IN THE COURT OF APPEALS OF THE STATE OF MISSISSIPPI
NO. 2023-WC-00494-COA
MUELLER INDUSTRIES, INC. AND APPELLANTS STONINGTON INSURANCE COMPANY
v.
SHANNON WAITS APPELLEE
DATE OF JUDGMENT: 03/22/2023 TRIBUNAL FROM WHICH MISSISSIPPI WORKERS’ COMPENSATION APPEALED: COMMISSION ATTORNEY FOR APPELLANTS: DANIEL P. CULPEPPER ATTORNEY FOR APPELLEE: YANCY B. BURNS NATURE OF THE CASE: CIVIL - WORKERS’ COMPENSATION DISPOSITION: REVERSED AND REMANDED - 05/13/2025 MOTION FOR REHEARING FILED:
EN BANC.
EMFINGER, J., FOR THE COURT:
¶1. In an order dated March 22, 2023, the Mississippi Workers’ Compensation
Commission (Commission) ordered Mueller Industries Inc. and Stonington Insurance
Company (collectively Mueller) to pay Shannon Waits his remaining workers’ compensation
benefits in the form of a lump sum payment in the amount of $33,411.11. Mueller appealed
that decision.
FACTS AND PROCEDURAL HISTORY
¶2. The facts and procedural history in this case are extensive, as they stem from a claim
that arose on November 14, 2014, when Waits sustained a work-related injury to his right
arm and shoulder. Records show that Waits had surgery on his shoulder and was out of work for several months. Records filed with the Commission show that Mueller paid Waits the
maximum weekly amount for temporary total disability (TTD) benefits beginning the week
of November 15, 2014, through November 21, 2014. Those payments were suspended when
Waits returned to work, with restrictions, after he reached maximum medical improvement
(MMI) on May 7, 2015.1 The last TTD payment was made on May 1, 2015. The “Notice of
Suspension of Payment” filed with the Commission on May 5, 2015, also states:
Reason compensation was suspended: RTW light duty 4/25/15. IW Overpaid from 4/27/15-5/1/15-credit will be taken against PPD. Average weekly wage at time of injury was $826.29. Employee returned to work at weekly wage of $826.29.
A “Supplemental Agreement as to Compensation” was filed on June 9, 2015, which stated
in part:
TEMPORARY PARTIAL: Employee first became, or again became temporarily partially disabled on 5/11/2015, and is now receiving benefits at the rate of 2/3 of the decrease in wage earning capacity and continuing until further notice.[2]
A form filed with the Commission on July 14, 2015, showed the following decision:
PERMANENT PARTIAL: Employee is entitled to compensation for the 25% loss of upper extremity, commencing on 5/5/2015, at the rate of $454.42 per week, and continuing for a period of 50 weeks.[3]
(Emphasis added). The record on appeal shows that Waits worked at Mueller and earned
wages until about November 15, 2015, when his employment was terminated for reasons
1 Waits was determined to have reached MMI on at least three different occasions in this case: May 7, 2015; February 13, 2017; and August 15, 2022. 2 These payments will be referred to as TPD payments. 3 These payments will be referred to as PPD payments.
2 unrelated to his injury.
¶3. On January 28, 2016, Waits filed a “petition to controvert” with the Commission.
Later, on April 5, 2016, Waits filed a “Motion to Substitute Orthopedic Surgeon and Other
Relief.” In this motion, Waits contends that his previous doctor failed to properly assess his
disability and asked that TTD benefits be initiated “retroactively.” After a telephonic hearing,
the administrative judge (AJ) issued an order on April 29, 2016,4 that provided, in part:
Due to the severity of the injury and the fact that it is disabling by its very nature, employer/carrier shall reinstate temporary total disability benefits retroactively and shall continue said benefits until such time as claimant’s required treatment has been completed and maximum medical improvement has been reached.
(Emphasis added). While the order used the word “retroactively,” it does not state retroactive
to any date. On June 6, 2016, Waits filed a “Motion to Enforce Order Awarding Past Due
Indemnity Benefits” in which he maintained that Mueller had made no TTD payments in
response to the April 29 order and asked that a hearing date be set for this motion. On July
12, 2016, Waits filed another motion to enforce the order, stating that TTD payments “had
been paid through June 16, 2016.” In this motion, Waits asked for past due payments with
penalties and interest. On September 23, 2016, a telephonic hearing was conducted on this
4 This was the first “award” by an AJ or the Commission. Placing Waits on TTD arguably should have stopped Mueller’s voluntary TPD and PPD payments since the AJ’s order did not address those payments. See Walls v. Hodo Chevrolet Co., 302 So. 2d 862, 867-68 (Miss. 1974) (“However, it is also the general rule that a claimant may not pyramid benefits and receive in excess of the maximum weekly benefits provided by statute during any one period.”); Cockrell Banana Co. v. Harris, 212 So. 2d 581, 585 (Miss. 1968) (“In dealing with another vital problem in the field of workmen’s compensation law, this Court has said that permanent partial disability payments do not begin until the claimant has attained maximum medical recovery.”).
3 motion. Pursuant to an order dated September 30, 2016, the AJ found that the failure to pay
TTD by Mueller had been inadvertent and ordered timely payments be made in the future.
The order waived the payment of penalties and interest.
¶4. After a hearing on the petition to controvert on June 14, 2017, the AJ entered an order
on July 24, 2017, requiring Mueller to pay compensation benefits to Waits as follows:
1. Commencing on November 13, 2014 and concluding on February 13, 2017, temporary total disability benefits are applicable with proper credit to be given for any and all monies, wages or benefits previously paid to claimant during the aforementioned time frame.5
2. Permanent partial disability benefits are to be made in the amount of $454.42 per week, and are to conclude after a period of two hundred (200) weeks pursuant to Miss. Code Annot. Section 71-3-17(c)(1) and illustrative of one hundred percent (100%) industrial loss of use relative to the right upper extremity.
3. Penalties and interest, if applicable, in accordance with Miss. Code Annot. Section 71-3-37(5)(6).
4. Provide medical services and supplies to the claimant as required by the nature of the claimant’s injury and the process of his recovery therefrom pursuant to Mississippi Code Annotated Section 71-3-15 and governed by the Fee Schedule.
Mueller appealed the AJ’s decision to the full Commission, which affirmed and adopted the
decision by order entered on February 8, 2018.
5 At issue on appeal is how payments made by Mueller to Waits during the period of time between May 7, 2015, and November 15, 2015, should be credited. During this period, Waits was back at work and earned wages; therefore, he was not eligible for TTD. See Flowers v. Crown Cork & Seal USA Inc., 167 So. 3d 188, 193 (¶15) (Miss. 2014). As noted in Flowers and by a previous filing by Mueller with the Commission noted above, Waits was entitled only to TPD during this period. We will address this conflict below. The order also did not address how to give Mueller “proper credit” for payments it had already made to Waits.
4 ¶5. Mueller appealed and challenged the finding that Waits was entitled to 100% PPD
and that the administrative judge showed partiality toward Waits. Mueller Ind. Inc. (Mueller
I) v. Waits, 283 So. 3d 1137 (Miss. Ct. App. 2019). This Court found that the Commission’s
decision was supported by substantial evidence and affirmed the full Commission’s
decision.6 Id.
¶6. After the July 24, 2017 order was affirmed in Mueller I, Waits filed an application
with the Commission for a lump sum payment on November 18, 2019. Over the next several
years, both Mueller and Waits made multiple filings with the Commission in an effort to have
the Commission calculate and approve a lump sum payment for all the remaining benefits
owed by Mueller to Waits pursuant to the July 24, 2017 order. On May 19, 2021, the
Commission entered its “Order Regarding Lump Sum Computation and Motion to Exclude.”
In this order, the Commission found that Mueller had “overpaid by $12,915.78 the amount
owed to [Waits] pursuant to the July 24, 2017, Order of Administrative Judge and owe no
further indemnity benefits under the Order.” (Emphasis added).
¶7. The next day, on May 20, 2021, Waits filed an “Emergency Motion to Re-open Claim
and/or Motion to Reconsider Order Regarding Lump Sum Order and Motion to Exclude.”
In this motion, Waits maintained that the Commission’s calculations were based upon
mistakes of fact, and he questioned the Commission’s calculation of benefits due after an
October 16, 2019 recurrence of his shoulder injury, which resulted in a new period of TTD.
In reference to this motion, Waits stated that the calculation performed by an actuary (which
6 We take judicial notice of documents in the appellate record in Mueller I. See Badger v. State, 290 So. 3d 377, 381 (¶14) (Miss. Ct. App. 2020).
5 the Commission referenced in finding that Mueller had overpaid his benefits) had not been
disclosed, and Waits asked that it be made a part of the record.7
¶8. A telephonic hearing was conducted on June 8, 2021, on this motion and others. As
a result of that hearing, the Commission entered an “Order Granting Motion to Re-Open
Claim and Motion to Compel Medical Treatment” on June 10, 2021. In this order, as a result
of the October 16, 2019 recurrence of his shoulder injury, Waits was found to be temporarily
totally disabled from that date and continuing until he is found to be at MMI. The order
required Mueller to pay Waits for TTD at the rate of $454.42 per week from October 16,
2019, until MMI was reached. The order noted that the parties had agreed to wait until Waits
reached MMI to pursue Waits’ motion to re-open the claim as to the lump sum payment
pursuant to the July 24, 2017 order. However, Waits did not wait to reach MMI. Instead, the
very next day, on June 11, 2021, he filed a “Supplemental Motion to Reconsider Lump Sum
Order.”8 On August 26, 2022, Mueller filed a “Notice of Suspension of Payment,” noting that
the last payment Mueller made to Waits for TTD was on August 14, 2022, because Waits
reached MMI on August 15, 2022.
¶9. In response to Waits’ motion to reconsider the order regarding a lump sum payment,
on March 22, 2023, the Commission entered the order that is the subject of this appeal. The
7 We do not find this calculation in the record on appeal. 8 There were a number of motions, responses to motions, replies to motions and attachments of letters and emails filed after this supplemental motion was filed. It got to a point where both counsel accused the other of unethical conduct. While most of these pleadings are not helpful to the resolution of this appeal, there is some information contained in these filings that will be useful in our analysis below.
6 order states that all payments made by Mueller to Waits prior to October 16, 2019, whether
designated as TTD, TPD, or PPD, “shall be applied to the amounts owed pursuant to the July
24, 2017, Order.”9 The Commission then ruled:
Based on this Order and Mueller and Stonington’s November 11, 2022 payment ledger, the Commission asked an actuary to compute the lump sum amount, including penalties and interest, due to Waits based on the July 24, 2017, Order of Administrative Judge. The actuary’s computations show that as of March 13, 2023, Mueller and Stonington owe $33,411.11, and we order payments of that amount by Mueller and Stonington to Waits. Payment of that amount within fourteen days of the date of this Order will complete Mueller and Stonington’s obligation for payment of indemnity benefits, interest and penalties pursuant to the July 24, 2017, Order.
(Emphasis added).
¶10. Aggrieved, Mueller filed its notice of appeal on April 20, 2023. After the initial
briefing was complete, this Court determined that the record on appeal was incomplete and,
on its own motion, ordered the Commission Secretary to supplement the appellate record
with the “November 11, 2022 payment ledger and the actuary’s computations referenced in
the final paragraph of the Commission’s March 22, 2023 order.”10 This Court also ordered
that upon “the Secretary’s filing of the supplemental record with this Court’s clerk, the
employer/carrier [should] within thirty days file with this Court a true calculation by a
certified public accountant as required by [Mississippi Rule of Appellate Procedure] 14(c).”
After all the supplemental materials were filed, this Court directed the parties to file
9 In this order, the Commission also vacated the May 19, 2021 order wherein the Commission ruled that Mueller had overpaid Waits by $12,915.78 and owed no further benefits under the July 24, 2017 order. 10 This calculation was not disclosed to the parties prior to the Commission’s ruling, just as the calculation relied upon for the May 19, 2021 ruling had not been disclosed.
7 supplemental briefs in response to the supplemental record filed on May 10, 2024, and the
Rule 14(c) calculations “as they relate to the Commission’s $33,411.11 lump sum award to
the claimant.” In its supplemental brief, Mueller asserts that the lump sum amount ordered
by the Commission was incorrect and that Mueller should be allowed credits for “all monies,
wages or benefits previously paid to the Claimant.” Mueller further requests that this Court
remand the matter back to the Commission with instructions to determine the calculation
while taking into account credit for “all monies, wages or benefits” previously paid to Waits.
Also, during the pendency of this appeal, Waits filed a “Motion to Dismiss Frivolous
Appeal.” Waits’ motion will be considered along with the merits of the case below.
STANDARD OF REVIEW
¶11. In Clear River Construction Co. v. Chandler ex rel. Chandler, 926 So. 2d 273, 275
(¶¶9-10) (Miss. Ct. App. 2006), this Court held:
An appellate court must defer to an administrative agency’s findings of fact if there is even a quantum of credible evidence which supports the agency’s decision. Hale v. Ruleville Health Care Center, 687 So. 2d 1221, 1224 (Miss. 1997). “This highly deferential standard of review essentially means that this Court and the circuit courts will not overturn a Commission decision unless said decision was arbitrary and capricious.” Id. at 1225; Georgia Pacific Corp. v. Taplin, 586 So. 2d 823, 826 (Miss. 1991). This court will overturn a commission decision only if there has been an error of law. Id.
We do not sit as triers of fact; that is done by the Commission. South Central Bell Telephone Co. v. Aden, 474 So. 2d 584, 589 (Miss. 1985). We do not review the facts on appeal to determine how we would resolve the factual issues were we the triers of fact, rather our function is to determine whether the factual determination made by the Commission is supported by substantial credible evidence. Id.
ANALYSIS
8 ¶12. The actions and inactions of the parties and the Commission, over the course of time,
have all worked together to create a Gordian knot that we doubt Alexander the Great could
remedy with his sword. The confusion created by the changing circumstances in this case is
reflected in the Commission order that is the subject of this appeal. In this order, the
Commission attempts to retrospectively identify how all payments made by Mueller should
be classified (either TTD, TPD, or PPD) and to calculate the lump sum payment due. But
first, the Commission notes in its order:
The parties cited scant, if any, relevant authority to support their positions, and our research did not reveal any guidance in statutes, case law, or the Commission’s rules other than the general proposition that “The Commission shall have full power and authority to determine all questions relating to the payment of claims [for] compensation.” Miss. Code Ann. § 71-3-47. Because there is no specific guidance to help decide this issue, our decision is based on what we think is logical and makes sense, what we perceive to be the parties’ intent at the time the payments were made, and what will cause the least problems as the claim progresses to a resolution.
(Emphasis added). In any event, in an effort to move toward a resolution of the issues
presented by this appeal, we start with the basics.
¶13. The primary purposes of the Mississippi Workers’ Compensation Law were set forth
by the Legislature in Mississippi Code Annotated section 71-3-1(3) (Rev. 2021) as follows:
The primary purposes of the Workers’ Compensation Law are to pay timely temporary and permanent disability benefits to every worker who legitimately suffers a work-related injury or occupational disease arising out of and in the course of his employment, to pay reasonable and necessary medical expenses resulting from the work-related injury or occupational disease, and to encourage the return to work of the worker.
(Emphasis added). In order to comply with the stated goal of providing timely benefits to
injured workers, the law is based upon employers and their insurance carriers making
9 voluntary payments as required in Mississippi Code Annotated section 71-3-37 (1)-(2) (Rev.
2021):
(1) Compensation under this chapter shall be paid periodically, promptly, in the usual manner, and directly to the person entitled thereto, without an award except where liability to pay compensation is controverted by the employer.
(2) The first installment of compensation shall become due on the fourteenth (14th) day after the employer has notice, as provided in Section 71-3-35, of the injury or death, on which date all compensation then due shall be paid. Thereafter, compensation shall be paid in installments, every fourteen (14) days, except where the commission determines that payment in installments should be made at some other period.
(Emphasis added). As can be seen, there is an expectation that employers will make
compensation payments directly to the injured employee in cases where the injury is clearly
covered under the act. The Commission should receive timely notice of an injury, Miss. Code
Ann. § 71-3-67 (Rev. 2021), notice of payment of compensation and timely notice of any
suspension of payments. Miss. Code Ann. § 71-3-37(3). In most cases, these payments are
made without an AJ or the Commission becoming involved. However, if the employer wishes
to challenge liability for an injury or the employee wishes to challenge a decision of the
employer as to the provision of benefits, either side can file a petition to controvert, and the
Commission will decide the disputed matters.
¶14. This case started out like most others, with voluntary payments by Mueller. A “First
Report of Injury or Illness” was filed with the Commission on November 17, 2014, wherein
the Commission was advised that Waits had suffered a workplace injury on November 14,
2014. On December 8, 2014, a “Notice of First Payment of T.T.D. Benefits” was filed,
10 noting that Waits was paid $454.42 on November 20, 2014. Then, on May 5, 2015, a “Notice
of Suspension of Payment” was filed. This form advised the Commission and Waits that the
last payment to Waits of TTD was made on May 1, 2015, because Waits had returned to
work on light duty on April 27, 2015. It is clear that Waits, or Mueller’s insurance carrier,
had provided Mueller with the note from his physician dated May 7, 2015, that stated Waits
had reached MMI and was released to return to work on light duty on May 12, 2015.11 On
June 9, 2015, Mueller filed a “Supplemental Agreement as to Compensation,” indicating that
beginning on May 11, Waits would receive TPD as provided by law. The final “voluntary”
act by Mueller (before the Commission became involved in the case) was the filing of a
second “Supplemental Agreement as to Compensation” wherein Mueller agreed to pay Waits
PPD at the rate of $454.42 per week for fifty weeks. Shortly after Waits’ employment with
Mueller was terminated for reasons other than his injury, Waits filed a “Petition to
Controvert” on January 28, 2016.
¶15. At this point, Mueller had paid Waits TTD payments of $454.42 from the date of his
injury until he returned to work. Mueller had then agreed to pay Waits TPD payments after
he returned to work, because, as noted above, he was no longer eligible for TTD payments.
However, while it is clear that Waits earned wages after he returned to work, we cannot
determine that TPD payments were properly calculated, pursuant to Mississippi Code
Annotated section 71-3-21 (Rev. 2021), and paid. Neither the records provided by Mueller
nor the Commission are clear on this point. Apparently, Mueller did not file a form with the
11 This note was attached to later pleadings.
11 Commission indicating that it had suspended TPD payments when Waits was terminated. We
must also note that Mueller had begun paying Waits PPD benefits at the rate of $454.42 per
week and that no form was filed indicating that PPD payments were suspended. Ledgers filed
by Mueller show that it completed the “voluntary” payment of the original fifty weeks of
PPD on May 4, 2016; however, Mueller filed no form with the Commission indicating that
such final payment had been made.
¶16. All of this occurred before the AJ’s April 29, 2016, order placing Waits on TTD and
before the AJ ruled on Waits’ Petition to Controvert on July 24, 2017. This award differed
from how Waits’ disability was treated by Mueller in making voluntary payments. The order
provided that Waits was entitled to receive TTD payments for the entire period beginning
November 13, 2014, and concluding on February 13, 2017. This conflicts with Mueller’s
supposed “voluntary” payment of TPD for the period of time between May 7, 2015, and
November 15, 2015. However, the AJ’s order also required that “proper credit to be given
for any and all monies, wages or benefits previously paid to claimant during the
aforementioned time frame.” What constitutes “proper credit” under these circumstances is
the issue that must be resolved in this appeal.12
12 The AJ’s order also addressed Waits’ permanent disability. While “voluntary” payments by Mueller were based upon a permanent 25% loss of use of Waits’ right upper extremity, the AJ found that Waits suffered a “100% industrial loss of use relative to the right upper extremity.” This changed the period of PPD payments from 50 weeks to 200 weeks, but the amount of the weekly benefit remained the same. There does not seem to be any argument challenging that finding in this appeal. In Mueller I, Mueller did challenge the finding that Waits had suffered a 100% industrial loss of use. This Court affirmed the full Commission’s adoption of the AJ’s finding in that regard. Credit for payments made before the Commission order and the designation of the period of TTD were not raised by the parties or addressed in Mueller I.
12 ¶17. We recognize that ultimately, the Commission has the authority to determine what
benefits a worker may be entitled to receive. In Keys v. Military Department Gulfport, 345
So. 3d 1206, 1210 (¶13) (Miss. Ct. App. 2022), this Court stated:
Additionally, we find it beneficial to recognize that employers and carriers do not have the authority to classify the type of compensation benefits a claimant receives; only an AJ and the Commission have the authority to classify the degree of disability and the claimant’s compensation benefits. See Cockrell Banana Co. v. Harris, 212 So. 2d 581, 585 (Miss. 1968) (“Naturally, neither the date of maximum medical recovery nor the determination of the percentage of apportionment are questions for determination by the employer or carrier.”). The record indicates that the employer elected to begin making indemnity benefit payments to the claimant before the AJ had officially determined the claimant’s degree of disability. . . . Notably, the employer’s prompt and voluntary payment of indemnity benefits was well-intentioned, and we find this action meritorious; our ruling is not intended to discourage such actions in the future.
The instant appeal again presents the problem that is created when the encouraged, prompt,
and voluntary acts of the employer are later placed in conflict with the Commission’s
ultimate decision as to benefits.
¶18. On appeal, particularly in its supplemental briefing, Mueller argues that after
reviewing all the supplemental records produced by the Commission, Mueller was not given
proper credit for the salary payments it made during the time period that Waits returned to
work after reaching MMI on May 7, 2015, until his termination in November 2015. Mueller
argues that at the same time Waits was receiving a salary during this period, he was also
receiving PPD payments. On appeal, Mueller focuses on the classification of and credit
given for payments made by Mueller to Waits during the approximate six-month period
between May and November of 2015 while Waits was working for Mueller. Mueller argues
13 that it should be given “dollar for dollar” credit for actual earnings by Waits during the time
the 2017 order stated that he was temporarily totally disabled. In the alternative, Mueller
suggests that if this Court finds that Waits was not totally disabled during that period, we
should remand for the Commission to make a proper calculation of his temporary partial
disability. Waits contends that the full Commission’s March 22, 2023 order should be
affirmed.
¶19. The conflict is whether Waits was temporarily totally disabled during this period as
stated in the July 24, 2017 order, or whether Waits was temporarily partially disabled because
he had returned to work and actually earned wages during this period. The parties now agree
that Waits actually earned wages during the period in question.13 In Flowers v. Crown Cork
& Seal USA Inc., 167 So. 3d 188, 191-92 (¶12) (Miss. 2014), the supreme court explained:
“Disability,” as defined by the Mississippi Workers’ Compensation Act, is the “incapacity because of injury to earn the wages which the employee was receiving at the time of injury in the same or other employment, which incapacity and the extent thereof must be supported by medical findings.” Miss. Code Ann. § 71-3-3(i) (Rev. 2011). The Act categorizes disabilities by duration as either temporary or permanent, and by degree as either partial or total. See Miss. Code Ann. § 71-3-17 (Supp. 2013). “Temporary disability, whether total or partial, has reference to the healing period following injury, . . . until such time as the employee reaches the maximum benefit from medical treatment[.]” Triangle Distrib. v. Russell, 268 So. 2d 911, 912 (Miss. 1972) (citation omitted). After that point, any lingering disability is considered permanent. See McGowan v. Orleans Furniture, Inc., 586 So. 2d 163, 168 (Miss. 1991) (citing A. Larson, The Law of Workmen’s Compensation § 57.12(c), at 10–22 to 10–29 (1989)).
(Emphasis added). The first issue to be resolved is whether Waits had reached MMI before
13 The full Commission decided in its May 19, 2021 order that the payments Mueller made to Waits were earned and that TPD benefits should have been paid.
14 going back to work with Mueller. This was an issue that Waits contested in his petition to
controvert. The AJ’s first award in the April 29, 2016 order placed Waits on TTD and made
no mention of Dr. Van Osten’s MMI determination. The AJ’s July 24, 2017 order recognizes
that Dr. Van Osten placed Waits at MMI on May 7, 2015, and released him to return to work
on May 12, 2015; however, the order did not make the finding that Waits reached MMI on
that date. Instead, the order placed Waits at MMI on February 13, 2017. That was clearly the
basis for placing Waits on TTD for the entire period.
¶20. However, under the cases we cite here, a person cannot be temporarily disabled, either
totally or partially, if MMI has been achieved. Further, a person cannot be temporarily totally
disabled if he is back at work and earning wages to some degree, regardless of whether MMI
has been reached. Assuming the AJ rejected Dr. Van Osten’s finding that Waits had reached
MMI, then, since Waits was back at work and earning wages, he should have been placed
at TPD pursuant to Howard Industries Inc. v. Robinson, 846 So. 2d 245, 253 (¶21) (Miss. Ct.
App. 2002), where this Court reasoned:
“Temporary disability, whether total or partial, has reference to the healing period following injury; it begins with the disabling injury and continues until such time as the employee reaches the maximum benefit from medical treatment, or differently expressed, it is a condition which exists until the injured employee is cured or is as far restored as the permanent character of his injuries will permit.” Triangle Distributors v. Russell, 268 So. 2d 911, 912 (Miss. 1972) (emphasis added). Russell holds that the period of temporary disability is not necessarily a period of total disability. Whether total or partial, temporary disability ends when the worker reaches maximum benefit from medical treatment. Id. at 912-13. Retaining substantial wage earning capacity and being returned by a physician to work while the healing process continues constitutes a temporary partial disability, not a total one. While temporarily and partially disabled, the injured worker is entitled to two-thirds of the difference between his average weekly
15 wages before the injury and his earning capacity during the period “in the same or other employment . . . .” Miss. Code Ann. § 71-3-21 (Rev. 2000).
(Emphasis added). According to the appellate record, the Commission took the position, as
early as 2020, that Waits was actually at TPD during the period he earned wages from
Mueller from May to November of 2015. The method for calculating TPD benefits is set
forth in section 71-3-21:
In case of temporary partial disability resulting in decrease of earning capacity, there shall be paid to the injured employee sixty-six and two-thirds percent (66-2/3%) of the difference between the injured employee’s average weekly wages before the injury and his wage-earning capacity after the injury in the same or other employment, subject to the maximum limitations as to weekly benefits as set up in this chapter, payable during the continuance of such disability but in no case exceeding four hundred fifty (450) weeks or an amount greater than the multiple of four hundred fifty (450) weeks times sixty- six and two-thirds percent (66-2/3%) of the average weekly wage for the state.
¶21. Applying this statute, the Commission has observed that with respect to “wages
actually earned by the claimant” during periods of TPD, “[c]redit . . . is not the true issue.”
Hendershot v. Weiser Sec. Sys. Inc., No. 97-08017-G-0280, 1999 WL 377899, at *2-3 (Miss.
Workers’ Comp. Comm’n May 25, 1999) (emphasis added). Wages earned by the claimant
post-injury are relevant to the determination of TPD benefits because they are relevant to the
claimant’s “wage-earning capacity after the injury.” Miss. Code Ann. § 71-3-21. In other
words, they are relevant to the determination of the amount of TPD benefits payable to the
claimant, but they are not “credited” against that amount after it is determined.
¶22. In at least some prior cases, the Commission has calculated TPD benefits as simply
two-thirds of the difference between the claimant’s pre-injury average weekly wage and his
16 actual post-injury earnings. Hendershot, 1999 WL 377899, at *3; Hardaway v. Howard
Indus. Inc., No. 09-06933-K-7217, 2014 WL 1724245, at *3 (Miss. Workers’ Comp.
Comm’n Apr. 22, 2014). This method may not be correct in all cases because a claimant’s
“wage-earning capacity after the injury” is not necessarily the same as his actual post-injury
earnings. See Karr v. Armstrong Tire & Rubber Co., 216 Miss. 132, 137, 61 So. 2d 789, 791
(1953) (interpreting the term “wage-earning capacity thereafter” in a permanent partial
disability statute). However, in Hardaway, we affirmed the Commission’s decision, stating
that “in a case such as this one, the Commission may employ evidence of actual post-injury
earnings as a rebuttable presumption of post-injury wage-earning capacity. Either party may
rebut the presumption by relevant evidence showing that post-injury earnings are not an
accurate reflection of post-injury earning capacity.” Howard Indus. Inc. v. Hardaway, 191
So. 3d 1257, 1264 (¶18) (Miss. Ct. App. 2015) (citing Nissan N. Am. v. Short, 942 So. 2d
276, 280 (¶17) (Miss. Ct. App. 2006)).
¶23. Here, for the weeks that Waits earned wages working for Mueller from May 2015 to
November 2015, the Commission indicated that it calculated the TPD benefits that should
have been paid as two-thirds of the difference between Waits’ pre-injury average weekly
wage and his actual post-injury earnings. That may be a valid method for calculating Waits’
TPD benefits for those weeks, but we cannot review the Commission’s computations on the
present record. Therefore, we must reverse the order and remand this case to the Commission
to determine whether TPD benefits were “properly” calculated and credited during this
period.
17 ¶24. We also note that the voluntary payments begun by Mueller, prior to the
Commission’s involvement, and the award of benefits by the AJ and the Commission
resulted in periods of “overlapping” benefits. Mississippi Code Annotated section 71-3-13(1)
(Rev. 2021) limits the amount of weekly benefits:
Compensation for disability or in death cases shall not exceed sixty-six and two-thirds percent (66-2/3%) of the average weekly wage for the state per week, nor shall it be less than Twenty-five Dollars ($25.00) per week except in partial dependency cases and in partial disability cases.
Waits was not entitled to receive more than $454.42 in benefits per week. In Tucker v.
Bellsouth Tel. Inc., 130 So. 3d 96, 101 (¶16) (Miss. Ct. App. 2013), we held:
It is a well-established rule “that a claimant may not pyramid benefits and receive in excess of the maximum weekly benefits provided by statute during any one period.” Walls v. Hodo Chevrolet Co. Inc., 302 So. 2d 862, 867 (Miss. 1974) (citations omitted).
When the Commission placed Waits on TTD, it should have suspended the voluntary PPD
payments until Waits again reached MMI. Upon remand, in any week where Waits received
more than the maximum weekly benefit, Mueller should be credited in subsequent weeks for
any overage and should not be charged with penalties and interest for weeks where such
credits are applied.
¶25. Further, on May 19, 2021, the Commission ruled that Mueller owed no further
benefits under the July 24, 2017 order. That ruling stood until it was vacated by the March
22, 2023 order that is the subject of this appeal. We find that, as stated in that order, it is
“logical and makes sense” that Mueller not be charged with penalties and interest beyond
May 19, 2021, in the new calculation of any lump sum payment now due.
18 ¶26. On October 9, 2023, Waits filed a motion to dismiss the present appeal “as frivolous
and/or on for failure to ensure that the record was complete.” This Court on its own motion
ordered supplementation of the appeal record and ordered supplemental briefing, rendering
Waits’ motion moot. Because this Court reverses and remands this case back to the
Commission for a result consistent with this opinion, we deny Waits’ “Motion to Dismiss
Frivolous Appeal” and the relief requested within it.
CONCLUSION
¶27. After reviewing the record and all the supplements, we find error with the
Commission’s order granting Waits lump sum disability benefits in the amount of
$33,411.11. We therefore reverse the order and remand the case to the Commission to
calculate the total amount of benefits now owed to Waits, if any, and, consistent with this
opinion:
1. Determine whether TPD was properly calculated and credited for the weeks May 7, 2015-November 25, 2015; and
2. Determine whether Waits received more than the maximum weekly benefit in any week and should Mueller be credited for any overage and, therefore, not charged with penalties and interest for any such “pre-paid” amounts; and,
3. Mueller shall not be charged with penalties and/or interest after May 19, 2021, the date the Commission issued an order finding that Mueller owed Waits no further benefits.
The Commission should make its calculation available to the parties and should attach to its
calculation a spreadsheet that identifies the due date of each payment, the date it was actually
paid, and each payment as either TTD, TPD or PPD to show how the Commission arrived
19 at the final determination of the amount now due, if any.
¶28. REVERSED AND REMANDED.
BARNES, C.J., CARLTON AND WILSON, P.JJ., LAWRENCE, McCARTY, WEDDLE AND ST. PÉ, JJ., CONCUR. McDONALD, J., CONCURS IN PART AND DISSENTS IN PART WITHOUT SEPARATE WRITTEN OPINION. WESTBROOKS, J., CONCURS IN PART AND DISSENTS IN PART WITH SEPARATE WRITTEN OPINION, JOINED BY McDONALD, J.; McCARTY, J., JOINS IN PART.
WESTBROOKS, J., CONCURRING IN PART AND DISSENTING IN PART:
¶29. I concur with the majority that remand is necessary to address the impermissible
overlap of temporary total disability benefits and permanent partial disability benefits. See
Maj. Op. ¶24.
¶30. However, I would not order a reevaluation of Waits’s calculated temporary partial
disability benefits for the period of May 2015 to November 2015. See Maj Op. ¶23. The
statute looks at the “wage-earning capacity after the injury,” which here, the Commission
considered to be his actual post-injury earnings. See Miss. Code Ann. § 71-3-21 (Rev. 2021).
Although use of this approach has been affirmed, “[e]ither party may rebut the presumption
by relevant evidence showing that post-injury earnings are not an accurate reflection of post-
injury earning capacity.” See Maj. Op. ¶22 (quoting Howard Indus. Inc. v. Hardaway, 191
So. 3d 1257, 1264 (¶18) (Miss. Ct. App. 2015)).
¶31. Here, after extensive proceedings before the Commission and even after this Court
ordered supplementation of the record and supplemental briefing, we can still only say that
the Commission’s method “may be a valid method for calculating Waits’s TPD benefits for
those weeks, but we cannot review the Commission’s computations on the present record.”
20 Maj. Op. ¶23. The parties had ample opportunity to present evidence rebutting the
presumption of wage-earning capacity and to designate a record for appeal that would
facilitate review of this computation. Considering that, along with our standard of review,
I would defer to the Commission’s finding on this point of contention.
¶32. Therefore, I concur in part and dissent in part.
McDONALD, J., JOINS THIS OPINION. McCARTY, J., JOINS THIS OPINION IN PART.