Msc Walbridge Coatings, Inc. v. Harmeyer, Unpublished Decision (6-23-2006)

2006 Ohio 3181
CourtOhio Court of Appeals
DecidedJune 23, 2006
DocketCourt of Appeals No. WD-05-075, Trial Court No. 04-CV-757.
StatusUnpublished
Cited by1 cases

This text of 2006 Ohio 3181 (Msc Walbridge Coatings, Inc. v. Harmeyer, Unpublished Decision (6-23-2006)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Msc Walbridge Coatings, Inc. v. Harmeyer, Unpublished Decision (6-23-2006), 2006 Ohio 3181 (Ohio Ct. App. 2006).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This case is before the court on appeal from the Wood County Court of Common Pleas following the September 1, 2005 entry of summary judgment against appellants, Richard and Lenore Harmeyer. For the reasons that follow, we affirm the trial court's decision.

{¶ 2} The relevant facts of this case are as follows. In August 1994, appellee, MSC Walbridge Coatings, Inc. ("MSC"), entered into an agreement as seller with H H, a partnership consisting of Richard Harmeyer and Tom Houston. The parties entered into three contracts total, with the fourth contract listing "H H Metals, Inc./Harmeyer" as the buyer.

{¶ 3} The remaining five contracts, including the February 19, 2003 contract for scrap steel pup coils at issue in this case, list "Dick and Lenore Harmeyer" as buyer. The Harmeyers were the sole shareholders of H H Metals and Harmeyer, Inc. The last contract between the parties was negotiated by both Richard and Lenore Harmeyer and Tom Bishop, MSC's former plant manager. The contract was signed by Bishop as the seller and Lenore Harmeyer as the buyer; nothing in the contract indicated that Lenore Harmeyer was signing on behalf of anyone other than the buyers as identified in the contract.

{¶ 4} On December 7, 2004, MSC filed a complaint against appellants for breach of the February 19, 2003 contract, money due on the account, unjust enrichment, and quantum meruit. On January 31, 2005, appellants filed their answer denying that they were individually responsible and, asserting a counterclaim for $8,600 due on the account, appellants further requested contract reformation asserting that the contract did not state the true agreement entered into between the parties.

{¶ 5} On June 29, 2005, appellee's counsel deposed Richard and Lenore Harmeyer. During the depositions, appellants' counsel instructed his clients not to answer any questions about who, other than appellants, was liable for the scrap steel and whether the scrap steel was sold for a profit. Appellee's counsel objected to appellants' refusal to answer these questions.

{¶ 6} On July 18, 2005, appellee filed a motion for summary judgment on its breach of contract claim arguing that there was no genuine issue of fact based on the pleadings, appellants' depositions, and the affidavit of Ryan Rigney, an accounting manager for MSC. Appellee contended that the appellants were personally liable for the amount of money still owed on the contract and that its claim of personal liability was supported by the unambiguous language of the document.

{¶ 7} In their memorandum opposing summary judgment, appellants argued that the contract was never properly signed by MSC because Bishop was not identified as its representative. Additionally, appellants argued that the prior relationship and course of dealings between the parties confirm that appellee knew it was doing business with Harmeyer, Inc., and not the Harmeyers as individuals.

{¶ 8} On August 9, 2005, appellee filed a motion to compel discovery in response to the appellants' refusal to answer certain interrogatories; and, on August 16, 2005, the court ordered appellants to provide complete responses and pay the attorney's fees incurred in seeking the order.

{¶ 9} On September 1, 2005, appellee's motion for summary judgment was granted. The trial court agreed with appellee that the contract was unambiguous in its description of the parties bound by the contract. Additionally, the court rejected the appellants' argument that because the address listed on the contract was that of Harmeyer, Inc., and not the Harmeyer's home address appellee knew it was doing business with Harmeyer, Inc. Appellee was awarded $367,688.72 in damages at 1.5 percent interest per month from November 30, 2004, until the judgment was paid. Thereafter, appellee dismissed its remaining claims against appellants, and appellants dismissed their counterclaim.

{¶ 10} On September 9, and September 12, 2005, appellee submitted its applications for attorney fees regarding the ordered motion to compel granted on August 16, 2005.

{¶ 11} On September 22, 2005, the trial court entered a nunc pro tunc judgment to correct its interest calculation with regard to damages. The judgment stated damages were to be awarded to the appellee in the amount of $341,602.96, plus $26,085.76, the amount of interest accrued through November 30, 2004, plus 1.5 percent interest per month from November 30, 2004, on the total price of the steel at issue until the judgment was paid.

{¶ 12} On September 28, 2005, appellants filed their notice of appeal.

{¶ 13} On October 4, 2005, the trial court awarded sanctions against appellants in the amount of $2,383 for attorney's fees incurred in seeking the order to compel discovery responses and for the expenses related to obtaining appellants' depositions.

{¶ 14} On appeal, appellants raise two assignments of error:

{¶ 15} "1. The trial court erred in granting the summary judgment for Plaintiff and in granting judgment against Defendants individually.

{¶ 16} "2. The trial court abused its discretion in awarding attorney fees to Plaintiff because of alleged failure to provide discovery."

{¶ 17} We first note that appellate review of a trial court's grant of summary judgment is de novo. Grafton v. Ohio EdisonCo., 77 Ohio St.3d 102, 105, 1996-Ohio-336. Accordingly, we review the trial court's grant of summary judgment independently and without deference to the trial court's determination. Brownv. Scioto Cty. Bd. of Commrs. (1993), 87 Ohio App.3d 704, 711. Summary judgment will be granted only when there remains no genuine issue of material fact, and when construing the evidence most strongly in favor of the nonmoving party, reasonable minds can only conclude that the moving party is entitled to judgment as a matter of law. Harless v. Willis Day Warehousing Co. (1978), 54 Ohio St.2d 64, 66; Civ.R. 56(C). The burden of showing that no genuine issue of material fact exists falls upon the party who moves for summary judgment. Dresher v. Burt,75 Ohio St.3d 280, 294, 1996-Ohio-107. However, once the movant supports his or her motion with appropriate evidentiary materials, the nonmoving party "may not rest upon the mere allegations or denials of his pleadings, but his response, by affidavit or as otherwise provided in this rule, must set forth specific facts showing that there is a genuine issue for trial." Civ.R. 56(E).

{¶ 18} Appellants' first assignment of error disputes the trial court's determination that appellee was entitled to summary judgment on its breach of contract claim. Specifically, appellants dispute that they were personally liable under the contract; appellants assert that they signed the contract on behalf of Harmeyer, Inc., and not personally.

{¶ 19} The interpretation of a contract is an issue of law, not of fact, to be determined by the court. Graham v. DrydockCoal Co., 76 Ohio St.3d 311,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State ex rel. Ames v. Geauga Cty. Bd. of Revision
2023 Ohio 1247 (Ohio Court of Appeals, 2023)

Cite This Page — Counsel Stack

Bluebook (online)
2006 Ohio 3181, Counsel Stack Legal Research, https://law.counselstack.com/opinion/msc-walbridge-coatings-inc-v-harmeyer-unpublished-decision-6-23-2006-ohioctapp-2006.