Moser v. Loeper

8 Pa. D. & C. 651, 1926 Pa. Dist. & Cnty. Dec. LEXIS 180
CourtPennsylvania Court of Common Pleas, Schuylkill County
DecidedSeptember 13, 1926
DocketNo. 15
StatusPublished

This text of 8 Pa. D. & C. 651 (Moser v. Loeper) is published on Counsel Stack Legal Research, covering Pennsylvania Court of Common Pleas, Schuylkill County primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moser v. Loeper, 8 Pa. D. & C. 651, 1926 Pa. Dist. & Cnty. Dec. LEXIS 180 (Pa. Super. Ct. 1926).

Opinion

Bekgek, J.,

William M. Moser, the claimant, filed a mechanic’s lien for material alleged to have been furnished and work and labor alleged to have been done in the erection and construction of the Loeper hotel building at Ashland, Pa., of which P. H. Loeper and Anton Loeper are the owners. The building, it is alleged in the lien, was erected and constructed by Stofflet and Tillotson, employed by the owners as contractors and builders. The architect was W. H. Lee, and Fegely and Moore erected the structural steel required for the building, pursuant to a contract with Stofflet and Tillotson. The lien claimant bases his claim upon a contract with Fegely and Moore, sub-contractors for the erection of the steel. The lien is entitled and entered against the owners only, who filed a petition and obtained a rule to show cause why it should not he stricken from the record for matters of fact specifically alleged in the petition. The claimant made answer to the petition, but did not traverse any of the material allegations of fact therein contained; his answer to the petition being, in substance, but not in form, a demurrer. And in his answer he also gave notice of an intended application to move for the amendment of the lien. The claimant’s answer to the rule to strike off, and his petition to amend, were filed April 5, 1926, and the same day a rule issued on the latter petition to show cause why the amendment should not be allowed. The owners, in effect, demurred to the petition to amend. After the questions raised or suggested by the parties had been presented to the court by oral argument and the submission of written briefs, the owners discovered that through inadvertence their petition to strike off the lien did not state that the claimant was a sub-subcontractor, and also that only one of six different items of claim for soft coal, twelve and one-half tons in the aggregate, delivered to the Loeper hotel premises by the claimant, had been attacked, whereas it was the intention of the owners to attack all such items. By agreement of the parties, the rule to strike off the lien has now been so amended as to raise properly the questions, first, whether the claimant is a sub-subcontractor, and, if so, whether this is fatal to the lien which he has filed; and, second, whether a right of lien exists for the soft coal furnished to the hotel premises during the course of the erection of the hotel.

The owners’ contention that the claimant is a sub-subcontractor not entitled to file a lien raises the controlling question in this case. In paragraphs 5 and 6 of his lien the claimant sets forth the basis of his alleged right of lien thus:

[652]*652“5. The name of the sub-contractor with whom claimant contracted is Fegely and Moore, the sub-contractors employed by Stofflet and Tillotson to erect the steel. Part of the work, to wit, the unloading and hauling of the structural steel, was also authorized by StofHet and Tillotson, through its superintendent, and the entire contract for work and materials furnished was, subsequent to its performance, ratified and approved by said Stofflet and Tillotson and said P. H. Loeper and Anton Loeper.
“6. Said work was done and materials furnished under and by virtue of a verbal contract made on Dec. 10, 1924, with Thomas W. Moore acting on behalf of said Fegely and Moore, by which it was agreed by and between said Fegely and Moore and claimant that said claimant should unload from cars and haul to the building site of the proposed Loeper Hotel all the structural steel at an agreed price of three ($3.00) dollars per ton. Said agreement was subsequently reduced to writing, as appears by Exhibit ‘A’ hereto attached and by reference thereto made part hereof. At the same time, it was also agreed that claimant should haul the equipment of said Fegely and Moore, then at Mt. Carmel, to Ashland, unload, by means of a steam shovel, other equipment, and any other miscellaneous hauling, at the usual prices for such work, and furnish so much soft coal as said Fegely and Moore required at'the rate of twelve ($12.00) dollars per ton, delivered at the building site. Claimant avers that the prices charged on Exhibit ‘B’ for the hauling and unloading by steam shovel were and are the usual prices for that character of work, and that the twelve and one-half (12i) tons of coal as delivered were ordered and accepted by said Fegely and Moore.”

Mechanics’ liens are purely of statutory origin, and complete compliance with statutory requirements is essential to their validity: Dyer v. Wallace, 264 Pa. 169. The right of a sub-subcontractor to a lien, if it exists, must, therefore, be conferred by the Act of June 4, 1901, P. L. 431, and its supplements. Section 1 of the Act of 1901 defines the words used to describe that which may be subject to and bound by mechanics’ liens, and defines or describes the parties to such liens, when the right of lien exists. A sub-contractor is defined as “one who, by contract or agreement, express or implied, with the contractor or with one who acts for him, superintends the structure or other improvement, or any part thereof; or furnishes labor, skill or superintendence thereto; or supplies or hauls material reasonably necessary for and actually used therein, or any or all of them, whether as superintendent, builder or materialman; excluding, however, architects and those contracting with materialmen.” A sub-contractor is, therefore, one who has no contract directly with the owner or his agent or agents. Section 2 of the act provides that every structure or other improvement and the appurtenant curtilage shall be subject to a lien for all debts due to the contractor or sub-contractor in the erection and construction thereof. It is to be noted that a sub-subcontractor is neither defined by the act nor mentioned as one who has a right of lien for any debt due him for work done or materials furnished in the erection and construction of any structure or other improvement.

The precise question in hand was considered in Harlan v. Rand, 27 Pa. 511, where Harlan, as owner, had a contract with Singerly for the construction of an entire building; Leeds, a sub-contractor under Singerly, the principal contractor, a contract for the instalment of all the heating apparatus; and Rand a contract under sub-contractor Leeds for the execution of a part of his (Leeds’) work, by furnishing work and materials necessary to the instalment of the heating apparatus; and it was held that the lien filed by Rand, a sub-subcontrator, had no validity. In Tebay v. Kirkpatrick, 146 Pa. 120, 123, [653]*653Sterrett, J., cited Harlan v. Rand, 27 Pa. 511, and in applying it to the Mechanics’ Lien Act of June 16, 1836, P. L. 696, said: “Claims of workmen and materialmen do not become liens on a building from the mere fact that the work was done or the materials furnished for its erection; they must be founded on a contract, express or implied, with the owner of the estate sought to be charged. The Lien Law of 1836 provides only for ‘debts contracted’ for work and materials: Section 1, Act of June 16, 1836, P. L. 696. When the owner employs a house-builder to erect a house for him, the parties are directly connected by contract, and the lien must be founded thereon. ‘It is the plain and obvious duty of one who deals with an alleged contractor to know the relation which he bears to the owner; failing in this, he furnishes labor and materials at his peril:’ Brown v. Cowan, 110 Pa. 588. Hence, it was said in Schroeder v. Galland, 134 Pa.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harlan v. Rand
27 Pa. 511 (Supreme Court of Pennsylvania, 1856)
McCay's Appeal
37 Pa. 125 (Supreme Court of Pennsylvania, 1860)
Duff v. Hoffman
63 Pa. 191 (Supreme Court of Pennsylvania, 1870)
Schenck v. Uber
81 Pa. 31 (Supreme Court of Pennsylvania, 1876)
Brown v. Cowan & Steele
1 A. 520 (Supreme Court of Pennsylvania, 1885)
Schroeder v. Galland
19 A. 632 (Supreme Court of Pennsylvania, 1890)
Goodfellow v. Manning
23 A. 1052 (Supreme Court of Pennsylvania, 1892)
Waters v. Wolf
29 A. 646 (Supreme Court of Pennsylvania, 1894)
Owen v. Johnson
34 A. 549 (Supreme Court of Pennsylvania, 1896)
Horn & Brannen Manufacturing Co. v. Steelman
64 A. 409 (Supreme Court of Pennsylvania, 1906)
Dyer v. Wallace
107 A. 754 (Supreme Court of Pennsylvania, 1919)
Mortar Co. v. Cassell
15 Pa. Super. 330 (Superior Court of Pennsylvania, 1900)
Tebay v. Kirkpatrick & Co.
23 A. 318 (Armstrong County Court of Common Pleas, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
8 Pa. D. & C. 651, 1926 Pa. Dist. & Cnty. Dec. LEXIS 180, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moser-v-loeper-pactcomplschuyl-1926.