Morris v. Ohio Dept. of Transp.

2010 Ohio 3147
CourtOhio Court of Claims
DecidedMarch 5, 2010
Docket2009-08501-AD
StatusPublished

This text of 2010 Ohio 3147 (Morris v. Ohio Dept. of Transp.) is published on Counsel Stack Legal Research, covering Ohio Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morris v. Ohio Dept. of Transp., 2010 Ohio 3147 (Ohio Super. Ct. 2010).

Opinion

[Cite as Morris v. Ohio Dept.. of Transp., 2010-Ohio-3147.]

Court of Claims of Ohio The Ohio Judicial Center 65 South Front Street, Third Floor Columbus, OH 43215 614.387.9800 or 1.800.824.8263 www.cco.state.oh.us

MICHAEL P. MORRIS

Plaintiff

v.

OHIO DIVISION OF TRANSPORTATION

Defendant

Case No. 2009-08501-AD

Deputy Clerk Daniel R. Borchert

MEMORANDUM DECISION

{¶ 1} Plaintiff, Michael P. Morris, filed this action contending his company car, a 2010 Chevrolet Malibu was damaged on September 25, 2009 as a proximate cause of negligence on the part of defendant, Department of Transportation (ODOT), in maintaining State Route 608 in an area where roadway construction activity was being conducted. Specifically, plaintiff explained the vehicle was damaged when the front facia shield on the car struck a transition area on the roadway where a section of pavement that had been milled met an area where existing pavement remained intact. Plaintiff described this roadway transition area as “a very pronounced lip” and observed that when the front end of the car contacted with the transition the impact pushed the facia shield into the vehicle’s air conditioning condenser damaging both parts. Plaintiff located the damage-causing incident at “southbound on Route 608 [a]t the junction of Lake (County) and Geauga (County) just before Radcliff Road.” Plaintiff recalled there were no construction workers present at the time of the property damage event (approximately 10:00 p.m. on Friday, September 25, 2009) and he was “driving below the posted speed limit due to the darkness, the construction, and the deer in the area.” Plaintiff filed this complaint seeking to recover damages in the amount of $816.85, the cost of automotive repair expense he incurred as a result of the described incident. Plaintiff advised the 2010 Chevrolet Malibu is owned by his employer, Tim Lally Chevrolet, Inc., but he is responsible for property damage to the vehicle “up to $1,000.00.” The $25.00 filing fee was paid. {¶ 2} Defendant acknowledged that the stated area where plaintiff’s described damage event occurred was located within the limits of a construction project under the control of ODOT contractor, Kokosing Construction Company, Inc. (Kokosing). Defendant explained the particular project “dealt with grading, draining, planning and resurfacing with asphalt concrete on SR 608 in Lake County.” From plaintiff’s description of the damage event, defendant located the incident “close to milepost 0.0 which is the beginning of this project in Lake County.” Defendant asserted Kokosing, by contractual agreement, was responsible for any roadway damage, occurrences, or mishaps within the construction zone. Therefore, ODOT argued that Kokosing is the proper party defendant in this action. Defendant implied all duties, such as the duty to inspect, the duty to warn, the duty to maintain, and the duty to repair defects were delegated when an independent contractor takes control over a particular section of roadway. All work by the contractor was to be performed in accordance with ODOT mandated specifications and requirements and subject to ODOT approval. Furthermore, defendant maintained an onsite personnel presence in the construction project area. {¶ 3} For plaintiff to prevail on a claim of negligence, he must prove, by a preponderance of the evidence, that defendant owed him a duty, that it breached that duty, and that the breach proximately caused his injuries. Armstrong v. Best Buy Company, Inc., 99 Ohio St. 3d 79, 2003-Ohio-2573,¶8 citing Menifee v. Ohio Welding Products, Inc. (1984), 15 Ohio St. 3d 75, 77, 15 OBR 179, 472 N.E. 2d 707. Plaintiff has the burden of proving, by a preponderance of the evidence, that he suffered a loss and that this loss was proximately caused by defendant’s negligence. Barnum v. Ohio State University (1977), 76-0368-AD. However, “[i]t is the duty of a party on whom the burden of proof rests to produce evidence which furnishes a reasonable basis for sustaining his claim. If the evidence so produced furnishes only a basis for a choice among different possibilities as to any issue in the case, he fails to sustain such burden.” Paragraph three of the syllabus in Steven v. Indus. Comm. (1945), 145 Ohio St. 198, 30 O.O. 415, 61 N.E. 2d 198, approved and followed. {¶ 4} Defendant has the duty to maintain its highways in a reasonably safe condition for the motoring public. Knickel v. Ohio Department of Transportation (1976), 49 Ohio App. 2d 335, 3 O.O. 3d 413, 361 N.E. 2d 486. However, defendant is not an insurer of the safety of its highways. See Kniskern v. Township of Somerford (1996), 112 Ohio App. 3d 189, 678 N.E. 2d 273; Rhodus v. Ohio Dept. of Transp. (1990), 67 Ohio App. 3d 723, 588 N.E. 2d 864. The duty of ODOT to maintain the roadway in a safe drivable condition is not delegable to an independent contractor involved in roadway construction. ODOT may bear liability for the negligent acts of an independent contractor charged with roadway construction. Cowell v. Ohio Department of Transportation, Ct. of Cl. No. 2003-09343-AD, jud, 2004-Ohio-151. Despite defendant’s contention that ODOT did not owe any duty in regard to the construction project, defendant was charged with duties to inspect the construction site and correct any known deficiencies in connection with particular construction work. See Roadway Express, Inc. v. Ohio Dept. of Transp. (June 28, 2001), Franklin App. 00AP-1119. {¶ 5} Alternatively, defendant argued that neither ODOT nor Kokosing had any knowledge “of any problems with uneven pavement on this project” prior to plaintiff’s damage occurrence. Defendant related ODOT “records (copies submitted) indicate that no calls or complaints were received at the Lake County Garage for SR 608 regarding uneven pavement prior to Plaintiff Morris’ incident.” Defendant advised the specific portion of State Route 608 has an average daily traffic of over 3000, yet no complaints were received concerning uneven pavement problems before September 25, 2009. Defendant did not provide any evidence to establish when the pavement on State Route 608 was initially milled in preparation for repaving. Evidence submitted shows the contract between ODOT and Kokosing was finalized on August 10, 2009. Therefore, the trier of fact shall infer State Route 608 was milled at sometime between August 10, 2009 and September 25, 2009. Defendant contended plaintiff failed to produce evidence establishing the damage to the 2010 Chevrolet Malibu was attributable to conduct on either the part of ODOT or Kokosing. {¶ 6} Defendant submitted a copy of an e-mail from Kokosing Claims Specialists, Pamela LeBlanc, in response to plaintiff’s allegations of a hazardous roadway condition created on State Route 608 from the milled pavement. LeBlanc noted that she spoke with Kokosing Project Superintendent, Lee Schloss who informed her “Bump” signage was installed at the area of State Route 608 where the milled roadway transitioned to existing pavement. LeBlanc also noted that Schloss reported a butt joint of 1 1/4" was placed at the transition site to provide for safe travel and ODOT did not designate any maintenance of traffic for the specific roadway area. LeBlanc insisted “[s]afe travel through this work zone was provided and appropriate signage was in place.” Furthermore, in reference to the purported incident site defendant submitted a copy of an e-mail from ODOT Project Engineer, Neal Moscato, who advised “[t]he butt joint in that area was 1 and ½ inches deep.” Moscato also provided with his correspondence a “Standard Construction Drawing B P 3.1" (copy submitted) used as a standard for installation of butt joints on milled roadway surfaces to merge milled pavement with existing pavement. Defendant maintained the ODOT specifications depicted in the drawing were utilized by Kokosing upon milling State Route 608.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Knickel v. Department of Transportation
361 N.E.2d 486 (Ohio Court of Appeals, 1976)
McClellan v. Ohio Department of Transportation
517 N.E.2d 1388 (Ohio Court of Appeals, 1986)
Kniskern v. Township of Somerford
678 N.E.2d 273 (Ohio Court of Appeals, 1996)
Rhodus v. Ohio Department of Transportation
588 N.E.2d 864 (Ohio Court of Appeals, 1990)
Feichtner v. Ohio Department of Transportation
683 N.E.2d 112 (Ohio Court of Appeals, 1995)
Stevens v. Industrial Commission
61 N.E.2d 198 (Ohio Supreme Court, 1945)
Neff Lumber Co. v. First National Bank
171 N.E. 327 (Ohio Supreme Court, 1930)
Bello v. Cleveland
138 N.E. 526 (Ohio Supreme Court, 1922)
Bussard v. Ohio Department of Transportation
507 N.E.2d 1179 (Ohio Court of Claims, 1986)
State v. Dehass
227 N.E.2d 212 (Ohio Supreme Court, 1967)
Cascone v. Herb Kay Co.
451 N.E.2d 815 (Ohio Supreme Court, 1983)
Shinaver v. Szymanski
471 N.E.2d 477 (Ohio Supreme Court, 1984)
Menifee v. Ohio Welding Products, Inc.
472 N.E.2d 707 (Ohio Supreme Court, 1984)
White v. Ohio Department of Transportation
564 N.E.2d 462 (Ohio Supreme Court, 1990)
Armstrong v. Best Buy Co.
788 N.E.2d 1088 (Ohio Supreme Court, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
2010 Ohio 3147, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morris-v-ohio-dept-of-transp-ohioctcl-2010.