Morrison v. Ultican

213 P.2d 617, 35 Wash. 2d 504, 1950 Wash. LEXIS 478
CourtWashington Supreme Court
DecidedJanuary 19, 1950
Docket30915
StatusPublished
Cited by3 cases

This text of 213 P.2d 617 (Morrison v. Ultican) is published on Counsel Stack Legal Research, covering Washington Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison v. Ultican, 213 P.2d 617, 35 Wash. 2d 504, 1950 Wash. LEXIS 478 (Wash. 1950).

Opinion

Mallery, J.

Victor Morrison, owner of Grays Harbor Public Log Dump, Inc., hereinafter called Log Dump, brought this action for accounting against defendants, the other partners in Ulmidmor, a partnership. Plaintiff appeals from a judgment in favor of the defendants.

In 1943, respondents, timber owners and sawmill operators, were strongly motivated to expedite logging and milling in the Grays Harbor area to meet their commitments on war-time contracts. Log Dump was engaged in performing three logging contracts hereinafter called the Weyerhaeuser, Ultican and Saginaw contracts. The first two were to be performed prior to December 31, 1944, the latter prior to November 30,1944. This litigation concerns a plan which, from respondents’ point of view, was an auxiliary device to assure them a ready source of urgently needed lumber.

November 18, 1943, appellant and respondents joined to form the partnership Ulmidmor for the exclusive purpose of assuring performance of these Log Dump contracts. Appellant and respondent Ultican contributed thirty thousand dollars each; the others contributed the balance of the total ninety thousand dollars of contributed capital. The partnership contract provided for profit and loss sharing in proportion to capital contribution, for control by partners representing a majority of contributed capital, for no borrowing without written consent of all partners, and for dissolution on completion of Ulmidmor’s exclusive purpose.

The same day, Ulmidmor contracted to finance and equip Log Dump for the performance of its three contracts. In exchange, Log Dump promised faithfully to perform its three contracts, to channel all contract payments through *506 Ulmidmor and to pay Ulmidmor fifty cents a thousand for timber delivered under the contracts. The contract also provided that upon Log Dump’s default on any of the logging contracts, Ulmidmor could assume control of Log Dump’s operations to complete performance thereof.

Pursuant to the contract, Log Dump, with Ulmidmor’s money and equipment, commenced logging the three tracts. Substantial amounts of timber were felled and bucked under each contract.

Late in 1944 appellant became dissatisfied. Accentuated by the dual relationships of the several partners, especially that of Mr. Ultican, personal differences between appellant and respondents became especially acrimonious when Log Dump failed to complete any of its contracts on time.

Weyerhaeuser was willing to extend its contract with appellant. Ulmidmor contended that it had the right to make the extension but Weyerhaeuser dealt exclusively with Log Dump. The Weyerhaeuser-Log Dump one year extension included financial provisions repugnant to the Ulmidmor-Log Dump contract.

January 1,1945, Mr. Ultican, as timber owner, terminated his Log Dump contract by forfeiture.

The Saginaw contract was not terminated.

Eager to complete the Weyerhaeuser logging within the year extension, Log Dump subcontracted with other loggers and continued Weyerhaeuser operations. Appellant disapproved of Ulmidmor’s further activities in securing performance of the Ultican and Saginaw contracts on the ground that they would prove unprofitable.

Ulmidmor, on the other hand, motivated by respondents’ interest in early availability of lumber to meet their contract commitments, assumed control of Log Dump’s logging operations, in accordance with Ulmidmor-Log Dump contract, and continued Ultican and Saginaw logging.

During this period of disagreement, the parties, seeking harmony, negotiated in vain for a revision of the partnership contract.

January 30, 1945, Saginaw contracted with Ulmidmor to extend the Saginaw-Log Dump contract to October 31,1945, *507 and Ulmidmor, as Log Dump’s assignee, promised to complete the logging by that date. This extension, signed by all the partners, recited that Ulmidmor was also logging Ultican’s tract.

To implement its decision to log Ultican and Saginaw, Ulmidmor subcontracted with loggers to do the work. Appellant signed this subcontract, also.

In July, 1945, fire destroyed machinery and logs and damaged standing timber on the Ultican and Saginaw tracts. Prior to the fire the logging was profitable; thereafter it was not.

October 8, 1945, appellant, by letter to each copartner, expressed dissatisfaction with Ulmidmor’s management, explained that he signed Ulmidmor’s subcontract with the loggers on the condition that the partnership contract would be revised, a condition which had not occurred, disclaimed liability on all operations beyond the scope of the partnership contract, and expressed eagerness to proceed with Ulmidmor’s dissolution as soon as he had completed Weyerhaeuser’s logging. This was not appellant’s only expression of dissatisfaction, but it is the most definitive formal effort made to limit his liability prior to commencement of this action.

Eventually, Ultican and Saginaw logging was completed at great loss. The final balance sheet revealed exhaustion of all contributed capital as well as debts of about twenty thousand dollars to third parties and to Messrs. Ultican and Middleton on advances.

Appellant is unwilling to bear his share of the loss. He disclaims liability as a partner and seeks adjustments in the final accounting on certain items of loss to which he did not specifically consent.

Trial was held in two phases. In the first it was held that Ulmidmor was not dissolved prematurely by appellant’s acts and that he was a partner during its entire existence. In the second phase it was held that the accounting, as evidenced by the final balance sheet, was substantially correct and that appellant was not entitled to any adjust *508 ments, there being no fraud or breach of duty, and that he was liable to the liquidator for an amount in excess of five thousand dollars as his share of the losses.

Implicit in each of appellant’s assignments of error is the contention that, either at the point when the Ulmidmor-Ultican contract was made, or when respondents borrowed and advanced money in violation of the partnership contract, or after appellant’s October 8, 1945, letter, appellant ceased to be a partner with a partner’s liabilities.

Appellant’s expressions of dissatisfaction over respondents’ breach of the partnership contract by the making of the Ulmidmor-Ultican contract were equivocal. He consented to the variance from the partnership contract by signing the Ulmidmor-Saginaw contract and Ulmidmor’s subcontract with the loggers who were to perform the Ultican and Saginaw logging. The October 8th letter, upon which appellant strongly rélies, does not dissolve the partnership or terminate his liability, since it admits his status as partner and expresses eagerness for early dissolution of the partnership, thus acknowledging its continued existence on that date. The letter’s denial of liability on Saginaw and Ultican operations is equivocal in view of appellant’s signature on the Ulmidmor-Saginaw contract and on the logger’s subcontract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Day v. Sidley & Austin
394 F. Supp. 986 (District of Columbia, 1975)
Richert v. Handly
330 P.2d 1079 (Washington Supreme Court, 1958)
In Re the Estate of Wilson
315 P.2d 287 (Washington Supreme Court, 1957)

Cite This Page — Counsel Stack

Bluebook (online)
213 P.2d 617, 35 Wash. 2d 504, 1950 Wash. LEXIS 478, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-v-ultican-wash-1950.