Mueller v. Board of Education

11 Ohio N.P. (n.s.) 113
CourtCourt of Common Pleas of Ohio, Hamilton County
DecidedMarch 15, 1911
StatusPublished

This text of 11 Ohio N.P. (n.s.) 113 (Mueller v. Board of Education) is published on Counsel Stack Legal Research, covering Court of Common Pleas of Ohio, Hamilton County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mueller v. Board of Education, 11 Ohio N.P. (n.s.) 113 (Ohio Super. Ct. 1911).

Opinion

Bromwell, J.

Decision on motion for instructed verdict.

The petition in this case is as follows:

“Plaintiff states that he is the proprietor of the Standard Marble Works and engaged in the business of cutting, polishing and setting marble and doing general marble contracting work [114]*114in the city of Cincinnati, and that the defendant is the board of education of the school district of the city of Cincinnati, a body corporate existing under the laws of the state of Ohio.
“Plaintiff states that on March 2, 1908, the plaintiff and defendant entered into a contract, whereby the plaintiff agreed to furnish and set the marble work, mosaic and tile floors, wall tiling, cement tile floors and Terrazzo floors in the new Hughes High School building in the city of Cincinnati, said material to be furnished and work to be done in accordance with certain plans ,and specifications which were on file in the office of the superintendent of buildings of said board of education, and the defendant agreed to pay plaintiff for said work the sum of $37,-297; a copy of said contract is hereto attached, marked ‘ Exhibit A.’ and made part hereof; said contract being made in accordance with the statutes made and provided.
“Plaintiff states that at the time of making his estimate for the marble work on said building the defendant furnished him with a set of blue print plans which the defendant represented to be the blue prints ,and exact copies of the said plans on file in the office of the superintendent of buildings; that plaintiff paid the defendant for said blue prints, based his estimates thereon, and relying upon said representation, signed said contract and thereafter performed said contract in strict accordance with the terms thereof.
“Plaintiff further states that when said building was nearing completion a dispute arose between the plaintiff and defendant as to whether the plans and specifications to the plaintiff called for the making, and erection of twenty-eight marble shields in the main hallway of said building and that the defendant contended that said marble shields were called for by said plans and specifications and required to be furnished by the plaintiff under his contract; the plaintiff refused to make and erect said shields, claiming that they were not called for by the plans and specifications furnished him and were not part of his contract, and that if such shields were erected they would be an 'extra’ to and in addition to said contract. Plaintiff says that the doing of said work was a case of urgent necessity and for the security and protection of said building. ' It was thereupon agreed between the plaintiff and defendant that the plaintiff should make and erect said twenty-eight marble shields at $175 per shield, the defendant’s liability therefore as an 'extra’ to said contract to be determined by a suit at law and to depend upon whether said marble shields were called for by the plans’ and specifications furnished to the plaintiff.
[115]*115“Plaintiff states that said, marble shields were not called for by the plans and specifications furnished him and were not a part of or included in his original contract.
“Plaintiff further states that after making said supplementary agreement with defendant he made and erected said marble shields to the satisfaction of the defendant, and that there is due him for said work the sum of $4,900, with interest thereon from the 23d day of July, 1910, and that sum is the reasonable value thereof. ”

The amended answer and cross-petition admits:

First, that plaintiff is the proprietor of the Standard Marble Works and is engaged in doing general marble contracting in this city.

' Second, that defendant is a city school district uhder the laws of this state.

Third, that on March 2, 1908, plaintiff and defendant entered into the so-called contract set out in paragraph two in said petition, and that defendant agreed to pay the sum of $37,297 for the said work in accordance with the terms of the so-called contract.

Fourth, that at the time of making the estimate of plaintiff for said work, certain blue prints covering the subject of plaintiff’s so-called contract were on file in the office of the superintendent of buildings of the defendant board.

Fifth, that plaintiff furnished and placed in position in said new Hughes High School building the marble shields referred to; and,

Sixth, that the reasonable value of the shields and the setting thereof was $175 each, or a total of $4,900.

The answer then sets up its separate defenses as follows:

' First, that said shields were included in, and were called for by the plans and specifications of the original contract of March 2, 1908, and were furnished and set in accordance therewith, and have been fully paid for by the defendant.

Second, that in ease of any doubt as to whether said shields were included in the original contract, such doubt was to be finally and conclusively left to the decision of the architect, and {hat the Tatter did decide {hat they were so included.

[116]*116Third, that it was provided in said contract that all disputes or doubts concerning the construction or performance of said contract should be submitted to and determined by the superintendent of buildings of the defendant, and that said superintendent decided that said shields were included in said contract, and that his decision was final and conclusive upon the parties.

Fourth, that because said original contract has been fully performed and because said shields were included in said original contract, the subsequent agreement as to the construction and setting of the said shields at the price of $175 each, or a total of $4,900 was without consideration.

Fifth, that if the furnishing and setting of said shields were not included in said original contract, the second agreement is void because the statutory requirements provided for in Section 7623 of the General Code were not carried out, namely:

(а) Said board did not advertise for a period of four weeks for bids in any newspaper of general circulation in the district.

(б) That the bid did not contain the names of every person interested therein.

(c) That said bid was not accompanied by the guarantee required by statute.

(d) That there was no separation in said bid of the amounts charged for labor and the amount charged for material.

Sixth, that by reason of the failure to separately specify the amounts to be paid for labor and those for material the contract was void.

At the close of the evidence for the plaintiff the defendant made a motion for an instructed verdict in behalf of defendant. It is this motion that we now have to pass upon.

While a considerable amount of time has been given to the case and a large number of witnesses have testified, the questions which have to be settled are few and simple.

For the purposes of this decision I shall consider only the first, fourth and fifth defenses.

It is evident that if the shields were included in the original contract as part of the marble work on which the plaintiff bid and for which he. was paid in full, any-, subsequent contract, of

Free access — add to your briefcase to read the full text and ask questions with AI

Cite This Page — Counsel Stack

Bluebook (online)
11 Ohio N.P. (n.s.) 113, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mueller-v-board-of-education-ohctcomplhamilt-1911.