Mortenson v. Leatherwood Construction, Inc.

137 S.W.3d 529, 2004 Mo. App. LEXIS 971
CourtMissouri Court of Appeals
DecidedJune 29, 2004
Docket25514, 25515, 25516, 25517, 25518
StatusPublished
Cited by14 cases

This text of 137 S.W.3d 529 (Mortenson v. Leatherwood Construction, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mortenson v. Leatherwood Construction, Inc., 137 S.W.3d 529, 2004 Mo. App. LEXIS 971 (Mo. Ct. App. 2004).

Opinion

*531 JEFFREY W. BATES, Judge.

Defendanb-Appellant Leatherwood Construction, Inc. (“Leatherwood”) appeals from a judgment, entered after a consolidated bench trial, in which Leatherwood was ordered to pay double damages and attorney fees to Plaintiffs-Respondents Dwayne Mortenson, Mike Shannon, Jack Hiltibran, Alan Filip and Gilbert Lewis (hereinafter collectively referred to as “Workers”) for violating Missouri’s Prevailing Wage Act (“PWA”), §§ 290.210-290.340. 1 Leatherwood contends the trial court erred in determining that Leather-wood violated the PWA by not paying Workers the prevailing wage for an iron-worker during all three phases of a project to construct an addition to the public school in Norwood, Missouri. We affirm.

I. Standard of Review

As the judgment in favor of Workers was entered after a trial by the court, appellate review is conducted pursuant to Rule 84.13(d). 2 Therefore, we must affirm the trial court’s decision unless it is not supported by substantial evidence, it is against the weight of the evidence, or it erroneously declares or applies the law. Murphy v. Carron, 536 S.W.2d 30, 32 (Mo. banc 1976). 3 Ml evidence favorable to the judgment and all inferences to be drawn from the evidence are accepted as true, and all contradictory evidence is disregarded. Ridgway v. TTnT Development Corp., 126 S.W.3d 807, 812 (Mo.App.2004). Judging credibility and assigning weight to evidence and testimony are matters for the trial court, which is free to believe none, part, or all of the testimony of any witnesses. Savannah Place, Ltd. v. Heidelberg, 122 S.W.3d 74, 86 (Mo.App.2003). We defer to the trial judge’s superior opportunity to assess the witnesses’ credibility. Harris v. Lynch, 940 S.W.2d 42, 45 (Mo.App.1997). No such deference is afforded the trial court, however, when we review its conclusions of law. We independently evaluate whether the trial court properly declared or applied the law to the facts presented. Schubert v. Trailmobile Trailer, L.L.C., 111 S.W.3d 897, 899 (Mo. App.2003); Rathbun v. CATO Corp., 93 S.W.3d 771, 777 (Mo.App.2002).

II. Facts and Procedural History

In the Spring of 1999, the Norwood School District (“the District”) began accepting bids on a project to construct a three-story addition to the school. The District acted as its own general contractor on the project. The architectural plans for the addition specified that the building would have a structural steel skeleton, metal roof decking, masonry block walls set on a concrete foundation, and insulated metal siding installed over the masonry block.

In April 1999, Leatherwood submitted subcontractor bids for the structural steel, metal roofing and metal siding portions of the construction. In one bid, Leatherwood proposed to supply “all structural steel, bar joist, decking, purlins, stairs, handrails, bolts, no bulb tee, mise, steel, and standing seam roof with 4" vinyl insulation” and all labor necessary to install it for $272,000. In a separate bid document, Leatherwood also proposed to affix additional foam insulation to the block walls, install a hat channel system to hold the metal siding, and hang the metal siding on *532 the walls for $15,394. By installing insulation over the masonry blocks and then covering the insulation with metal siding, the energy efficiency of the building would be increased. Supporting documents submitted with Leatherwood’s bids described the work as the construction of a “steel building.” After Leatherwood reduced its bid for the structural steel and metal roof decking portions of the project to approximately $269,000, these two bids were accepted by the District.

Since this was a public works project, the PWA applied to the construction. Therefore, Leatherwood was required to comply with Annual Wage Order No. 5 issued by the Missouri Department of Labor Standards (“MDLS”). Section 118 of this order set prevailing wages for work performed by various occupational titles on public works projects within Wright County-

The “red iron” structural steel skeleton of the building and metal roof decking were supplied to Leatherwood by L & R Industries (“L & R”). The structural steel and metal roof components were delivered in packages to the job site by L & R on its trucks. The packages included the component metal parts, all hardware (i.e., nuts, bolts, screws, etc.) necessary to assemble the components, and instructions on how to put the parts together. Each metal part in the packages had its own unique identification number. Using the instructions, Workers unloaded the parts and stacked them in the yard by identification number so they could be retrieved sequentially to expedite construction. Each metal part was precut and predrilled so it could be easily assembled by bolting and/or welding with only minor adjustments required. Workers used the instructions and hardware to assemble these metal components without having to cut or alter the parts.

The metal siding used by Leatherwood on the project was supplied by Carr Ward Metal (“Carr”). The matérial was delivered to the job site by truck from Carr’s business in West Plains, Missouri. The metal siding was precut in incremental lengths because it was designed to go on a building with a pitched roof. There were two pieces of siding of each length to progress up the roofs pitch. These pieces were unloaded and divided into two piles so Workers could install one-half of the building’s siding at a time. The siding came with instructions and the necessary bolts to assemble it.

Workers first assembled the red iron skeleton of the building using the components, hardware and instructions supplied by L & R. After this phase of the project was completed, another contractor poured the concrete foundation and constructed the masonry block walls. The budding’s doors and windows were framed and installed by employees of the masonry block contractor. Once the walls were finished, Workers installed the metal roof using the component parts, hardware and instructions supplied by L & R. Finally, Workers installed the insulation, hat channel and metal siding on the building.

The dispute in this case arose because of a disagreement between Leatherwood and Workers concerning their rate of pay during the three phases of construction. When Workers assembled the red iron skeleton and metal roof decking of the building, Leatherwood paid them the prevailing wage for an ironworker. When Workers installed the metal siding on the building, however, Leatherwood paid them the prevailing wage for a sheet metal worker.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

GARY TURNER, Plaintiff-Respondent v. JANET L. WESSLAK and ROBERT WESSLAK
453 S.W.3d 855 (Missouri Court of Appeals, 2014)
Baker v. Walnut Bowls, Inc.
423 S.W.3d 293 (Missouri Court of Appeals, 2014)
City of Cape Girardeau ex rel. Kluesner Concreters v. Jokerst, Inc.
402 S.W.3d 115 (Missouri Court of Appeals, 2013)
Spears ex rel. Clendening v. Freeman Health Systems
403 S.W.3d 616 (Missouri Court of Appeals, 2012)
Entergy Gulf States, Inc. v. Summers
282 S.W.3d 433 (Texas Supreme Court, 2009)
Holtcamp v. State
259 S.W.3d 537 (Supreme Court of Missouri, 2008)
Surrey Condominium Ass'n, Inc. v. Webb
163 S.W.3d 531 (Missouri Court of Appeals, 2005)
Ewanchuk v. Mitchell
154 S.W.3d 476 (Missouri Court of Appeals, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
137 S.W.3d 529, 2004 Mo. App. LEXIS 971, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mortenson-v-leatherwood-construction-inc-moctapp-2004.