Morrisville Hydroelectric Proj Water Quality - Decision on Motions

CourtVermont Superior Court
DecidedMarch 14, 2018
Docket103-9-16 Vtec
StatusPublished

This text of Morrisville Hydroelectric Proj Water Quality - Decision on Motions (Morrisville Hydroelectric Proj Water Quality - Decision on Motions) is published on Counsel Stack Legal Research, covering Vermont Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrisville Hydroelectric Proj Water Quality - Decision on Motions, (Vt. Ct. App. 2018).

Opinion

STATE OF VERMONT SUPERIOR COURT ENVIRONMENTAL DIVISION Docket No. 103-9-16 Vtec

Morrisville Hydroelectric Project Water Decision on Motions Quality

The present appeal is from a water quality certification issued by the Agency of Natural Resources to Morrisville Water and Light for the Morrisville Hydroelectric Project located on the Lamoille River and its tributaries in northern central Vermont. Morrisville Water and Light appealed the certification to this Court. The matter presently before the Court is the Agency of Natural Resources’ (ANR) motion for summary judgment on Questions 4, 7, 9, 10, 11, 12, 13 raised by Morrisville Water and Light (MWL).1 Findings of Fact We recite the following factual findings solely for the purpose of ruling on the pending motion. 1. On September 9, 2015, MWL submitted an application for water quality certification to ANR for hydroelectric facilities located on the Lamoille River and its tributaries (the Project). 2. The Project consists of the Morrisville Facility, the Cadys Falls Facility, the Green River Facility, and the Lake Elmore Facility. 3. On August 9, 2016, ANR issued a water quality certification to MWL with conditions regarding the Clean Water Act and the Vermont Water Quality Standards (VWQS). 4. The Project does not affect any high-quality waters as defined by the VWQS.

1 ANR has titled their motion as a motion for summary judgment. The motion, and ANR’s reply to Morrisville’s opposition, however, requests “summary dismissal” and summary judgment on Questions 4, 7, 9, 12, and 13. MWL asserts that this motion is actually a motion in limine, because in addition to requesting judgment on these questions, the motion seeks to preclude MWL from presenting certain evidence at trial. We decline to interpret the motion in this manner and instead read the motion in its entirety as a motion for summary judgment because ANR requests judgment on all questions.

1 5. The Project additionally operates pursuant to a license issued by the Federal Energy Regulatory Commission (FERC), originally issued in 1981 (Project 2629). 6. Pursuant to the FERC license, MWL is required, within five years from the date of issuance of the license, to “acquire title in fee with the right in perpetuity all lands, other than lands of the United States, necessary or appropriate for construction, maintenance, and operation of the Project.” MWL must also hold “all riparian or other rights that are necessary or appropriate in the operation or maintenance of the project.” 7. On March 30, 1999, the State of Vermont conveyed to MWL by warranty deed an interest in approximately 5,110 acres in the towns of Hyde Park and Eden, Vermont. 8. Part of this conveyance included land “around (but not beneath)” the Green River Facility. Standard of Review The Court may grant summary judgment to a party “if the movant shows that there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” V.R.C.P. 56(a), applicable here through V.R.E.C.P. 5(a)(2). When determining if there is a genuine dispute as to any material fact, “we will accept as true the allegations made in opposition to the motion for summary judgment, so long as they are supported by affidavits or other evidentiary material.” Robertson v. Mylan Labs., Inc., 2004 VT 15, ¶ 15, 176 Vt. 356 (citation omitted). The nonmoving party also receives the benefits of all reasonable doubts and inferences. Id. Discussion I. Whether the Court’s June 13, 2017 Decision precludes MWL from raising issues of practicability

In a June 13, 2017 decision, we determined that “state and federal water quality laws do not authorize consideration of economic or social factors in this case.” In re Morrisville Hydroelectric Project Water Quality, No. 103-9-16, slip op. at 14 (Vt. Super. Ct. Envtl. Div. Jun. 13, 2017) (Walsh, J.). This determination still stands and, therefore, any questions that directly raise social or economic considerations are not properly before the Court. ANR asserts that Questions 4, 7, 9, 12, and 13 implicitly address social and economic concerns and, therefore, they are entitled to judgment pursuant to our June 13, 2017 decision.

2 MWL disagrees, arguing that these questions raise issues regarding practicability that are properly before the Court. These questions do not explicitly ask whether social and economic factors should be considered.2 As such, these questions address issues that are properly before the Court. To the extent that they implicitly raise these issues, the Court’s June 13, 2017 determination remains in effect. For these reasons, ANR’s motion for summary judgment on Questions 4, 7, 9, 12, and 13 is DENIED. The Court looks forward to the parties’ presentation of evidence on issues properly before us at trial. Nothing in this decision limits the parties’ rights at trial to raise objections to evidence implicating social and economic considerations. The Court will rule on such evidentiary issues at that time. II. Whether MWL’s deed prevents ANR from regulating the Project Question 11 asks the Court to determine if ANR is estopped from imposing conditions on various aspects of the Green River Facility because of language included in MWL’s deed from ANR. ANR now moves for judgment on this question claiming MWL’s retention of private property rights cannot estop ANR from enforcing reasonable governmental regulation of the Project.

2 The challenged questions read as follows: Question 4: “[w]hether the bypass flow conditions for the Morrisville and Cady’s Falls facilities are in excess of what is necessary to provide a “high quality aquatic habitat,” pursuant to [the VWQS] § 3-04.A.1, and whether lower bypass flows would provide such habitat and meet all applicable requirements of the [VWQS], including considerations set forth in ANR Streamflow Procedure, Part E—Hydroelectric and Hydromechanical. Question 7: “[w]hether ANR’s condition requiring spilling water over the crest of the Morrisville and Cady’s Falls dams for aesthetic purposes is appropriate, given the limited visibility to the public and the extreme difficulty of complying with this condition.” Question 9: “[w]hether the Water Quality Certification should be revised to specifically allow new flow and water level management conditions to be phased in over an extended period of time (10 years) to accommodate engineering design, permitting and construction improvements needed to implement new conditions.” Question 12: “[r]egarding the Green River facility, whether ANR failed to adequately consider the requirements of the Hydrology Criteria (VWQS § 3-01.C), the Class B Waters Management Objectives (VWQS § 3- 04.A), and the Anti-Degradation Police (VWQS § 1-03) with respect to providing for adequate flows that fully support and maintain the use of the waters for boating, commercial activity (which includes hydroelectric power generation), and other recreation.” Question 13: “[f]or all facilities, whether less significant changes to existing operations, that result in less of a loss to renewable energy generation, would meet the [VWQS].”

3 The State, through ANR, conveyed to MWL by warranty deed a parcel of land in the towns of Hyde Park and Eden in 1999. MWL asserts that their deed precludes ANR from regulating the Project. The deed includes, in relevant part, a clause in which MWL retained the right to raise or lower the reservoir’s water level and generally regulate the cycle of water.3 As a general matter, “all contracts entered into, all charters granted, all rights possessed and all property held are subject to the proper exercise of [the State’s] police power, and must submit to its valid regulations and restrictions.” Vermont Woolen Corp. v. Wackerman, 122 Vt. 219, 224 (1961) (citing State v. Quattropani, 99, Vt. 360, 363 (1926)).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Vermont Woolen Corporation v. Wackerman
167 A.2d 533 (Supreme Court of Vermont, 1961)
Robertson v. Mylan Laboratories, Inc.
2004 VT 15 (Supreme Court of Vermont, 2004)
In Re McDonald's Corp.
505 A.2d 1202 (Supreme Court of Vermont, 1985)
In re Appeal of Griffin
2006 VT 75 (Supreme Court of Vermont, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
Morrisville Hydroelectric Proj Water Quality - Decision on Motions, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrisville-hydroelectric-proj-water-quality-decision-on-motions-vtsuperct-2018.