Morrison-Knudsen Company v. Wingate

492 S.E.2d 122, 254 Va. 169, 1997 Va. LEXIS 97
CourtSupreme Court of Virginia
DecidedSeptember 12, 1997
DocketRecord 961606
StatusPublished
Cited by2 cases

This text of 492 S.E.2d 122 (Morrison-Knudsen Company v. Wingate) is published on Counsel Stack Legal Research, covering Supreme Court of Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrison-Knudsen Company v. Wingate, 492 S.E.2d 122, 254 Va. 169, 1997 Va. LEXIS 97 (Va. 1997).

Opinion

CHIEF JUSTICE CARRICO

delivered the opinion of the Court.

In this slip-and-fall case, a jury awarded the plaintiff, Alton Bruce Wingate, a verdict for $300,000 against the defendants, Morrison-Knudsen Company, Inc. and Eugene W. Kelsey & Son, Inc., a joint venture operating under the name of Kelsey & Associates. The trial court entered judgment on the verdict, and we awarded the defendants an appeal.

*171 The plaintiff was injured when he slipped and fell on an outside stairway at Building 1949 in a housing complex at the Naval Weapons Station in Yorktown. Building 1949 was one of 36 two-story buildings containing a total of 232 housing units for which the defendants were awarded a construction contract by the United States Navy Department in 1981. Pursuant to the contract, the defendants acted as architect and designer as well as general contractor for the project, including the exterior stairways.

Building 1949 was the first structure erected, and it was used as a prototype for the remaining thirty-five buildings. The second-floor units in each building were reached by an exterior stairway in the shape of a “Y,” with the leg of the “Y” joined to the arms by a landing located approximately one-third of the way up the stairs.

The original shop drawings for the prototype stairway specified a “steel trowel finish” for the precast concrete treads and landing, meaning that the finish would be “relatively smooth,” and the treads and the landing on the stairway in Building 1949 were finished in this manner. However, after Building 1949 was completed, “the Navy . . . decided [it] wanted broom finish instead of steel-trowel finish” on the stair treads, and a change order was issued directing the replacement of “[s]tair treads at Bldg. 1949.” A note on the change order stated that the “[o]riginal stair treads were smooth [and should] have been rough texture.” The change order made no mention of the landing on the stairway in Building 1949.

The stair treads in Building 1949 were replaced with treads having a “broom finish,” meaning that “you still trowel [the concrete], and then you run a broom over it to get a slight texture.” 2 C.H. Morgan, the framing subcontractor who originally erected the prototype stairway, was employed to do the replacement work. He asked a representative of the defendants why the landing was not being replaced and was told that the surface of the landing would be roughened by application of an epoxy material. However, the finish on the landing was still smooth when he examined it some time later.

The plaintiff was employed by a private commercial firm to perform maintenance work at the housing complex after it was completed. On August 14, 1984, he had been working in a second-floor unit of Building 1949 when it began to rain. Walking briskly down the stairway to raise the windows on his van, he slipped on the wet *172 landing and fell to the bottom of the stairs, suffering the injuries for which he sought damages in the action filed below. He examined the landing the day after he fell and found it was composed of “real smooth concrete,” unlike the “rough, broom-finished concrete” on the steps.

On appeal, the defendants argue that actionable negligence requires proof of a legal duty to exercise ordinary care for the safety of another person, a,breach of that duty, and an injury proximately resulting from the breach. The defendants say that the plaintiff was required to establish by the use of expert testimony what duty they owed him as designers and general contractors, yet the plaintiff failed to produce such expert testimony. Furthermore, the defendants submit, there was no showing that they breached any duty they owed the plaintiff; he produced no evidence to show that the trowel finish was unfit or unsafe for use on an exterior landing or that the trowel finish constituted a defect in the premises. Hence, the defendants conclude, their motions to strike and for summary judgment, made below, should have been granted.

The plaintiff responds that expert testimony was not required to establish the defendants’ duty because this is a case “in which the facts and circumstances are within the common understanding and experience of the average lay juror.” The plaintiff maintains that “[f]or a proper statement of the duty owed to a person injured by a defective condition created by a contractor, the court must look to tort law and apply the objective standard of the reasonably prudent man.”

Here, the plaintiff says, there was “ample evidence from which the jury could conclude that [the defendants] failed to use ordinary care in creating and failing to repair the condition that caused [the plaintiff’s] injury.” The evidence showed, the plaintiff submits, that the defendants failed to use ordinary care “in (1) designing a stairway composed of a smooth concrete surface exposed to the weather, (2) replacing all but one surface when the owner rejected it as too smooth, and (3) failing to perform the repair they arranged for (application of epoxy).” Hence, the plaintiff concludes, the trial court did not err in refusing to grant the defendants’ motions to strike and for summary judgment.

For purposes of this discussion, we will assume, without deciding, that the plaintiff is correct in his assertion that expert testimony was not required to prove what duty the defendants owed him, and we will agree with the plaintiff that the defendants owed him the *173 duty of ordinary care. Yet, there remained upon the plaintiff the burden of showing a breach of that duty by producing evidence of a non-expert nature establishing that the smooth finish on the landing in the stairway of Building 1949 constituted what the plaintiff calls “a hazardous condition . . . created by [the defendants] which they failed to repair.”

We are of opinion that the plaintiff failed to carry his burden. Indeed, at best, the plaintiff’s evidence may be described as sketchy. He cites the testimony of the defendants’ quality control officer that there is no custom in the building industry concerning broom-finished versus trowel-finished concrete. The plaintiff also cites the testimony of the defendants’ project manager to the effect that he was unfamiliar with building code requirements. The plaintiff then argues that if the defendants could have shown that they had complied with applicable industry standards or building codes, “they would have done so.”

The difficulty with this argument is that the burden was not upon the defendants to show that they complied with industry standards or building codes, if any were applicable. Rather, the burden was upon the plaintiff to show that the defendants deviated from the standard of ordinary care, either by failing to observe applicable trade customs and building code provisions or by some other defalcation.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Federico v. Lincoln Military Housing, LLC
127 F. Supp. 3d 623 (E.D. Virginia, 2015)
Foglia v. Clapper
885 F. Supp. 2d 821 (E.D. Virginia, 2012)

Cite This Page — Counsel Stack

Bluebook (online)
492 S.E.2d 122, 254 Va. 169, 1997 Va. LEXIS 97, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrison-knudsen-company-v-wingate-va-1997.