Mullins v. Morgan

10 S.E.2d 593, 176 Va. 201, 131 A.L.R. 785, 1940 Va. LEXIS 246
CourtSupreme Court of Virginia
DecidedSeptember 5, 1940
DocketRecord No. 2259
StatusPublished
Cited by2 cases

This text of 10 S.E.2d 593 (Mullins v. Morgan) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mullins v. Morgan, 10 S.E.2d 593, 176 Va. 201, 131 A.L.R. 785, 1940 Va. LEXIS 246 (Va. 1940).

Opinion

Campbell, C. J.,

delivered the opinion of the court.

Appellants instituted this suit against appellees in the Circuit Court of Buchanan county. The object of the suit was to enjoin appellees from the further construction of a large building situated on the south side of Slate Creek and to compel the removal of a concrete wall eight or ten feet high, erected by appellees, which extends out into the creek for a distance of eleven feet.

The material allegations of the bill of complaint are that appellants are the owners in fee of certain real estate situated in the town of Grundy; that said tracts or parcels of land are situated along and border on Slate Creek; that the channel of Slate Creek was seventy-four feet wide; that appellees are erecting a building on the south side of Slate [204]*204•Creek, and have, by the erection of a concrete wall, encroached upon the channel of Slate Creek to the extent of eleven feet, thereby diverting the flow of water in the channel of the creek and exposing the -properties of appellants to the hazard of inundation and damage in time of high waters; and that said wall constitutes a nuisance. -

■The court granted a temporary injunction, but upon the Anal submission of the case on bill, answer and depositions, a decree was pronounced refusing a permanent injunction and dismissing the-bill of complaint. From this decree appellants have been allowed an appeal.

It is conceded by counsel that the case falls within narrow limits and is to be determined by a decision of two issues, viz: TL&ve appellees, in the erection of the concrete wall in the channel of Slate Creek to the extent of eleven feet, created such a nuisance as entitles appellants to injunctive relief? Have appellants been guilty of laches in the prosecution of their suit seeking relief?

The evidence that appellees have encroached upon the channel of Slate Creek preponderates in favor of appellants. If there was any doubt about this conclusion, it has been settled by the trial court. In a written opinion, the trial court has reached a conclusion upon both of the issues involved in this case. The opinion is brief and is as follows:

“It is quite clear from the evidence that the creek bed just 'below the bridge recently constructed had a clearance of about seventy-seven feet in width and that defendant, Morgan, in the construction of the foundation for his building went out into the bed of the creek 10 or 11 feet, thus taking about one-seventh of the creek bed, which, of course, considerably lessened the carrying capacity of the creek bed at this point. However, it is contended by the defendant that the part of the creek bed not thus appropriated is amply sufficient to carry all of the water in Slate Creek in time of tide low or high. This contention is seriously controverted by complainants and constitutes their chief ground for asking the aid of a court of equity.
[205]*205“Complainants assume the burden of proving that the flow of the water down Slate Creek is and will be seriously hampered by act of the defendant to their detriment.
“In support of this contention the complainants and certain other witnesses testify that in their opinion and from their observation of this creek in the past the channel left open is not sufficient to carry the water in time of high tide and that same will be diverted over on to their land thereby damaging same.
“The defendant counters chiefly with the testimony of a skilled engineer who after taking various measurements and after making neat calculations gives it as his opinion that the creek bed in its present condition is sufficient to carry the flow of water at all times. He backs this up with rather strong and persuasive figures and illustrations.
“Thus the case comes to the court in a state highly problematical and none can say with any degree of certainty as to which contention is right without an actual test and this has not yet come.
“The court must either perpetuate the injunction or dissolve the same and dismiss the bill.” (Citing authorities.)
* sfc * * * $ $
“The court is of opinion under this evidence that in defendant Morgan’s construction work he went out entirely too far into the creek bed and that if the case had been presented before the work was done it would have been seasonable ¿nd proper to have granted a perpetual injunction, but as the case now stands the court views it in a much more unfavorable light.
“Counsel for defendant contends that complainants are guilty of laches and that their conduct invokes equitable estoppel against them. Complainants’ counsel presents an extensive brief in an effort to show that these defenses are not proper to be invoked in this case.
“Strictly speaking it may be that complainants are not guilty of laches and that their conduct does not justify an equitable estoppel, but however it may be, the Court is [206]*206clearly of the opinion that complainants were guilty of, for lack of a better name, we will call it procrastination, greatly to the injury of the defendant.
“Complainants had ample time to have acted earlier and justice and fair play loudly called upon them to act and act promptly if they meant to interpose objection to this work. Thus they could have saved defendant of an expenditure of at least three thousand dollars, which they now ask to destroy.
!(• *{S
“True, complainants did not wait for any great length of time, but time is not the determining factor in a case of this kind. They knew their rights and if they were being violated or infringed upon it was certainly open and obvious. They were bound to know that the defendant was preparing to expend large sums of money and they owed it to him to enter a solemn protest and if this failed they should have gone into court which they certainly could have done, and it was their solemn duty to have done without waiting until defendant had done work which it would now cost bim thousands of dollars to undo.
“It is claimed that they did protest but the evidence fails to disclose any protest. It does show that certain of the complainants had informal talks with the defendant in which they suggested that he was building too far out into the stream and that it might throw the water over on them, to which he replied that he did not think it would do so but if it did he would pay the damage and here the discussion ended. Two of the complainants most vitally concerned, Anderson and Jackson, saw the work progress from start to finish and they never one time mentioned the matter to the defendant.
“This inexcusable delay bears mightily upon the conscience of this court in the exercise of the court’s discretion in the perpetuation or dissolution of the injunction, in fact, it is the deciding factor. The court cannot escape the conclusion that to perpetuate this injunction would be inequitable and unjust.
[207]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Sequel Investors, Ltd. Partnership v. Albemarle Place EAAP, L.L.C.
89 Va. Cir. 337 (Albemarle County Circuit Court, 2014)
Town of Purcellville v. Potts
19 S.E.2d 700 (Supreme Court of Virginia, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
10 S.E.2d 593, 176 Va. 201, 131 A.L.R. 785, 1940 Va. LEXIS 246, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mullins-v-morgan-va-1940.