MT Reed Const. Co. v. NICHOLAS ACOUSTICS, ETC.

379 So. 2d 308, 1980 Miss. LEXIS 1830
CourtMississippi Supreme Court
DecidedJanuary 23, 1980
Docket51562
StatusPublished
Cited by10 cases

This text of 379 So. 2d 308 (MT Reed Const. Co. v. NICHOLAS ACOUSTICS, ETC.) is published on Counsel Stack Legal Research, covering Mississippi Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
MT Reed Const. Co. v. NICHOLAS ACOUSTICS, ETC., 379 So. 2d 308, 1980 Miss. LEXIS 1830 (Mich. 1980).

Opinion

379 So.2d 308 (1980)

M.T. REED CONSTRUCTION COMPANY
v.
NICHOLAS ACOUSTICS & SPECIALTY COMPANY.

No. 51562.

Supreme Court of Mississippi.

January 23, 1980.

*309 Cox & Dunn, Vardaman S. Dunn, Jackson, for appellant.

Young, Scanlon & Sessums, Brad Sessums, Jackson, for appellee.

Before PATTERSON, P.J., and BROOM and COFER, JJ.

COFER, Justice, for the Court:

From a decree of the Chancery Court of the First Judicial District of Hinds County, considered substantially against it, appellant M.T. Reed Construction Company (Reed), and in favor of appellee, Nicholas Acoustics and Specialty Company, (Nicholas), appellant has taken this appeal and assigns numerous errors, which, in its brief, it has condensed into three points of argument:

1. The chancellor erred in finding that certain items of cost to Reed are not allowable under change order 3-A.
2. The chancellor erred in denying appellant's claim for delay damages.
3. The chancellor erred in allowing prejudgment interest.

The suit was begun by declaration in circuit court, by which declaration Nicholas sought recovery under a change order to a basic subcontract, to be noticed hereinafter, and prejudgment interest and punitive damages. The suit had contractual and tort features. In the circuit court it was determined that the contract feature contained complicated mutual accounts, issues which made transfer to the chancery court proper. Mississippi Constitution, section 161 (1890). In the chancery court appellee complainant, complying with Mississippi Code Annotated, section 11-1-39 (1972), filed its bill of complaint, wherein it did not pray for prejudgment interest, but incorporated a prayer for general relief.

The appellant was the successful bidder to become the prime contractor for the construction of the Mississippi Methodist Rehabilitation Center, in Jackson, and entered into contract for that work on April 24, 1972. The contract included work in ceilings, partitions and floors, and Reed by subcontract dated May 24, 1972, contracted with Nicholas, a contractor skilled in the required ceiling, partitions, and floor installation, for the performance of that part of the contract.

The building was being built for the housing and care of patients, and the specifications *310 called for the use, in designated areas, of wall partitioning of non-combustible and sound resistant materials. The particular material specified was in such short supply that appellee substituted a material fire resistant but not fire proof, which was available at a small reduction in price under that required by the specifications. Whether appellee did this substitution after coordination with the architect, through the architect's inspector on the job, was, to the extent of its materiality, a question for the trier of fact, being in conflict.

A fire broke out in a partition in the building, on October 2, 1974, when the building was 85 to 98 percent completed, and the conflagration brought into bright focus, if it was not from the beginning, the use of the substituted wall partition materials. (Some were able to testify that the materials were not fire proof because they saw them burning.)

Conferences ensued between the owner, the architect, appellant, and appellee, wherein the parties hereto undertook to escape the financial loss of replacing the substituted materials with specified materials. Finally, it was agreed, by a change order from the owner to appellant, that the materials would be torn out and replaced by materials mutually agreed upon and available, and that the owner would pay $70,000 toward the work entailed by the change order.

With this change order agreement, appellant and appellee agreed, reduced to their change order 3-A, (3-A), that they would do the work necessary under the owner's change order (G-10), and that only "actual labor and material costs plus taxes," would be charged, first against the $70,000 in change order G-10, and all above the $70,000 would be paid in equal parts by appellant and appellee. G-10 gave to appellant 110 extra days in which to complete its contract; by 3-A appellant gave to appellee 89 days wherein to complete work under that change order. (As to who was at fault makes significant the owner's agreement to pay $70,000 toward the remedial work, and Reed's agreement to pay one-half of the balance of the cost thereof.)

Four monthly reports were given by appellee to appellant covering its labor, material, and taxes costs on the 3-A work. Appellant Reed paid the first two of these, for November and December 1974, less 10 percent retained from their amounts, but never did pay the latter two reports.

The 3-A work was completed in March 1975 but Reed submitted to Nicholas its 3-A expenses summary on August 27, 1975, and in an amount re-examined and substantially increased in a summary tendered by appellant to appellee on November 5, 1975.

The parties were never able to agree on an account and a determination of which of them owed the other, and this suit resulted.

In answering Nicholas' bill of complaint filed as noticed above, Reed incorporated a cross bill wherein it injected a prayer for delay damages, in the amount of $20,642.86, contending that this damage was suffered by Reed because of the arbitrary act of Nicholas in substituting the wall materials as shown above. Delay damages were sought in the circuit court, by way of a counterclaim before transfer of the case to the chancery court.

After a time, the chancellor, after conference with the parties' attorneys, referred all issues and prayers in the pleadings, other than the delay damages matters in the cross bill, to a special master in chancery. Griffith, Mississippi Chancery Practice, Chapter 38 (2d ed. 1950). In her decree making the appointment, she recited that she had reviewed the pleadings, and held a pre-trial conference, and observed that "this case involves a complex mutual accounting to determine the respective costs to each of the parties in performing and completing `Change No. 3-A' to the subcontract of Nicholas Acoustics and Specialty Company, prime contractor, ... which accounting is to be followed by a calculation of the amount due from one party to the other, arising out of the sub-contract between the parties plus Change No. 3-A, and that a special master should be appointed to state the account between the parties and to make the aforesaid calculation."

*311 She appointed to that office an attorney and certified public accountant and made provision for the filing of itemized statements of claims supported by evidence of payments, on the part of each of the parties and for filing, by each party, of detailed exceptions to the claims of the other party, and that the master could take testimony in the hearing.

Pursuant to the appointment, hearing or hearings produced testimony and exhibits filling much of the ten volumes making up the appeal record herein. Within a reasonable and proper time after the conclusion of the hearing, the master filed his report of his findings of fact and including a statement of the account between the parties and a calculation of the amount he found to be due from either party to the other.

Exceptions were freely filed; these were examined by the master and he replied to them, giving explanation as to his reasoning in the case of particular exceptions.

In its appeal brief, Reed has condensed down to one item (with several parts) its assignment of error of the findings that certain claims of costs to Reed are not allowable under 3-A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Preferred Risk Mut. Ins. Co. v. Johnson
730 So. 2d 574 (Mississippi Supreme Court, 1998)
Joshua Charles Miller v. State of Mississippi
Mississippi Supreme Court, 1997
American Fire Protection, Inc. v. Lewis
653 So. 2d 1387 (Mississippi Supreme Court, 1995)
Ivy v. Illinois Cent. Gulf R. Co.
510 So. 2d 520 (Mississippi Supreme Court, 1987)
Blaylock v. Life Insurance Co. of North America
615 F. Supp. 310 (N.D. Mississippi, 1985)
Tideway Oil Programs, Inc. v. Serio
431 So. 2d 454 (Mississippi Supreme Court, 1983)
Thompson v. First Mississippi Nat. Bank
427 So. 2d 973 (Mississippi Supreme Court, 1983)
M. T. Reed Construction Co. v. Nicholas Acoustics & Specialty Co.
387 So. 2d 98 (Mississippi Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
379 So. 2d 308, 1980 Miss. LEXIS 1830, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mt-reed-const-co-v-nicholas-acoustics-etc-miss-1980.