MPower Communications Corp. v. Hurley

381 F. Supp. 2d 738, 2005 U.S. Dist. LEXIS 15707, 2005 WL 1812928
District Court, N.D. Illinois·Decided July 29, 2005·No. 04 C 6909, No 04 C 7402·Published·Cited by 2 cases

Opinion

MEMORANDUM OPINION AND ORDER

CASTILLO, District Judge.

The Illinois Commerce Commission (“ICC”) entered an order, pursuant to the Telecommunications Act of 1996 (“1996 Act”), Pub.L. No. 104-104, 110 Stat. 56 (codified in scattered sections of 47 U.S.C.) and the Federal Communication Commission’s (“FCC”) rules, 47 C.F.R. §§ 51.501-51.515, setting rates for unbundled network elements (“UNEs”) that the Illinois Bell Telephone Company (“SBC”), which is the incumbent local exchange carrier (“ILEC”), must make available to competing local exchange carriers (“CLECs”) that enter into interconnection agreements with SBC. SBC and several CLECs- — specifically Mpower Communications Corp., Forte Communications Inc., CIMCO Communications, Inc., and XO Illinois, Inc.— have filed summary judgment motions requesting federal review of the ICC’s order. These CLECs also claim that the underlying ICC proceeding was preempted by the 1996 Act. For the reasons provided below, we grant the CLECs and SBC’s motions for summary judgment. (R. 34-1; R. 59-1.) Accordingly, we reverse three aspects of the ICC’s order and remand this case back to the ICC with directions to re-visit these specific issues.

PROCEDURAL HISTORY

This case has a complex and complicated procedural history dating back to 2002 when SBC filed a tariff — docketed with the ICC as 02-0864 — under 220 Ill. Comp. Stat. 5/9-201 to update the rates at which it must lease UNEs to CLECs. After the ICC initiated an investigation into SBC’s proposed rates, the Illinois legislature passed a law (220 Ill. Comp. Stat. 5/13-408) that abated SBC’s tariff proceeding and required the ICC to update these rates in a specified manner within 30 days. Various CLECs challenged the law in federal court asserting that it was preempted by the 1996 Act. The district court agreed and issued an injunction declaring the state law unlawful. The Seventh Circuit affirmed and stated that the “ICC is compelled by the injunction to reinstate the proceeding in its Docket 02-0864, which the state law had terminated, and to proceed to decision as expeditiously as possible.” AT&T Communications of Ill., Inc. v. Ill. Bell Tel. Co., 349 F.3d 402, 411 (7th Cir.2003).

The ICC complied with the Seventh Circuit’s directive. Within approximately seven months, the ICC re-opened SBC’s abated tariff proceeding, permitted dozens of parties to intervene, heard extensive expert testimony and arguments, and issued a single-spaced, 299 page order. 1 The ICC was concerned that the proceeding might be preempted by the 1996 Act so specifically addressed that issue. (ICC Order at 289-94.) The ICC’s order states that the “CLECs requested [that] the Commission move forward with this case but treat it as a generic rate investigation” and asserted that “there was consensus among the parties that the Commission could move forward with this proceeding as a generic rate investigation under the [1996 Act].” 2 *742 (Id. at 291-92.) Ultimately, the ICC held that the proceeding was not preempted by the 1996 Act and decided to treat it procedurally as a state-law tariff proceeding but substantively as a generic ratemaking proceeding. (Id. at 9.)

The ICC’s order sets the UNE rates that SBC must make available to CLECs that enter into interconnection agreements with SBC and explains why these rates are TELRIC-compliant. TELRIC stands for “total element long-run incremental cost” and is the specific methodology that the FCC requires state regulators to use when setting UNE rates. 3 See 47 C.F.R. § 51.505(b). “TELRIC obliges both incumbents and state regulators to set prices based on the long-run costs that would be incurred to produce the services in question using the most-efficient telecommunications technology now available, and the most efficient network configuration.” AT&T, 349 F.3d at 405. To set TELRIC-compliant UNE rates, the ICC undertook studies of recurring and nonrecurring costs and analyzed labor rates, common costs, annual charges, and many additional miscellaneous factors. A substantive description of the ICC’s order will be provided in the analysis section of this opinion due to the ICC’s order’s length, its technical complexity, and the substantial number of issues raised by the parties.

LEGAL STANDARDS

We review the ICC’s legal conclusions de novo and its factual determinations under the arbitrary and capricious standard. See Ind. Bell Tel. Co. v. McCarty, 362 F.3d 378, 383-85 (7th Cir.2004). Under the arbitrary and capricious standard, we will affirm all factual decisions that are “supported by substantial evidence” and are “the result of a deliberate principled reasoning process.” Mich. Bell Tel. Co. v. Strand, 305 F.3d 580, 587 (6th Cir.2002). A deliberate principled reasoning process requires consideration of all the necessary information as well as the provision of a meaningful explanation. See Ill. Bell Tel. Co. v. Wright, 245 F.Supp.2d 900, 905 (N.D.Ill.2003). Because we must defer to the ICC’s judgment and technical expertise, we cannot re-weigh evidence, decide credibility questions, or supplant the ICC’s judgment. Ill. Bell Tel. Co. v. Wright, No. 00 C 7050, 2003 WL 22757752, at *6 (N.D.Ill. Nov.20, 2003). In short, a decision is only arbitrary and capricious if it is “so implausible that it could not be ascribed to a difference in view or the product of agency expertise.” U.S. West Comm., Inc. v. Hix, 986 F.Supp. 13, 18 (D.D.C.1997). 4

ANALYSIS

Free access — add to your briefcase to read the full text and ask questions with AI

MPower Communications Corp. v. Hurley, 381 F. Supp. 2d 738, 2005 U.S. Dist. LEXIS 15707, 2005 WL 1812928 (N.D. Ill. 2005).

381 F. Supp. 2d 738 (MPower Communications Corp. v. Hurley) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

TDS METROCOM, LLC v. Bridge
387 F. Supp. 2d 935 (W.D. Wisconsin, 2005)