Morrison v. Union Indemnity Co.

161 S.E. 418, 163 S.C. 137, 1931 S.C. LEXIS 15
CourtSupreme Court of South Carolina
DecidedNovember 17, 1931
Docket13278
StatusPublished

This text of 161 S.E. 418 (Morrison v. Union Indemnity Co.) is published on Counsel Stack Legal Research, covering Supreme Court of South Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison v. Union Indemnity Co., 161 S.E. 418, 163 S.C. 137, 1931 S.C. LEXIS 15 (S.C. 1931).

Opinion

The opinion of the Court was delivered by

Mr. Justice Cothran.

This is an action, commenced October 17, 1929, upon a contractor’s bond, dated June 4, 1928, signed by the defendant Powers, the contractor, as principal, and the defendant ¡Union Indemnity Company, as surety, for faithful performance by the contractor of a contract entered into between him and the plaintiffs, trustees of school district No. 1, McClellanville, S. C., providing for certain alterations of and additions to the schoolhouse, dated May' 22, 1928, at the contract price of $10,960.00, the bond being in the sum of $5,480.00, the date of completion being fixed at September 15, 1928.

The plaintiffs alleged in the complaint an abandonment of the contract by the contractor and a completion of it by them at a cost of $3,641.80 in excess of the contract price, for which they demanded judgment.

The defendant company answered admitting the building contract, the bond, the default of Powers, and the completion of the work by the trustees. The answer further alleged that, subsequent to Powers’ abandonment of the work, the *140 plaintiffs and the defendant made a written contract whereby plaintiffs assumed the completion of the work and discharged the surety from further responsibility, therefor, the surety agreeing to save the plaintiffs harmless from pecuniary loss through claims arising out of work done by Powers, provided they were such claims as the surety was already liable for under the bond. The answer alleged that the surety had performed all the obligations imposed on it by the bond as modified by said contract.

To this answer the plaintiffs replied, admitting the execution of the contract set up in the answer, but alleging that it was void because procured by the fraud of the bond company; Vetsch, a representative of the company, went to McClellanville and met with the plaintiffs; that he proposed that his company pay all existing bills for material and the like amounting to $2,528.41 and that the plaintiffs assume the completion of the work and free the company from further responsibility; that this proposal was agreed to by plaintiffs; that Vetsch fraudulently procured the drafting of the contract attached to the answer of the company, which differed radically from the agreement actually made; that Vetsch- then sought out the plaintiffs separately and procured their signatures to the contract by representing to them that it stated the agreement already made, and that it had been approved by .the attorney for the county superintendent of education; that the company subsequently repudiated its agreement to pay the bills amounting to $2,528.41.

The case was tried before his Honor, Judge Mauldin, February, 1931, the trial resulting in a vetdict in favor of the plaintiffs for $2,528.41. From the judgment entered upon this verdict, the defendant bond company has appealed.

The condition of the bond was thus stated: “The condition of the foregoing obligation is such that, if the said principal shall well and truly indemnify and save harmless the said obligee from any pecuniary loss resulting from the breach of any of the terms, covenants and conditions of the *141 said contract on the part of the said principal to be performed, then this obligation shall be void; otherwise to remain in full force and effect in law; provided, however, that this bond is issued subject to the following conditions and provisions: * * * That in case of such default on the part of the principal the surety shall have the right, if it so desires, to assume and complete or procure the completion of said contract, and shall be subrogated and entitled to all the rights and properties of the principal arising out of the said contract and otherwise, including all securities and indemnities theretofore received by the obligee, and all deferred payments, retained percentages and credits, due to the principal at the time of such default, or to become due thereafter by the terms and conditions of the contract. * * * That in no event shall the surety be liable to another than the obligee, or for a greater sum than the penalty of this bond, or be subject to any suit, action or other proceeding thereon that is instituted later than the 15th day of September, A. D. 1928. * * * ”

Shortly after the execution and delivery of the bond (dated June 4, 1928) Powers, the contractor, entered upon the performance of the contract. On or about September 11th, four days before the date fixed for its completion, Powers abandoned the contract, and on that day the trustees notified the bond company of the abandonment, and called upon it, “as surety to have this contract completed and the building delivered to our board without further delay,” expressing the opinion that, with the funds in their hands applicable to the contract, the work could be completed with very little cost to the bonding company. (It will be observed, in passing, that this demand was not justified by the terms of the bond, which gave the bonding company the option, “if it so desires, to assume and complete or procure the completion of said contract.”)

The bonding company did not respond to the suggestion of the trustees that it take over and complete the building, *142 and on October 1st Benson, the architect in charge of the building, wrote to the bonding company on behalf of the trustees, reiterating the demand of the trustees. He appears to have been under the same misapprehension that had seized the trustees as is shown by this paragraph in his letter: “In the circumstances you know that the board is without power or authority to make any move at all towards completing the building; the matter is up to the surety to complete the work, or to authorize them to have the building completed, charging to your company what amount over and above .the contract price that may be required to do this.”

He suggested a conference between the bond company and the trustees with a view of arriving at an understanding. Accordingly, on October 8th, after the work had been at a standstill for over three weeks, a meeting was arranged, attended by Vetsch, as representative of the bond company, McCarley, the county superintendent of education, Benson, the architect in charge, Morrison, chairman of the board of trustees, and Graham, secretary of the board. (It appears that Lofton, the third member of the board, did not attend.)

It seems very sure that an agreement was reached among the persons who attended that meeting, but exactly what it was, is a matter of controversy. The main objects, however, appear to have been attained; that the bond company would waive its option to take over and complete the building; that the trustees should take over and complete the building with the funds on hand, and be relieved of any liability which they might have incurred upon outstanding claims of persons who had furnished material and supplies to Powers prior to his abandonment of the contract, amounting to $2,528.41; and that the bond company should be released from further liability upon the bond.

The real point of attrition between the parties is whether the agreement claimed to have been made on October 8th altered the terms of the bond (which limited the obligation of the bond company to an indemnity to the trustees alone), *143

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Carmichael v. Carmichael
96 S.E. 526 (Supreme Court of South Carolina, 1918)
Crum Et Ux. v. Jenkins
143 S.E. 21 (Supreme Court of South Carolina, 1928)
Stouffer v. Erwin
62 S.E. 843 (Supreme Court of South Carolina, 1908)
Windham v. Black Creek School District No. 9
141 S.E. 896 (Supreme Court of South Carolina, 1928)
Trimble v. Carlisle
88 S.E. 28 (Supreme Court of South Carolina, 1916)
Piper v. American Fidelity & Casualty Co.
154 S.E. 106 (Supreme Court of South Carolina, 1930)
Benn v. Camel City Coach Co.
160 S.E. 135 (Supreme Court of South Carolina, 1931)

Cite This Page — Counsel Stack

Bluebook (online)
161 S.E. 418, 163 S.C. 137, 1931 S.C. LEXIS 15, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-v-union-indemnity-co-sc-1931.