23CA1908 Mostellar v City of Colo Spgs 10-24-2024
COLORADO COURT OF APPEALS
Court of Appeals No. 23CA1908 El Paso County District Court No. 23CV31616 Honorable Eric Bentley, Judge
Jaimi J. Mostellar,
Plaintiff-Appellee,
v.
City of Colorado Springs, a Colorado municipality,
Defendant-Appellant.
ORDER REVERSED AND CASE REMANDED WITH DIRECTIONS
Division V Opinion by JUDGE GROVE Lum, J., concurs Freyre, J., specially concurs
NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced October 24, 2024
Kane Law Firm, P.C., Mark H. Kane, Colorado Springs, Colorado, for Plaintiff- Appellee
Wynetta P. Massey, City Attorney, W. Erik Lamphere, Division Chief, Colorado Springs, Colorado, for Defendant-Appellant ¶1 Defendant, the City of Colorado Springs, appeals the district
court’s order denying its motion to dismiss based on the failure of
plaintiff, Jaimi Mostellar, to provide timely notice of her claim under
the Colorado Governmental Immunity Act (CGIA). We reverse,
holding that because Mostellar did not provide timely notice to
Colorado Springs as required by the CGIA, the district court did not
have subject matter jurisdiction over the case. We also remand to
the district court to determine Colorado Springs’s reasonable
attorney fees.
I. Background
¶2 Mostellar alleged in her complaint that, on August 26, 2021,
she was walking on a sidewalk in Manitou Springs when she
tripped over the remnant of a bus stop sign and fell, injuring
herself. Believing that Manitou Springs was responsible for
maintaining the sign, she gave timely notice of her claim to Manitou
Springs 131 days after her fall. See § 24-10-109(1), C.R.S. 2024
(requiring a “person claiming to have suffered an injury by a public
entity” to “file a written notice as provided in this section within one
hundred eighty-two days after the date of the discovery of the
injury”).
1 ¶3 However, in April 2023, approximately a year and a half after
Mostellar’s fall, Manitou Springs informed her it was not
responsible for maintaining the sign. Instead, Manitou Springs
asserted that the sign was Colorado Springs’s responsibility under
an intergovernmental agreement between the cities for bus services.
¶4 Mostellar notified Colorado Springs of her claim in May 2023,
roughly one month after Manitou Springs told her about the
intergovernmental agreement but more than 600 days after she was
injured. Mostellar ultimately filed suit against Colorado Springs on
August 24, 2023.
¶5 Colorado Springs moved to dismiss Mostellar’s complaint,
asserting that the district court lacked subject matter jurisdiction
because Mostellar failed to provide Colorado Springs with notice of
her claim within the CGIA’s 182-day deadline.
¶6 Noting that there were no factual disputes, the district court
denied the motion to dismiss after concluding that the CGIA’s
notice period did not begin to run until Mostellar was informed of
the intergovernmental agreement between Manitou Springs and
Colorado Springs. Thus, the court ruled that because Mostellar
provided notice to Colorado Springs within 182 days of learning of
2 the intergovernmental agreement, she complied with section 24-10-
109(1).
¶7 Colorado Springs now appeals the district court’s denial of its
motion to dismiss as permitted by section 24-10-108, C.R.S. 2024.
II. Standard of Review and Applicable Law
¶8 Timely notice under the CGIA is a matter of subject matter
jurisdiction. See Trinity Broad. of Denver, Inc. v. City of
Westminster, 848 P.2d 916, 924 (Colo. 1993). Whether a plaintiff
has satisfied the CGIA’s notice requirement is a mixed question of
law and fact. City & Cnty. of Denver v. Crandall, 161 P.3d 627, 633
(Colo. 2007). However, where, as here, the jurisdictional facts are
undisputed, we apply de novo review. Id.; see also Winkler v. Rocky
Mountain Conf. of United Methodist Church, 923 P.2d 152, 159
(Colo. App. 1995) (“[I]f the undisputed facts clearly show that a
plaintiff discovered, or reasonably should have discovered, the
negligent conduct as of a particular date, the issue may be decided
as a matter of law.”).
3 III. Mostellar’s Notice was Untimely
¶9 Colorado Springs contends the district court erroneously
found that Mostellar complied with the CGIA’s notice requirement.
We agree.
¶ 10 The CGIA requires a person claiming to have suffered an
injury by a public entity to file written notice with the entity within
182 days “after the date of the discovery of the injury, regardless of
whether the person then knew all of the elements of a claim or of a
cause of action for such injury.” § 24-10-109(1). The 182-day
deadline is jurisdictional, and because it is a non-claim provision, it
cannot be waived, tolled, or estopped. Mesa Cnty. Valley Sch. Dist.
No. 51 v. Kelsey, 8 P.3d 1200, 1206 (Colo. 2000). Thus, failure to
strictly comply with the CGIA’s notice requirements requires
dismissal of the action. See Crandall, 161 P.3d at 633-34; Reg’l
Transp. Dist. v. Lopez, 916 P.2d 1187, 1190-91 (Colo. 1996).
¶ 11 The CGIA’s notice period begins when a claimant “knew or,
through the exercise of reasonable diligence, should have known”
that she was wrongfully injured. Trinity, 848 P.2d at 927. The
claimant need not yet know the cause of the injury or the extent of
the damage. Gallagher v. Bd. of Trs. for Univ. of N. Colo., 54 P.3d
4 386, 391 (Colo. 2002), abrogated on other grounds by Martinez v.
Est. of Bleck, 2016 CO 58. Nor is the claimant required to know the
identity of the tortfeasor for the CGIA’s notice period to begin. See
E. Lakewood Sanitation Dist. v. Dist. Ct., 842 P.2d 233, 233-36
(Colo. 1992); Abrahamson v. City of Montrose, 77 P.3d 819, 821
(Colo. App. 2003).
¶ 12 Citing East Lakewood, 842 P.2d at 235-36, the district court
acknowledged in its order that “[a] claimant’s ignorance as to what
parties may bear responsibility for the injury is not a defense to the
notice deadline.” But the court nonetheless denied the motion to
dismiss, distinguishing East Lakewood on the basis that “Mostellar
could [not] reasonably have been expected to know that [Colorado
Springs] had any potential liability or to find out about the
intergovernmental agreement between the two municipalities other
than by proceeding as she did — giving Manitou Springs notice of
her claim and awaiting its response.” Under these circumstances,
the court concluded, it was required to follow the “squarely on
point” holding of State v.
Free access — add to your briefcase to read the full text and ask questions with AI
23CA1908 Mostellar v City of Colo Spgs 10-24-2024
COLORADO COURT OF APPEALS
Court of Appeals No. 23CA1908 El Paso County District Court No. 23CV31616 Honorable Eric Bentley, Judge
Jaimi J. Mostellar,
Plaintiff-Appellee,
v.
City of Colorado Springs, a Colorado municipality,
Defendant-Appellant.
ORDER REVERSED AND CASE REMANDED WITH DIRECTIONS
Division V Opinion by JUDGE GROVE Lum, J., concurs Freyre, J., specially concurs
NOT PUBLISHED PURSUANT TO C.A.R. 35(e) Announced October 24, 2024
Kane Law Firm, P.C., Mark H. Kane, Colorado Springs, Colorado, for Plaintiff- Appellee
Wynetta P. Massey, City Attorney, W. Erik Lamphere, Division Chief, Colorado Springs, Colorado, for Defendant-Appellant ¶1 Defendant, the City of Colorado Springs, appeals the district
court’s order denying its motion to dismiss based on the failure of
plaintiff, Jaimi Mostellar, to provide timely notice of her claim under
the Colorado Governmental Immunity Act (CGIA). We reverse,
holding that because Mostellar did not provide timely notice to
Colorado Springs as required by the CGIA, the district court did not
have subject matter jurisdiction over the case. We also remand to
the district court to determine Colorado Springs’s reasonable
attorney fees.
I. Background
¶2 Mostellar alleged in her complaint that, on August 26, 2021,
she was walking on a sidewalk in Manitou Springs when she
tripped over the remnant of a bus stop sign and fell, injuring
herself. Believing that Manitou Springs was responsible for
maintaining the sign, she gave timely notice of her claim to Manitou
Springs 131 days after her fall. See § 24-10-109(1), C.R.S. 2024
(requiring a “person claiming to have suffered an injury by a public
entity” to “file a written notice as provided in this section within one
hundred eighty-two days after the date of the discovery of the
injury”).
1 ¶3 However, in April 2023, approximately a year and a half after
Mostellar’s fall, Manitou Springs informed her it was not
responsible for maintaining the sign. Instead, Manitou Springs
asserted that the sign was Colorado Springs’s responsibility under
an intergovernmental agreement between the cities for bus services.
¶4 Mostellar notified Colorado Springs of her claim in May 2023,
roughly one month after Manitou Springs told her about the
intergovernmental agreement but more than 600 days after she was
injured. Mostellar ultimately filed suit against Colorado Springs on
August 24, 2023.
¶5 Colorado Springs moved to dismiss Mostellar’s complaint,
asserting that the district court lacked subject matter jurisdiction
because Mostellar failed to provide Colorado Springs with notice of
her claim within the CGIA’s 182-day deadline.
¶6 Noting that there were no factual disputes, the district court
denied the motion to dismiss after concluding that the CGIA’s
notice period did not begin to run until Mostellar was informed of
the intergovernmental agreement between Manitou Springs and
Colorado Springs. Thus, the court ruled that because Mostellar
provided notice to Colorado Springs within 182 days of learning of
2 the intergovernmental agreement, she complied with section 24-10-
109(1).
¶7 Colorado Springs now appeals the district court’s denial of its
motion to dismiss as permitted by section 24-10-108, C.R.S. 2024.
II. Standard of Review and Applicable Law
¶8 Timely notice under the CGIA is a matter of subject matter
jurisdiction. See Trinity Broad. of Denver, Inc. v. City of
Westminster, 848 P.2d 916, 924 (Colo. 1993). Whether a plaintiff
has satisfied the CGIA’s notice requirement is a mixed question of
law and fact. City & Cnty. of Denver v. Crandall, 161 P.3d 627, 633
(Colo. 2007). However, where, as here, the jurisdictional facts are
undisputed, we apply de novo review. Id.; see also Winkler v. Rocky
Mountain Conf. of United Methodist Church, 923 P.2d 152, 159
(Colo. App. 1995) (“[I]f the undisputed facts clearly show that a
plaintiff discovered, or reasonably should have discovered, the
negligent conduct as of a particular date, the issue may be decided
as a matter of law.”).
3 III. Mostellar’s Notice was Untimely
¶9 Colorado Springs contends the district court erroneously
found that Mostellar complied with the CGIA’s notice requirement.
We agree.
¶ 10 The CGIA requires a person claiming to have suffered an
injury by a public entity to file written notice with the entity within
182 days “after the date of the discovery of the injury, regardless of
whether the person then knew all of the elements of a claim or of a
cause of action for such injury.” § 24-10-109(1). The 182-day
deadline is jurisdictional, and because it is a non-claim provision, it
cannot be waived, tolled, or estopped. Mesa Cnty. Valley Sch. Dist.
No. 51 v. Kelsey, 8 P.3d 1200, 1206 (Colo. 2000). Thus, failure to
strictly comply with the CGIA’s notice requirements requires
dismissal of the action. See Crandall, 161 P.3d at 633-34; Reg’l
Transp. Dist. v. Lopez, 916 P.2d 1187, 1190-91 (Colo. 1996).
¶ 11 The CGIA’s notice period begins when a claimant “knew or,
through the exercise of reasonable diligence, should have known”
that she was wrongfully injured. Trinity, 848 P.2d at 927. The
claimant need not yet know the cause of the injury or the extent of
the damage. Gallagher v. Bd. of Trs. for Univ. of N. Colo., 54 P.3d
4 386, 391 (Colo. 2002), abrogated on other grounds by Martinez v.
Est. of Bleck, 2016 CO 58. Nor is the claimant required to know the
identity of the tortfeasor for the CGIA’s notice period to begin. See
E. Lakewood Sanitation Dist. v. Dist. Ct., 842 P.2d 233, 233-36
(Colo. 1992); Abrahamson v. City of Montrose, 77 P.3d 819, 821
(Colo. App. 2003).
¶ 12 Citing East Lakewood, 842 P.2d at 235-36, the district court
acknowledged in its order that “[a] claimant’s ignorance as to what
parties may bear responsibility for the injury is not a defense to the
notice deadline.” But the court nonetheless denied the motion to
dismiss, distinguishing East Lakewood on the basis that “Mostellar
could [not] reasonably have been expected to know that [Colorado
Springs] had any potential liability or to find out about the
intergovernmental agreement between the two municipalities other
than by proceeding as she did — giving Manitou Springs notice of
her claim and awaiting its response.” Under these circumstances,
the court concluded, it was required to follow the “squarely on
point” holding of State v. Young, 665 P.2d 108 (Colo. 1983), and
deny the motion to dismiss.
5 ¶ 13 For two reasons, we disagree with the district court’s reliance
on Young and conclude that Mostellar’s notice period under the
CGIA began to run on August 26, 2021, the date of her fall.
¶ 14 First, the district court’s adherence to Young does not
adequately account for the General Assembly’s 1986 decision to
amend section 24-10-109(1) in direct response to the supreme
court’s holding in that case. The amendment to section 24-10-
109(1) was intended, in part, to clarify that the CGIA’s notice period
is triggered by the discovery of the injury, and not by the discovery
of the legal theory for the plaintiff’s claim. See Lopez, 916 P.2d at
1192-93. Following the passage of this statutory amendment, an
injured party has the burden to “determine the cause of the injury,
to ascertain whether a governmental entity or public employee is
the cause, and to notify the governmental entity” within the
statutory time limit. Trinity, 848 P.2d at 927.
¶ 15 Nothing in Young suggests that a claimant’s ability — or
inability — to identify the governmental entity that caused her
injury has any bearing on the date on which the CGIA notice clock
starts. Indeed, there was never any question in Young that the
Colorado State Patrol was the entity responsible for allegedly
6 negligently misfiling the traffic ticket and summons that ultimately
led to the plaintiff’s unlawful arrest and her subsequent tort claim.
Instead, the holding in Young hinged on the supreme court’s
conclusion that the plaintiff could not have sought redress under
the CGIA until she received confirmation of the officer’s error via a
copy of the El Paso County Court docket. Young, 665 P.2d at 110
(“Young’s claim that the defendants negligently misfiled the original
traffic complaint and summons [that led to her arrest] could not
have been brought until Young discovered the alleged negligence
upon receipt of the docket sheet on March 17, 1978.”). That is,
although the plaintiff knew that she had been arrested, she did not
discover that her arrest was wrongful until she confirmed her
suspicions via the court docket. Accordingly, applying the pre-1986
version of section 24-10-109(1), the supreme court held that the
CGIA clock began running on the date that she received the docket
instead of on the date of her arrest. Id. at 111. Nowhere in Young,
however, do we see any suggestion that the statutory deadline
should be similarly extended in cases where the identity of the at-
fault governmental entity is not immediately clear. To the contrary,
the statute “imposes a mandatory requirement that claimants . . .
7 file a written notice within one hundred eighty[-two] days from the
date on which they discovered their injuries.” E. Lakewood, 842
P.2d at 236.
¶ 16 Second, there are material distinctions between the
circumstances in Young and the facts here. As we have already
noted, the Young court found it significant that the plaintiff could
not be certain that her arrest was wrongful until she received a
copy of the docket that allowed her to “discover[] the alleged
negligence.” Young, 665 P.2d at 110. There was no such
uncertainty in this case because, assuming the accuracy of the
allegations in the complaint, it would have been immediately
apparent that Mostellar’s fall and injury was the result of negligence
that met the CGIA’s definition of “injury.” See § 24-10-103(2),
C.R.S. 2024 (“‘Injury’ means . . . injury to a person, . . . of
whatsoever kind, which, if inflicted by a private person, would lie in
tort or could lie in tort . . . .”). Because Mostellar knew or should
have known that she was injured by falling over the remnant of the
sign, and because an injury caused by the dangerous condition of a
public sidewalk lies in tort or could lie in tort, see § 24-10-
8 106(1)(d)(I), C.R.S. 2024, the CGIA’s clock started running right
away.
¶ 17 We are not persuaded otherwise by Mostellar’s argument that
she should be deemed to have satisfied the notice requirement
because she investigated and pursued her claim with reasonable
diligence. Section 24-10-109(1) requires strict compliance with the
182-day deadline. Substantial compliance is not enough. See
Lopez, 916 P.2d at 1190 (“Failure to strictly comply with the 18[2]-
day notice requirement results in dismissal of the action.”); E.
Lakewood, 842 P.2d at 236 (“The General Assembly, by
incorporating the word ‘shall,’ indicated that the 18[2]–day time
requirement must be complied with as a jurisdictional
prerequisite.”); Armstead v. Mem’l Hosp., 892 P.2d 450, 452-53
(Colo. App. 1995) (rejecting plaintiff’s argument that “only
‘substantial compliance’ is required with respect to the notice given
by claimants pursuant to § 24-10-109(1),” and holding that “when a
party fails to establish that proper notice was provided in
compliance with the 18[2]–day notice requirement, the party’s
action must be dismissed”).
9 ¶ 18 Mostellar knew that she was wrongfully injured on August 26,
2021, and had the burden to investigate her claim and provide
CGIA-compliant notice to Colorado Springs within 182 days of that
date. Because she did not provide the required notice until 602
days had passed, she failed to strictly comply with the statutory
deadline and her complaint should have been dismissed for lack of
subject matter jurisdiction.1
IV. Attorney Fees
¶ 19 Colorado Springs also requests its attorney fees — incurred in
the district court and on appeal — under section 13-17-201, C.R.S.
2024. An award of attorney fees under that statute is mandatory
when a court dismisses a tort action under C.R.C.P. 12(b) before
trial. Crandall v. City & Cnty. of Denver, 238 P.3d 659, 663 (Colo.
2010). Appellate attorney fees are likewise mandatory. See Falcon
1 Like the special concurrence, we acknowledge that this is a harsh
result, and perhaps an inequitable one, under these circumstances. Nevertheless, we are bound by East Lakewood Sanitation District v. District Court, 842 P.2d 233, 233-36 (Colo. 1992), in which the supreme court held that the language of section 24-10-109(1), C.R.S. 2024, unambiguously requires strict compliance with the 182-day deadline.
10 Broadband, Inc. v. Banning Lewis Ranch Metro. Dist. No. 1, 2018
COA 92, ¶ 66.
¶ 20 Because we conclude that the district court did not have
subject matter jurisdiction over Mostellar’s complaint against
Colorado Springs, Colorado Springs is entitled to its reasonable
attorney fees incurred in the district court and on appeal. We
therefore remand this case to the district court to determine
Colorado Springs’s reasonable attorney fees. See C.A.R. 39.1.
V. Disposition
¶ 21 We reverse the district court’s order and remand the case with
directions to dismiss Mostellar’s tort claims and to determine
Colorado Springs’ reasonable attorney fees.
JUDGE LUM concurs.
JUDGE FREYRE specially concurs.
11 JUDGE FREYRE, specially concurring
¶ 22 While I agree with the majority’s reasoning and its application
of the law, I write separately to express my concern with the policy
implications of our decision and to suggest that the General
Assembly consider statutory modifications to section 24-10-109(1),
C.R.S. 2024, to address this concern.
¶ 23 The Colorado Supreme Court has made clear that the notice
provision of the Colorado Government Immunity Act (CGIA) should
not act as a “trap for the unwary,” Jefferson Cnty. Health Servs.
Ass’n v. Feeney, 974 P.2d 1001, 1003 (Colo. 1998), and that
“interpretations of the [C]GIA should not permit public entities to
manipulate the notice provision to dodge otherwise proper suits,”
Finnie v. Jefferson Cnty. Sch. Dist. R-1, 79 P.3d 1253, 1258 (Colo.
2003). While these cases concerned section 24-10-109(3), and not
the provision at issue here, section 24-10-109(1), the facts of this
case illustrate the real possibility that public entities can
manipulate the jurisdictional 182-day notice requirement by failing
to timely inform a plaintiff of intergovernmental agreements (IAs)
affecting jurisdiction.
12 ¶ 24 Cases interpreting section 24-10-109(1) have consistently held
that it is a non-claim statute not subject to equitable defenses such
as waiver, tolling, or estoppel, Mesa Cnty. Valley Sch. Dist. No. 51 v.
Kelsey, 8 P.3d 1200, 1206 (Colo. 2000), and that strict compliance
with its terms is required, Finnie, 79 P.3d at 1256. Such an
interpretation facilitates the public policy of “prompt investigation[]
of claims and remedies of dangerous conditions by public entities.”
E. Lakewood Sanitation Dist. v. Dist. Ct., 842 P.2d 233, 236 (Colo.
1992). And we reach the decision we do here because we are bound
by decisions of the supreme court. People v. Smith, 183 P.3d 726,
729 (Colo. App. 2008).
¶ 25 However, the facts of this case contradict this “prompt
investigation” policy and beg the question why it took the City of
Manitou Springs a year and a half to inform Mostellar of an IA that
was executed only a few months before her fall. The city’s delay
made it impossible for her to comply with section 24-10-109(1).
Moreover, the length of the delay raises the question whether the
IA’s existence was discoverable through the exercise of reasonable
diligence.
13 ¶ 26 Case law in the context of section 24-10-109(3) makes clear
that “[a]llowing public entities to mislead plaintiffs about how to
meet the requirements of the notice provision, and then to assert
the affirmative defense of noncompliance, is beyond the legitimate
purposes of the [C]GIA’s notice provision.” Finnie, 79 P.3d at 1258.
I see no reason why this same policy should not apply to section
24-10-109(1). Accordingly, I specially concur.