Mueller v. Schmenger

28 Misc. 445, 59 N.Y.S. 189
CourtCity of New York Municipal Court
DecidedJuly 15, 1899
StatusPublished

This text of 28 Misc. 445 (Mueller v. Schmenger) is published on Counsel Stack Legal Research, covering City of New York Municipal Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mueller v. Schmenger, 28 Misc. 445, 59 N.Y.S. 189 (N.Y. Super. Ct. 1899).

Opinion

Schuchman, J.

The complaint alleges one cause of action as follows: “ That on or about May 6, 1895, the plaintiffs entered into an agreement with one, Fingerhut, for the performance of certain paint work in and about the store and premises known as Ho. 194 Third avenue, Hew York city, which premises were owned as a leasehold by the defendant and by him sublet for a term of years to said Fingerhut; that after part of the work had been done, said Fingerhut failed to pay therefor, and the plaintiffs refused to continue the work. That on or about June 13, 1895, the defendant agreed with the plaintiffs, that if plaintiffs would proceed and finish the said paint work, that he would pay the same. That plaintiffs, relying on that promise, proceeded with the said work for the defendant, and that there is now due plaintiffs the sum of $639.86,” for which judgment is asked. The answer is a general denial.

The proofs on the trial show that plaintiffs’ original contract for the paint work with Fingerhut was for the agreed amount of $925; that plaintiffs on this amount credited payments made by Fingerhut of $428, leaving a balance of $497, and then plaintiffs proved that, by special contracts made directly with the defendant, defendant owes them the sum of $75, for extra work done on the bar and transom, for $20, for coloring and flooring, and $45 for painting the front of the house, which three items amount to $143, [446]*446which added to the balance due on the above contract price, to-wit. $497, makes $640, for which, together with interest, the plaintiffs recovered. Thus it appears that plaintiffs were allowed to recover in this action on those three separate items which constituted separate causes of action without the shadow of an allegation in the complaint. It is true the defendant denied having given the orders for those three separate items, and apparently claimed no surprise, but plaintiffs never moved for an amendment of their pleadings, and none was made, nor was there a motion made to conform the pleading to the proof; so that we have herein a recovery by plaintiffs of $143, for three different and distinct causes of action, without any allegation thereof in the plaintiffs’ pleading. I know of no rule of pleading or practice whereby a suit can be brought on allegations of a certain contract and a recovery had on that contract and three others besides, not mentioned at all. Day v. Town of New Lots, 107 N. Y. 148; Romeyn v. Sickles, 108 id. 650. The plaintiffs presented their case on the theory, as alleged in their complaint, that the contract price made with Fingerhut was $925. That part of the work stipulated for in that contract was performed for Fingerhut; that the balance was performed under an agreement with the defendant herein, and that, therefore, the defendant was liable for the whole contract price less the payments made by Fingerhut. This does not seem to be correct. The defendant would only be liable for the value of the paint work done for him by his express order and contract. He would not be liable for that part of the work that was done under the contract with and for Fingerhut. There is no proof whatsoever in the case, or in the evidence, what the value was of the work that was done under the order and contract with the defendant, nor is there any proof what the value of the work was that had been done under the contract with and for Fingerhut.

For the reasons given, we think that justice requires a reversal of the judgment and a new trial, on which the parties litigant hereto can present their claims and defenses in a more proper and better defined manner.

Judgment and order appealed from reversed and a new trial ordered, with costs and disbursements to the appellant to abide the event.

Coitlatí and Hasoall, JJ., concur.

Judgment and order reversed and new trial ordered, with costs to appellant to abide event.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Day v. . Town of New Lots
13 N.E. 915 (New York Court of Appeals, 1887)

Cite This Page — Counsel Stack

Bluebook (online)
28 Misc. 445, 59 N.Y.S. 189, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mueller-v-schmenger-nynyccityct-1899.