Mullen v. Byers, Unpublished Decision (9-28-2001)

CourtOhio Court of Appeals
DecidedSeptember 28, 2001
DocketAccelerated Case No. 2000-T-0066.
StatusUnpublished

This text of Mullen v. Byers, Unpublished Decision (9-28-2001) (Mullen v. Byers, Unpublished Decision (9-28-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mullen v. Byers, Unpublished Decision (9-28-2001), (Ohio Ct. App. 2001).

Opinion

OPINION
Appellants, Chuck Byers and Byers Home Design, Inc. ("Byers"), appeal from the judgment of the Trumbull County Court, Eastern Division. After a bench trial, the court entered judgment in favor of appellees, Thomas and Beverly Mullen ("Mullen"), on their action for breach of contract and breach of implied warranty of workmanlike construction. Byers built a home for Mullen, completing it in November of 1997. The home subsequently developed water problems in the basement and problems with some roof shingles. The following facts are relevant to a determination of this appeal.

Mullen owned the lot on which the house was to be built. The contracted price for the construction of the home was $112,000. Drought conditions existed in the area for six to eight weeks prior to the beginning of excavation for the basement. Nevertheless, when Byers began the excavation, the excavated area immediately and continuously took on water, indicating a high water table or the presence of an underground spring nearby. Consequently, the excavation had to have water regularly pumped out of it until the internal and external drains were installed and the sump pump connected.

The original building plan for the basement anticipated that the ground, upon which the house was being built, was typical and normal, which is to say, relatively dry. The ground was not typical. It was unusually wet and sandy. Byers believed he could not deviate from the contract price, because he thought that Mullen was "maxed out" financially. Consequently, Byers did not suggest, recommend, or propose any alteration in the construction plan to address the presence of so much water. Byers did make a decision to "hold the house up out of the ground higher than usual." Byers also claimed he ordered double the normal amount of gravel installed, thirty-six inches instead of eighteen as required by the building code. Byers also claimed to have applied a coating of waterproofing cement to the exterior of the cement foundation blocks.

After moving in, Mullen complained to Byers about the basement being wet. Byers sent over an excavator who fixed a crushed drainpipe, but the water problem persisted. Then the basement floor developed a one-quarter inch crack, and a basement wall began to bow. Mullen also noticed that some of the roof shingles began to rise up, an indication that the nails securing them were lifting. Mullen filed suit for breach of contract and breach of implied warranty of workmanlike construction.

At trial, Mullen presented testimony from several witnesses. A landscaper testified that he attempted to dig a drainage ditch for the purpose of draining water away from the house. A general contractor testified regarding the problems with the roof shingles. Two individuals testified for Mullen regarding the home's foundation work. One had twenty years of experience in the basement waterproofing business, the other was a construction cost estimator with thirty years experience in the trade. On behalf of Byers, an excavator, who frequently worked for Byers and who repaired Mullen's drainpipe, testified. Byers also testified.

The trial court found that Byers was aware there was a water problem at the site due to the excessive amount of water present. The court found Byers took no corrective measures to effectively remedy the problem, which was certain to continue. The court found Byers did not properly install the footer drains. The court found Byers failed to properly construct the drainage system generally to insure proper drainage. The court also found Byers did not coat the basement walls to prevent seepage.

With regard to the bowed wall, the court found Byers either improperly constructed the wall or failed to properly back-fill materials along its foundation, thereby causing it to heave and crack. The court found the basement's cement floor was not properly installed, resulting in its cracking. The court found that some of the roof shingles were not installed in a workmanlike manner. The court assessed the following damages: $400 for the cost of the attempt to dig a drainage ditch away from the house; $7,500 for the cost of waterproofing the basement, and fixing the bowed wall and the cracked floor; and $1,000 to repair and re-nail the improperly seated roof shingles. From this judgment, Byers timely filed notice of appeal, assigning the following errors:

"[1]. The findings of fact and judgment entry in favor of the appellees dated March 27, 2000 is (sic.) against the manifest weight of the evidence and should be reversed.

"[2]. The trial court's assessment of damages in this matter was against the manifest weight of the evidence.

"[3]. The court improperly shifted the burden of proof to the appellants to prove that they were not negligent."

In Byers' first assignment of error, he argues that the trial court's conclusions as to whether the basement, the basement floor, the basement wall, and the roof shingles were installed in a workmanlike manner were against the manifest weight of the evidence.

When an appellate court reviews a civil judgment appealed from on the grounds the judgment is against the manifest weight of evidence, the court of appeals is guided by the presumption that the findings of the trier-of-fact were correct. Seasons Coal Co. v. Cleveland (1984),10 Ohio St.3d 77, 79-80. "Judgments supported by some competent, credible evidence going to all the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence." C.E. Morris Co. v. Foley Construction Co. (1978),54 Ohio St.2d 279, 280.

Byers argues that Mullen failed to put forth evidence establishing the workmanlike standard of care regarding the defects for which Mullen complained. Citing Floyd v. United Home Improvement Ctr. (May 23, 1997), Montgomery App. No. 16250, unreported, 1997 Ohio App. LEXIS 2180, Byers argues that merely establishing the existence of a defect is insufficient without showing that the defect resulted from the contractor's failure to use ordinary care. Byers argues that by failing to establish the standard of care, Mullen could not show that he failed to meet it. While his statement of law is correct, Byers is incorrect in his assertion that Mullen failed to put forth some competent, credible evidence regarding the workmanlike standard of care.

First, we note that the workmanlike standard of care is highly circumstantial, and it depends, among other things, on the inherent condition of the site upon which a structure is built. With respect to a builder's duty to complete a construction project in a workmanlike manner, the Supreme Court of Ohio set forth the following rule:

"A duty is imposed by law upon a builder-vendor of a real-property structure to construct the same in a workmanlike manner and to employ such care and skill in the choice of materials and work as will be commensurate with the gravity of the risk involved in protecting the structure against faults and hazards, including those inherent in its site. * * *" (Emphasis added.) Mitchem v. Johnson (1966), 7 Ohio St.2d 66, paragraph three of syllabus.

As Mitchem indicates, the circumstances dictate the standard of care, and the builder must use sufficient skill and care, and utilize the proper materials, to meet the gravity of the risks posed to a structure, including hazards posed which are inherent in the site of the structure.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jones v. Honchell
470 N.E.2d 219 (Ohio Court of Appeals, 1984)
State v. Prokos
631 N.E.2d 684 (Ohio Court of Appeals, 1993)
Floyd v. United Home Improvement Center, Inc.
696 N.E.2d 254 (Ohio Court of Appeals, 1997)
State v. Blankenship
657 N.E.2d 559 (Ohio Court of Appeals, 1995)
State v. Davis
607 N.E.2d 543 (Ohio Court of Appeals, 1992)
Moore v. McCarty's Heritage, Inc.
404 N.E.2d 167 (Ohio Court of Appeals, 1978)
McCray v. Clinton County Home Improvement
708 N.E.2d 1075 (Ohio Court of Appeals, 1998)
Mitchem v. Johnson
218 N.E.2d 594 (Ohio Supreme Court, 1966)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
Mullen v. Byers, Unpublished Decision (9-28-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/mullen-v-byers-unpublished-decision-9-28-2001-ohioctapp-2001.