November 10, 2004, Slaughter sued AME. Slaughter alleged that AME had improperly recommended Staggs as the lowest responsible bidder to the Board, in spite of the fact that Staggs's bid did not comply with the contract specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Horsfield Materials, Inc. v. City of Dyersville
834 N.W.2d 444 (Supreme Court of Iowa, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
961 So. 2d 889, 2007 WL 80502, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mun-and-env-eng-inc-v-slaughter-constr-co-alacivapp-2007.