Multibank 2009-1 CML-ADC Venture, L.L.C. v. S. Bass Island Resort, Ltd.

2017 Ohio 344
CourtOhio Court of Appeals
DecidedJanuary 27, 2017
DocketE-15-061
StatusPublished

This text of 2017 Ohio 344 (Multibank 2009-1 CML-ADC Venture, L.L.C. v. S. Bass Island Resort, Ltd.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Multibank 2009-1 CML-ADC Venture, L.L.C. v. S. Bass Island Resort, Ltd., 2017 Ohio 344 (Ohio Ct. App. 2017).

Opinion

[Cite as Multibank 2009-1 CML-ADC Venture, L.L.C. v. S. Bass Island Resort, Ltd., 2017-Ohio-344.]

IN THE COURT OF APPEALS OF OHIO SIXTH APPELLATE DISTRICT ERIE COUNTY

Multibank 2009-1 CML-ADC Court of Appeals No. E-15-061 Venture, LLC Trial Court No. 2008-CV-0749 Appellee

v.

South Bass Island Resort, Ltd., et al.

Defendants DECISION AND JUDGMENT

[John C. Tomberlin—Appellant] Decided: January 27, 2017

*****

Martha S. Sullivan, Stephanie E. Niehaus and F. Maximilian Czernin, for appellee.

Geoffrey L. Oglesby, for appellant.

PIETRYKOWSKI, J.

{¶ 1} Appellant, Dr. John C. Tomberlin, appeals the judgment of the Erie County

Court of Common Pleas, following a bench trial, which found that appellant personally

guaranteed a loan from the Columbian Bank and Trust Company (“Columbian Bank”) to South Bass Island Resort, Ltd. (“SBIR”), and awarded judgment to appellee, Multibank

2009-1 CML-ADC Venture, LLC (“Multibank”)—Columbian Bank’s successor in

interest—in the amount of $20,576,899.91 plus ongoing interest, taxes, assessments,

insurance, attorney fees, and costs. For the reasons that follow, we affirm.

I. Facts and Procedural Background

{¶ 2} Many of the underlying facts are undisputed. At the end of May 2006,

Columbian Bank offered to loan up to $8.6 million to SBIR for a property development

project. Included as one of the conditions of granting the loan contained in the loan

commitment letter was that the loan “will be 100% joint and severally guaranteed by

Cecil Weatherspoon; John C. Tomberlin; and 250 Centre, LTD.”1 Notably, this was the

only loan being discussed by Columbian Bank and SBIR in June 2006.

{¶ 3} The timeframe to close the loan was very short, with an original target date

of June 27, 2006. The timeframe was further cut shorter in an effort to close on June 15,

2006. On June 7, 2006, Guy Humphrey, the attorney for Columbian Bank,2 sent several

draft documents, including a draft of an “Unconditional Cognovit Guaranty” for

appellant, to SBIR’s attorney, Jeffrey Rengel. The draft had blanks for the date of the

guaranty and the date of the corresponding loan agreement. Rengel purportedly amended

the “Unconditional Cognovit Guaranty” to change the location of execution, and sent it to

1 Cecil Weatherspoon was the principle of both SBIR and 250 Centre Ltd. 2 Guy Humphrey is now a United States Bankruptcy Judge for the Southern District of Ohio. Thus, we will refer to him throughout as “Judge Humphrey.”

2. appellant, who was in Alabama. As the closing date approached, and having not yet

received the “Unconditional Cognovit Guaranty,” on June 12, 2006, Judge Humphrey

sent a second “Cognovit Unconditional Guaranty” to Rengel. The second guaranty listed

June 14, 2006, as the date of execution of both the guaranty and the corresponding loan

agreement.

{¶ 4} On June 15, 2006, Judge Humphrey emailed Rengel and stated that he had

reviewed everything for the closing and was just waiting to receive a few more

documents before the loan could be disbursed. Included in Judge Humphrey’s review

was the original draft of appellant’s “Unconditional Cognovit Guaranty.” Appellant had

signed the draft, and his signature was notarized on June 8, 2006. Furthermore,

June “8th,” 2006, was handwritten in the blanks for the dates of the guaranty and the

corresponding loan agreement. As for the additional documents that Judge Humphrey

was waiting on, one of them was a U.S. “Patriot Act form” for appellant. The completed

Patriot Act form and a copy of appellant’s driver’s license were received later that day,

and the funds were disbursed by Columbian. The HUD Settlement Statement indicates

that as part of the disbursement, $350,000 was paid to appellant.

{¶ 5} Relevant here, the details of the loan agreement itself are that it was to be a

loan of up to $8.6 million, which was to be made in multiple advances as the property

was developed. The loan agreement was dated June 14, 2006, and was for an 18-month

term, with a maturity date of December 15, 2007. In addition, the loan agreement

provided that

3. The payment and performance of all of the Obligations shall also be

secured and/or guaranteed by (i) the joint and several Cognovit

Unconditional Guaranty (the “Guarantees”) of Cecil Weatherspoon,

John C. Tomberlin, and 250 Centre, Ltd. (the “Guarantors”) of even date

herewith to be executed and delivered at Closing by the Guarantors for the

benefit of Lender * * *.

{¶ 6} It is undisputed that SBIR defaulted on the terms of the loan agreement, and

as of the date of the trial, no payments had been made on the loan.

{¶ 7} On August 13, 2008, Columbian filed its complaint against SBIR, Cecil

Weatherspoon, 250 Centre, Ltd., and appellant (the “defendants”). On March 26, 2009,

the defendants filed their answer and asserted two counterclaims, one for fraud and one

for breach of contract, based on Columbian’s alleged misrepresentations regarding the

disbursement of the funds, and its alleged failure to disburse the entire $8.6 million.

{¶ 8} After extensive litigation, the parties filed cross-motions for summary

judgment. Weatherspoon, 250 Centre, Ltd., and appellant moved for partial summary

judgment on appellee’s claims, on the basis that the guaranties were unenforceable as a

matter of law. Appellee, in turn, moved for summary judgment on its claims against all

the defendants, as well as for summary judgment on the defendants’ counterclaims.

{¶ 9} On November 16, 2011, the trial court entered its judgment denying

Weatherspoon’s, 250 Centre, Ltd.’s, and appellant’s motion for summary judgment on

appellee’s claims. Likewise, the trial court granted appellee’s motion for summary

4. judgment on its claims against SBIR, Weatherspoon, and 250 Centre Ltd. Thus, the court

entered judgment against SBIR, Weatherspoon, and 250 Centre Ltd. in the principle

amount of $7,849,093.30, plus interest, taxes, assessments and insurance, and costs. The

court also granted summary judgment in favor of appellee on the defendants’

counterclaims, and dismissed those counterclaims with prejudice. As to appellant, the

trial court ruled that genuine issues of material fact precluded summary judgment on

appellee’s claims against him. Specifically, the court identified the issues as “whether

there were two loans or one; the respective intent of the parties; and the details of the

content of the Tomberlin Guaranty.” The court ordered that the remaining issues related

to appellant’s guaranty would be set for a bench trial.

{¶ 10} After further litigation and numerous delays and continuances, the matter

finally came before the court for a two-day bench trial held on March 18 and 19, 2014.

At the trial, appellee called as its only two witnesses, Judge Humphrey, by a videotaped

deposition, and Michael Yaffe, a senior vice president of one of appellee’s subsidiaries.

Appellant rested without calling any witnesses or submitting any evidence.

{¶ 11} Following the trial, on September 2, 2015, the court entered its judgment

against appellant, finding by a preponderance of the evidence that appellant did guaranty

the loan between Columbian Bank and SBIR. The court awarded appellee

$20,576,899.91 plus ongoing interest, taxes, assessments, insurance, attorney fees, and

costs.

5. II. Assignments of Error

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eastley v. Volkman
2012 Ohio 2179 (Ohio Supreme Court, 2012)
Sunoco, Inc. (R & M) v. Toledo Edison Co.
2011 Ohio 2720 (Ohio Supreme Court, 2011)
Lorain National Bank v. Saratoga Apartments
572 N.E.2d 198 (Ohio Court of Appeals, 1989)
Midam Bank v. Dolin, Unpublished Decision (6-30-2005)
2005 Ohio 3353 (Ohio Court of Appeals, 2005)
Harless v. Willis Day Warehousing Co.
375 N.E.2d 46 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Kelly v. Medical Life Insurance
509 N.E.2d 411 (Ohio Supreme Court, 1987)
Village of Grafton v. Ohio Edison Co.
77 Ohio St. 3d 102 (Ohio Supreme Court, 1996)
Westfield Insurance v. Galatis
797 N.E.2d 1256 (Ohio Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2017 Ohio 344, Counsel Stack Legal Research, https://law.counselstack.com/opinion/multibank-2009-1-cml-adc-venture-llc-v-s-bass-island-resort-ltd-ohioctapp-2017.