Morton v. Union Traction Co.

20 Pa. Super. 325, 1902 Pa. Super. LEXIS 232
CourtSuperior Court of Pennsylvania
DecidedMay 22, 1902
DocketAppeal, No. 261
StatusPublished
Cited by9 cases

This text of 20 Pa. Super. 325 (Morton v. Union Traction Co.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morton v. Union Traction Co., 20 Pa. Super. 325, 1902 Pa. Super. LEXIS 232 (Pa. Ct. App. 1902).

Opinion

Opinion by

Rice, P. J.,

The plaintiff sued in assumpsit to recover an unpaid balance due upon a contract under which they erected a steel smokestack for the defendant. They sublet the work to one William M. Connery, but as the contract between the plaintiffs and the defendant provided that “ no subcontractor shall under any circumstances relieve the contractor” — meaning Morton Reed & Company — “of his liabilities or obligations under this contract,” the case is in the same situation, so far at least as the duty of Morton, Reed & Company to indemnify the defendant is concerned, as if they had performed the work. The defendant pleaded set-off, payment with leave, etc. On the trial of the case the plaintiffs offered in evidence a stipulation of counsel in which it was agreed, inter alia, as follows:

“ All the work required by the said contract to be performed by Morton, Reed & Company was by them performed and accepted by the defendant, but the defendant contends that Morton Reed & Company have not complied with the clauses of the contract relating to indemnifying the defendant.” The clauses of the contract here referred to will be discussed after we have disposed of the question, not distinctly suggested in the above stipulation, namely, as to the defendant’s right to contribution independently of the indemnity clause of the contract.

The defendant offered in evidence in support of its plea of set-off, a transcript of the record of the case, Verna R. Fetters v. Union Traction Company, in the United States Circuit Court, wherein she recovered a judgment in damages for the loss of the life of her husband, which judgment was paid by the defendant. The pleadings in that case are not printed, but from the evidence and the charge of the court, which are printed, there is no difficulty in ascertaining the ground of her recovery. [330]*330It appears that her husband was an employee of Keen and Frazier, who had a contract with the defendant for lining the stack in question with brick. After the metal work under Connery had been carried up a certain distance, the bricklayers under Keen and Frazier began their work. The metal work being carr ed on at the same time, Connery, at the instance of and pursuant to a special contract with the defendant, constructed a plank platform inside the stack to prevent tools and other things from dropping on the heads of the bricklaj'ers. Under its contract with the plaintiffs, the defendant had the fullest right of inspection as the work progressed. On the day of the accident its assistant engineer requested some of Connery’s men to remove one of the planks of this platform so that he might plumb the stack. This was done. Later in the day a heavy stringer or beam in the use, or under the control, of the metal workers was dislodged in some way, fell, and broke or passed through the protective platform and killed Fetters.

Whenever a plaintiff introduces and makes the record of an action, and a recovery therein against himself, the foundation of his suit or basis of his claim in an action brought by him afterwards against a third person, he is not at liberty to deny the principle upon which the action was decided: Weckerly v. Lutheran Congregation, 3 Rawle, 172. In order to ascertain what was passed upon by the jury, it is proper to examine the charge of the court filed of record in the case: Follansbee v. Walker, 74 Pa. 306. It will, therefore, be pertinent to quote from the charge to the jury in the Fetters case the instructions of the court as to the controlling questions in that case. At the outset of his charge the learned judge said, “We are not here to determine any other question than this, whether the' defendant is responsible; and we have nothing to do, I repeat, with the contingent liability of Morton, Reed and Company. So you may lay that aside in advance.”

Speaking of the original condition of the platform, he said: “ I see no evidence here that would justify the jury in finding that this protective platform was defectively constructed, either in the manner of its construction or in the materials selected; and therefore, even if the traction company were responsible for the erection of the platform, we should be obliged to say to you, and we do say, there is no evidence that it was insuífi[331]*331cient. ... We take it to have been, and you must take it to have been sufficient for the purposes for which it was erected.”

Speaking of the responsibility for the removal of the plank, he said: “ But I cannot agree with the defendant’s counsel in holding that the removal of that board was the work of the contractor. It was done, it is true, by persons who were in the employ of the contractor; but, as I understand, they were acting at that time under the direction of the engineer — or the assistant engineer, which is the same thing — in doing the work which the defendant itself was performing. The defendant itself was doing this work and it was interfering — properly enough, but still interfering — with the condition of the platform. Therefore, in my opinion, the men doing that work were doing it for the defendant.”

After careful instructions as to the questions of negligence to be determined by the jury, he concluded as follows: “ Now these are the questions — or perhaps it is more accurate to say, that is the question — in the case for you. It is the single question, whether under all the circumstances in this case the defendant used due and proper care to close this aperture, to restore this platform to the condition in which it found it. If it was neglectful; if, considering the danger to which the men were constantly exposed, it delayed an unreasonable time, then it may be responsible for what has happened in this case.”

In determining what was adjudicated in that case, we must presume that the jury obeyed the instructions of the court. Thus viewing the record we are warranted in saying that these points were adjudicated: First, the injury did not occur in consequence of any defect in the original construction of the protective platform or of any defect in, or inadequacy of, the materials used. Second, the traction company was responsible for the removal of the plank and for the failure to restore the platform to its original condition, and was negligent in not doing so. Third, if the traction company had not been negligent in this particular, the accident would not have happened; in other words, if a hole had not been left or the platform weakened by the removal of the plank, the beam or stringer would not have passed through and struck Fetters. But, fourth, the record in that case does not establish the fact that the injury was sustained in consequence of any joint, concurrent or independ[332]*332•ent negligence of the plaintiffs, their subcontractor or agents, in the construction of the work, or in guarding the same or in the use of improper materials, “ or by or on account of any act or omission” of the plaintiffs, their sub-contractor or agents. The ground of recovery in that case was the negligence of the traction company. The question whether the plaintiffs, their subcontractor or agents, were negligent, was not in issue and could not be decided by that jury. It was expressly excluded from their consideration by Judge McPherson’s charge. It follows that the record in that case does not, of itself, establish the recovery of damages for an injury with respect to which the traction company is entitled either to indemnity or to contribution from Morton, Reed & Company.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Babcock & Wilcox Co. v. Fischbach & Moore, Inc.
280 A.2d 582 (Superior Court of Pennsylvania, 1971)
Fisher v. United States
299 F. Supp. 1 (E.D. Pennsylvania, 1969)
Quinones v. TOWNSHIP OF UPPER MORELAND, ETC., PA.
187 F. Supp. 260 (E.D. Pennsylvania, 1960)
Southern Pacific Co. v. Layman
145 P.2d 295 (Oregon Supreme Court, 1943)
Pennsylvania Turnpike Commission v. U. S. Fidelity & Guaranty Co.
23 A.2d 416 (Supreme Court of Pennsylvania, 1941)
Boehm v. Northampton & Lehigh Counties
7 Pa. D. & C. 46 (Northampton County Court of Common Pleas, 1925)
Pennsylvania R. R. v. Roydhouse
110 A. 277 (Supreme Court of Pennsylvania, 1920)
Heman Construction Co. v. City of St. Louis
165 S.W. 1032 (Supreme Court of Missouri, 1914)
Sharpless v. Zelley
47 Pa. Super. 84 (Superior Court of Pennsylvania, 1911)

Cite This Page — Counsel Stack

Bluebook (online)
20 Pa. Super. 325, 1902 Pa. Super. LEXIS 232, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morton-v-union-traction-co-pasuperct-1902.