Mouledous v. Poirier

221 So. 2d 291
CourtLouisiana Court of Appeal
DecidedApril 7, 1969
Docket3405
StatusPublished
Cited by11 cases

This text of 221 So. 2d 291 (Mouledous v. Poirier) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mouledous v. Poirier, 221 So. 2d 291 (La. Ct. App. 1969).

Opinion

221 So.2d 291 (1969)

Richard C. MOULEDOUS
v.
Joseph O. POIRIER.

No. 3405.

Court of Appeal of Louisiana, Fourth Circuit.

April 7, 1969.

*292 Harry A. Burglass, Metairie, for plaintiff-appellee.

Baldwin, Haspel, Molony, Rainold & Meyer, Conrad Meyer, III, New Orleans, for defendant-appellant.

Before REGAN, CHASEZ and GARDINER, JJ.

*293 GARDINER, Judge.

Plaintiff, a qualified architect, brought this suit against defendant for recovery of the sum of $1,850.00, representing his fee for services allegedly rendered in the preparation of plans and specifications for defendant under a verbal agreement with defendant on December 3, 1964. In the alternative, plaintiff prays for the value of his work on a quantum meruit basis. Defendant refused to pay plaintiff any amount claiming that he failed to carry out the terms of their contract.

After trial in the 24th Judicial District Court for the Parish of Jefferson, there was judgment in favor of plaintiff on a quantum meruit basis in the sum of $1,500.00. Defendant appealed and plaintiff has answered the appeal praying that the amount be increased to $1,850.00.

Plaintiff alleges that he was retained by defendant for his "professional services in connection with preparation of plans and specifications for the construction of a proposed 22-unit multi-family structure"; that pursuant to this alleged agreement, he did in fact prepare "complete plans and specifications in a good, workmanlike and professional manner * * *", and that he had "taken all steps necessary" to obtain the building permit. In his answer defendant admits that he and plaintiff entered into an oral agreement for "complete" plans to be delivered to him by December 25, 1964, and that previous to February 2, 1965, he and plaintiff's assistant went over "preliminary plans" which defendant alleges were inadequate and required revision. Defendant further averred that he received the plans on February 11, 1965, from the Department of Regulatory Inspections of the Parish, but that they were of no value to him inasmuch as they were "unworkable, incomplete and unsatisfactory."

Defendant complains that the trial judge erred (1) in failing to hold that plaintiff is bound and estopped by the allegations of his petition; (2) in failing to exclude evidence objected to by counsel which enlarged the pleadings; (3) in allowing recovery under a quantum meruit where plaintiff proved the existence of the alleged contract, and (4) in failing to measure recovery according to the value of the benefits received.

At defendant's home, on December 3, 1964, plaintiff allegedly agreed verbally to prepare complete plans and specifications for a 22-unit apartment to be constructed on defendant's land and defendant asserts they were to be completed by Christmas as time was of the essence. Defendant contends that he was anxious to start construction before the parish enacted a comprehensive zoning ordinance which might prevent the contemplated construction and before money became "tight" making financing infeasible. A fee of about three per cent of the total cost of the building, without any supervision by the architect, was mentioned at this first and only meeting between plaintiff himself and defendant. The testimony is conflicting as to the cost of constructing the apartment; plaintiff says it was $225,000.00 and defendant states that it would cost $190,000.00. The evidence shows that the plans as submitted were incomplete and were defective in many respects. Defendant contacted plaintiff's office many times without success to ask for delivery of the plans, but it appears that they were finally filed by plaintiff's associate, a Mr. Olliges, on January 22, 1965, in the proper office of the parish. It was not until February 2, 1965, that plaintiff received a letter from defendant's counsel, copy, of which is introduced in evidence, notifying him that defendant would expect a compliance with his previous request to complete the plans and obtain a permit within five days or plaintiff would make other arrangements. On February 6, 1965, plaintiff wrote defendant that everything necessary had been done to obtain a permit for the proposed construction and that the permit would be issued by the Jefferson Parish Department of Regulatory Inspections as soon as defendant made a proper test pile on the land. On February 11, defendant *294 received a telephone call from Mr. Olliges, who did not testify in this case, saying that the plans were ready and that he could pick them up from the Department, which he did on that day by first paying $144.50. The amount of the construction, $225,000.00, was inserted in the application by Mr. Kennedy, a building inspector for the parish, after a call to the architect's office for this information. The permit was issued with certain restrictions, one being that a test pile had to be made by defendant at his own expense. Defendant said that the money market tightened up in June 1965, and while he did nothing further towards building the structure, he renewed the permit on August 5, 1965, and again on February 16, 1966.

On March 5, 1965, plaintiff wrote the following letter to plaintiff concerning his fee for services which had been performed to that time and additional work if required by defendant:

"Mr. Joseph O. Poirier 9501 Jefferson Highway New Orleans, Louisiana

"Re: Casa Grande Apartments CN: 6434

"Dear Sir:

"Some time ago when we first discussed the drawings for your apartments, the architectural fee was mentioned at about 2 ½% of the construction cost. Also, it was agreed that the fee would be reduced if the apartments were not built.

"For our mutual benefit and understanding, we believe that setting a lump sum fee would be preferable to the percentile agreement. We would like to propose that the project be listed in three stages, as follows:

"1. Drawings and specifications completed to date ..............        $ 1,850.00
"2. Revisions to drawings, completing engineering work, polishing-up
    drawings and specifications ....................................    $ 1,650.00
"3. Job supervision (if required) ..................................    $ 1,000.00
                                                                         _________
    TOTAL ...........................................................   $ 4,500.00

"Stage #1 has been completed by our office and should represent the total project should you decide not to build the apartments. Since we are starting on stage #2, we believe it important to come to some agreement at this time.

"Incidentally, the above figures, including supervision, total less than 2 ½% of our preliminary cost estimate ($190,000.00).

"If you concur in the above, we would appreciate your signing and returning to us one copy of this letter so we may proceed with the final phase of the drawings."

Defendant refused to sign the letter and on the trial admitted only that they agreed the architect's fee would be about two and a half or three per cent of the total cost provided defendant could secure proper financing and constructed the building.

*295 On May 1, 1967, plaintiff made demand upon defendant for $1,850.00 stating that it represented his fee for professional services for "preliminary and partially completed working drawings." A copy of a letter written by counsel for defendant to plaintiff, dated May 4, 1965, which plaintiff offered in evidence, reads in part as follows:

"It seems that a permit was obtained on the basis of certain plans which Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Scoggins v. Frederick
744 So. 2d 676 (Louisiana Court of Appeal, 1999)
Fontenot v. Sunland Construction
482 So. 2d 949 (Louisiana Court of Appeal, 1986)
National Bank of Bossier City v. Nations
465 So. 2d 929 (Louisiana Court of Appeal, 1985)
Coutee v. American Druggist Ins. Co. of Cincinnati
453 So. 2d 314 (Louisiana Court of Appeal, 1984)
Brashers v. Shreveport Ambulance Service, Inc.
424 So. 2d 409 (Louisiana Court of Appeal, 1982)
Vidrine v. Carmouche
422 So. 2d 1327 (Louisiana Court of Appeal, 1982)
Bank of New Orleans & Trust Co. v. Lambert
373 So. 2d 550 (Louisiana Court of Appeal, 1979)
Guidry v. Barras
368 So. 2d 1129 (Louisiana Court of Appeal, 1979)
Huhn v. Marshall Exploration, Inc.
337 So. 2d 561 (Louisiana Court of Appeal, 1976)
Valvoline Oil Company v. Krauss
335 So. 2d 64 (Louisiana Court of Appeal, 1976)
J. H. Jenkins Contractors, Inc. v. Farriel
259 So. 2d 882 (Supreme Court of Louisiana, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
221 So. 2d 291, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mouledous-v-poirier-lactapp-1969.