Mousseau v. Kuilman

309 P.2d 1042, 131 Mont. 264, 1957 Mont. LEXIS 115
CourtMontana Supreme Court
DecidedApril 15, 1957
DocketNo. 9326
StatusPublished

This text of 309 P.2d 1042 (Mousseau v. Kuilman) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mousseau v. Kuilman, 309 P.2d 1042, 131 Mont. 264, 1957 Mont. LEXIS 115 (Mo. 1957).

Opinion

MR. CHIEF JUSTICE HARRISON:

Appellants Carroll and Smith leased a garage building from appellant Kuilman. On December 18, 1950, the respondent entered into a contract with the appellants for the construction of a metallic masterplate floor in the building to be used for roller skating. The contract called for a consideration of $3,960. Eespondent began construction of the floor, and during the course of the construction he was paid the sum of $3,000 on the contract. On March 22, 1951, respondent filed this action, alleging completion of the floor, and demanded the balance of $960 due under the contract. Appellants filed a counterclaim alleging respondent failed to fulfill the terms of the contract, and demanded damages. By reply the respondent denied the counterclaim, and alleged that any damage to the floor was the result of appellants’ negligence. Trial was had before a jury which returned a verdict for the respondent. Motion for new trial was had and denied. This appeal followed.

Appellants specify two errors. First in the giving of an instruction based upon the theory of wrongful interference with the completion of the contract, and second in excluding certain offered testimony.

[266]*266Considering the first specification of error, the complaint of the respondent alleged in paragraph IV:

‘ ‘ That pursuant to the obligations fixed by the terms of said contract the plaintiff proceeded to do all work obligatory upon him under the terms of the contract and that he did such work as provided in said contract in a good, substantial and workmanlike manner, providing all of the materials necessary and properly and sufficiently completing and finishing said work. ’ ’

This allegation was denied in the answer of the appellants, and in their counterclaim they alleged in paragraph IV:

“That the plaintiff did not fulfill said contract on his part, but on the contrary, constructed and poured said floor in so unskillful and unworkmanlike manner and of so unsuitable materials, that shortly after its completion the floor cracked and came apart causing holes in numerous places on said floor,that the finish on said floor flakes and scrapes off and said floor is useless for roller skating through the negligent and unskillful manner of its construction, and is of no value to the defendants. ’ ’

In respondent’s reply he alleged:

“The plaintiff denies the allegations of paragraph IV of said counterclaim, except to admit that the floor was badly damaged and alleges the fact to be that said damage was caused by the wrongful conduct of the defendants and through no fault or omission of the plaintiff.”

The testimony developed that the pouring of the cement and application of the masterplate was finished on January 10, 1951. It was thereafter allowed to cure and a wax was then applied. The wax did not harden sufficiently and respondent contacted the manufacturer who advised its removal and the use of Sanaseal to cover the floor for hardening purposes. This was done and it was finally determined that the floor was ready for use and the roller skating rink was opened. Respondent gave certain instructions to the appellant with regard to the use of the floor and the manner of keeping it clean. Shortly after the opening, respondent went to the rink and found the [267]*267appellant cleaning the floor with water from a hose. He then notified them not to skate upon it until it had dried off, at which time appellant Carroll advised respondent the floor was dry. Respondent stated it could not be since it had been flooded shortly before, and he further told Carroll that if they skated on the floor they would take the responsibility. The floor was used for skating that evening in spite of respondent’s objection. Respondent continued to work applying the Sanaseal to portions of the floor that required further treatment, but shortly thereafter on coming to the rink, he discovered appellant applying another type of sealer. He remonstrated to them but they continued to apply this sealer and advised respondent that the Sanaseal was no good. It appeared that this sealer filled the pores in the floor so that further applications of Sanaseal could have no effect. The floor continued to be used as a roller rink until the latter part of May when it was shut down. Appellants thereafter lost their lease, the building was sold, the floor removed and dumped.

There is conflict in the testimony throughout as to the actions of the parties in connection with the floor, but no objections were made at any time to proof by the respondent of the actions of the appellants which stopped him from further trying to remedy the portions of the floor which appeared to flake or dust. At the very commencement of the cross-examination of the respondent by appellants’ counsel, this statement appears in the record made by respondent’s counsel: “I respectfully submit the witness answered he never completed the floor due to the interference of these defendants.” The case was tried on that theory, respondent showing in detail all the things done by appellants which forced him to stop his efforts to fix the portions which seemed to require further treatment.

At the close of respondent’s case, the appellants were fully advised of the theory of the case by respondent. No claim of variance, between the allegation in the pleading and the proof, was made and nothing appears in the record to indicate that appellants had been misled to their prejudice. No motion for [268]*268nonsuit was made at the close of respondent’s case. This situation has been before this court and we have stated:

“That this testimony established the injury and damage of plaintiff (injury, however, was admitted by the answer), and that the negligence of defendant was the proximate cause thereof, and that a prima facie case had been made, was inferentially admitted by defendant, for he did not move for a non-suit, a dismissal, a judgment, nor ask for any other relief when plaintiff rested his case.” Williams v. Hample, 62 Mont. 594, 205 Pac. 829, 830.
“That plaintiff’s complaint was sufficient, and that its evidence made a prima facie case, is admitted by defendant’s failure to attack the complaint or to move for relief at the close of plaintiff’s case.” Stoltze Land Co. v. Westberg, 63 Mont. 38, 206 Pac. 407, 408.

Appellants chose to proceed, and in their case explained their version of the interference claimed by respondent.

From the evidence produced at the trial, the question of whether or not the appellants had prevented respondent from fully completing his work under the contract became in effect the main issue.

Respondent offered the following instruction:

“You are instructed that where one is prevented from performing his obligations under a contract by the wrongful interference, if any, of the other party or parties to the contract, then the party whose performance is thus interfered with may treat the wrongful act of interference with his performance of the contract as terminating his duties thereunder and sue for the balance due him, if any, under the terms of the contract. ’ ’

The court gave the instruction over the objection of the .■appellants who then contended that the theory of the ease was that respondent completely performed and completed the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pease v. Citizens State Bank
214 N.W. 486 (Supreme Court of Iowa, 1927)
Des Moines Asphalt Paving Co. v. Lincoln Place Co.
207 N.W. 563 (Supreme Court of Iowa, 1926)
Johnson v. Caughren
104 P. 170 (Washington Supreme Court, 1909)
Williams v. Hample
205 P. 829 (Montana Supreme Court, 1922)
Stoltze Land Co. v. Westberg
206 P. 407 (Montana Supreme Court, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
309 P.2d 1042, 131 Mont. 264, 1957 Mont. LEXIS 115, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mousseau-v-kuilman-mont-1957.