Mostoller v. CWCapital, LLC

117 F. App'x 425
Court of Appeals for the Sixth Circuit·Decided December 6, 2004·No. 03-6069·Unpublished

Opinion

*426 PER CURIAM.

This is a contract dispute centered on a HUD-backed loan for a housing development. Plaintiff-Appellant Mostoller, Bankruptcy Trustee for West Pointe, appeals from the district court’s order granting summary judgment to defendant CWCapital in a suit for breach of contract. Appellant argues that CWCapital breached the contract by declaring West Pointe in default. We find that the contract plainly authorized CWCapital to declare a default if West Pointe failed to meet the construction deadline, and we therefore affirm.

I

On August 7, 1996, West Pointe (now in Chapter 7 and represented by Mostoller), obtained a HUD-insured loan from Continental Wingate (“CW”) (CWCapital’s predecessor). The loan was to support the construction of a low-to-medium-income residential housing complex, which was to have 33 acres and 150 home units, as well as swimming pools and other facilities. In connection with the loan, the parties executed a number of documents (collectively “loan agreement”) governing construction, repayment, and other requirements. The loan agreement required West Pointe to make monthly payments of interest for the first eleven months, and then to repay both interest and principal.

Among other conditions, the loan agreement included two requirements at issue in this case: (1) West Pointe must complete construction by July 7, 1997, and (2) West Pointe must make all payments when due. If West Pointe failed to meet either of these requirements, CW could declare the loan in default. Upon default, CW was authorized to accelerate the loans and demand full repayment immediately. HUD had all responsibility for inspecting the progress of the construction project and determining whether the pace and quality of construction met requirements.

The loan agreement provided that “no waiver by [CW] of any event of default [would] operate as a waiver of any other event of default or the same event of default on a future occasion.” Moreover, CW could “delay in exercising or omit to exercise any right or remedy ... without waiving that or any past, present or future right or remedy.” Also, the loan agreement specifically stated that it could be modified only in writing.

A. Problems with Construction (or lack thereof)

West Pointe contracted with Hicks Excavating (“Hicks”) to serve as the general contractor on the project. Hicks was required to finish construction by February 7, 1997, so that West Pointe could begin repaying loan principal by July 7, 1997. Changes to the construction contract had to be approved by HUD and CW in writing.

From an early date, HUD reported slow and problematic construction. In January 1997, West Pointe, with CW’s consent, submitted a request to HUD for an additional six-month extension beyond the February 7 deadline in the construction contract. HUD denied the six-month extension, but, in light of rain delays, granted West Pointe an additional eighty-seven days to May 5, 1997. Even with the extension, West Pointe could not complete construction on time. On May 8,1997, it requested another extension from HUD. In a July 9 letter, HUD’s representative stated that “additional time to complete the work has not been justified as required by the general conditions.... [M]y staff has not observed a proper, concerted effort ... to complete the job in a timely manner.” Ronald Frye, the president of West Pointe, acknowledged a litany of problems that *427 arose during construction, ranging from unpaved roads to lot grading to faulty piping installation.

Hicks, the general contractor, pulled off the project twice in July and August because of disputes with West Pointe. After Hicks returned briefly, West Pointe kicked Hicks off the work-site in October 1997. After Hicks left the work-site in October, West Pointe was unable to retain another general contractor or induce Hicks to return. At this point the project was about 25% complete.

On November 5,1997, HUD advised CW that West Pointe may have violated the loan agreement, and recommended that CW not advance further funds and “review the options available to them under default.” HUD identified a number of possible violations of the loan agreement by West Pointe, including problems with construction and failure to make required payments.

In addition to the construction problems, West Ponte failed to make full and timely payments on the loan. West Pointe never paid the $23,566 required by HUD as part of a fourth change order. The fourth change order was necessitated by problems with the water piping. HUD approved the change, but required West Pointe to pay the increased costs out of its own pocket by depositing the amount of the cost increase — $23,566—with CW. In addition, West Pointe failed to make the scheduled payment of interest and principal for October 1997. Instead, it submitted a request for an additional advance against the loan.

B. Default and Foreclosure

On December 10, 1997, CW declared West Pointe in default. CW exercised its right to accelerate the loan and demand repayment. Shortly thereafter, CW assigned the loan to HUD, pursuant to HUD regulations.

HUD gave West Pointe several opportunities over the next year to show why HUD should not foreclose. After a full hearing, HUD concluded that the project could not be salvaged and, on November 9, 1998, declared its intent to foreclose. In the hopes of staying foreclosure, West Pointe filed for bankruptcy. The bankruptcy court, however, granted HUD’s request for relief from the automatic bankruptcy stay, and foreclosure proceeded. HUD sold West Pointe’s property to the highest bidder for $350,000.

C. Proceedings Below

The Trustee for West Pointe (“West Pointe”) brought this suit for breach of contract. West Pointe claimed that HUD and CW were jointly and severally liable for damages resulting from the declaration of default and foreclosure. West Pointe sought $25 million in compensatory damages and $50 million in punitive damages. It alleged that oral modifications of the contract provided for an indefinite extension of construction deadlines. It also alleged that the July 9, 1997, letter from HUD extended the completion date for the project indefinitely.

In its first grant of summary judgment, the district court dismissed as speculative West Pointe’s claim for damages associated with “Phase II” of the project. Phase II involved a second parcel of undeveloped land that was adjacent to the land being developed by the HUD-backed loan. At no time was West Pointe the owner of the Phase II land. Although West Pointe had an option to acquire that land, that option expired on August 30, 1997, more than two months before the default. At no time did CW or any other party agree to finance the development of Phase II. The district court concluded that damages based on Phase II were entirely speculative.

In July 2003, the district court granted summary judgment for CW and HUD on *428 all remaining issues. The district court found that West Pointe had violated the loan agreement in three ways. First, West Pointe failed to complete construction on schedule.

Free access — add to your briefcase to read the full text and ask questions with AI

Mostoller v. CWCapital, LLC, 117 F. App'x 425 (6th Cir. 2004).

117 F. App'x 425 (Mostoller v. CWCapital, LLC) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related