Muller v. Gillick

66 Mo. App. 500, 1896 Mo. App. LEXIS 96
CourtMissouri Court of Appeals
DecidedMay 12, 1896
StatusPublished
Cited by3 cases

This text of 66 Mo. App. 500 (Muller v. Gillick) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Muller v. Gillick, 66 Mo. App. 500, 1896 Mo. App. LEXIS 96 (Mo. Ct. App. 1896).

Opinion

Biggs, J.

The defendants had the contract for the construction of a building in Belleville, Illinois. The plaintiffs agreed with them to furnish and put in place the necessary iron work for the building at the [501]*501agreed price of $7,500. Their agreement was reduced to writing, and, among other things, it provided that the plaintiffs would furnish all of the iron work called for ‘‘according to plans and specifications of library building, Belleville, Illinois, as furnished by L. Kledus, architect, in accordance with the drawings, plans and elevations and specifications, furnished by the superintending architect and adopted for said buildings, which ■are hereunto annexed and made a part of this contract. And said superintending architect shall be the agent of the parties of the first part (defendants) in the erection of the building and improvements herein named. * * * And should it appear that any of the work hereby intended to be done, or matters relative thereto, are not fully detailed or explained in the said- specifications and drawings, the said parties of the second part (plaintiffs) shall apply to the superintendent for such further detailed explanations, and perform his orders as part of this contract. The superintendent shall be at liberty to make any deviation from or alteration in the plan, form, construction, detail, and execution, described by the drawings and specifications without invalidating or rendering void this contract, and, in case of any difference in the expense, an addition to, or abatement from, the contract price shall be made. * * * And in case of any omission or addition to said building being required by said superintendent, the cost and expense thereof is to be agreed upon in writing, and such agreement is' to be signed by said parties of the second part _ and superintendent before the same is done or before any allowance therefor can be claimed; and in case of any failure so to agree, the same shall be completed upon the original plan. * * * The said parties of the first part agree and bind themselves, for and in consideration of the erection of said iron work as. áforesaid, to pay unto the parties of the [502]*502second part the sum of $7,500. Payments are to he made as the work progresses as follows: Upon monthly estimates furnished by the architect, and the balance of the money when the whole iron work is completed,” etc. (The italics are ours.)

In this action the plaintiffs sue for the reasonable value of materials furnished and work done under the foregoing contract, and also for the reasonable value of certain extra work. A statement of the materials furnished was filed with the petition, and it was claimed that they were of the reasonable value of $7,500, and of the two items of extra work, which it was averred the superintending architect had ordered, one was alleged to be worth $94.75 and the other $34.50, making a total of $7,629.25. Credits to the amount of $6,750 were admitted, leaving a balance of $879.25, for which a judgment was asked. The answer is a general denial. No instructions were asked or given. The jury returned a verdict for the full amount claimed, and the defendants have appealed.

The plaintiffs gave evidence which tended to prove that they furnished the materials called for in the contract according to the plans and specifications furnished to them by the superintending architect, but they seem to have conceded at the trial that the iron stairway of the building was improperly constructed in one particular, and hence the action was for the reasonable value of the materials and work, which the plaintiffs’ evidence tended to show was of the value stated. The chief matter of defense was that, after the contract was entered into, the architect so modified the original specifications to which the contract referred as to materially lessen the quantity of iron, thereby establishing a new contract price by which the plaintiffs’ recovery had to be limited, that is, the recovery could not exceed this however much in excess of it the evidence might [503]*503show the reasonable value of the work to be. Ahren v. Boyce, 19 Mo. App. 552; s. c., 26 Mo. App. 558. The evidence introduced by the plaintiffs on this branch of the case was to the effect that, before entering into the contract, they inspected certain plans for the building and some imperfect specifications which were then in the office of the architect; that at the time the contract was signed no such papers were attached to it, nor did the parties have them before them; that a few days afterward, and before the work was commenced, the architect handed to plaintiff Muller a set of specifications without any details, and that Muller under the directions of the architect prepared the necessary details which were submitted and approved by the architect, and thereupon the plaintiffs proceeded with and completed the work in accordance therewith. The evidence for defendants tended to prove that, at the time the contract was signed, there were in existence complete plans and specifications which had been adopted for the construction of the building, and that these were the plans and specifications which were referred to in the contract with the plaintiffs, and that subsequently the architect changed the specifications in certain particulars. The defendant Grillick was interrogated as to the difference in the weight of the iron required by the original specifications and that required by the specifications as modified and changed by the architect. The circuit court refused to allow the witness to testify for the reason that, in the opinion of the court, he did not have any accurate knowledge of the subject. The court also excluded the original plans and specifications, which the defendants offered in evidence. The defendants complain of both rulings.

There can be no question that the superintending architect had the power to deviate from the original [504]*504specifications without in any manner invalidating the contract between plaintiffs and defendants. The contract so provides in express terms. That some modifications or changes were made in the specifications seems to have been clearly established. Now, if these changes added to or abated from the original contract price, then a new contract price, so to speak, was established, and it became necessary to inquire as to this, for, as we have stated above, it was a limitation on the plaintiffs’ recovery. Therefore, the inquiry made of Grillick was proper, and, had he shown himself qualified to testify, the action of the court in excluding his estimates would have been erroneous. But he admitted that his estimate of the difference in the weight of the iron was a “mere guess,” which rendered it of no evidential value.

The defendants having introduced evidence tending to identify the plans and specifications produced by them as the original plans, etc., and to which reference was made in the contract, they were admissible in evideence for the purpose of determining the nature and extent of the changes made by the architect; and their exclusion is complained of as error. The record, however, shows that, although the court had previously ruled out these plans and specifications, it did subsequently admit evidence tending to show changes made in them by the subsequent plans and specifications and the nature of the changes. Hence it is not apparent how the defendants were prejudiced by the formal exclusion of these papers, when they got the benefit of that evidence for all practical purposes.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raftery v. Kansas City Gas Co.
169 S.W.2d 105 (Missouri Court of Appeals, 1943)
Nugent v. Armour Packing Co.
106 S.W. 648 (Supreme Court of Missouri, 1907)
Badaracco v. Badaracco
10 N.M. 761 (New Mexico Supreme Court, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
66 Mo. App. 500, 1896 Mo. App. LEXIS 96, Counsel Stack Legal Research, https://law.counselstack.com/opinion/muller-v-gillick-moctapp-1896.