Morris v. Myers

845 F. Supp. 750, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20165, 1993 U.S. Dist. LEXIS 19918
CourtDistrict Court, D. Oregon
DecidedSeptember 15, 1993
Docket93-332BR, CV 93-425BR
StatusPublished
Cited by6 cases

This text of 845 F. Supp. 750 (Morris v. Myers) is published on Counsel Stack Legal Research, covering District Court, D. Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morris v. Myers, 845 F. Supp. 750, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20165, 1993 U.S. Dist. LEXIS 19918 (D. Or. 1993).

Opinion

ORDER: 1) DENYING MOTION TO DISMISS; 2) DENYING ORAL ARGUMENT; and 3) GRANTING MOTION FOR SUMMARY JUDGMENT

BRYAN, District Judge.

THIS MATTER comes before the court on defendants’ Motion to Dismiss, or in the Al *753 ternative, for Summary Judgment. Defendants also request oral argument. The court has considered the arguments of the parties and has reviewed the record and is prepared to rule on this motion without oral argument.

INTRODUCTION

The General Services Administration (GSA) proposes to build a new Federal courthouse in downtown Portland, Oregon. Because this project is a major federal action, GSA initiated a review process under the National Environmental Policy Act (NEPA), to identify any potentially significant environmental impacts that would require preparation of an environmental impact statement (EIS). 42 U.S.C. § 4332(2)(C). GSA’s scoping process identified several areas of concern, mostly centering on the project’s effect on Portland’s low-income housing stock. Other issues raised involved parking and traffic circulation patterns, aesthetics and noise, and the demolition of buildings eligible for historic status.

GSA prepared an environmental assessment (EA), which evaluated the project’s possible effects in each of the following areas: geology, soils, and seismicity; hazardous waste; biological resources; water resources; traffic, transportation, and circulation; air quality; noise; population, employment, and housing; land use and zoning; urban design and aesthetics; community services; cultural resources; utilities; and decommissioning/future demolition. The EA also considered possible mitigation measures to lessen adverse impacts in several identified areas of concern.

The EA concluded that none of the environmental impacts were expected to be significant. Although the preferred building site presented “the potential for substantial impacts to housing, cultural resources and traffic” (EA at E-3), the EA found that these potentially significant impacts were temporary, did not rise to the level of environmental significance, or could be mitigated adequately to avoid significant environmental impacts. Based on the results of the EA, GSA determined that no EIS was required and issued a Finding of No Significant Impact (FONSI), published in the Federal Register on December 30, 1992. See 57 Fed. Reg. 62348.

Plaintiffs challenged GSA’s finding, alleging that the EA and FONSI were incomplete and inadequate because they failed to consider secondary environmental impacts caused by the reduction in low-income housing stocks, relied on mitigation measures that were not imposed by statute or regulation, and failed to explain adequately the determinations of nonsignificance. Plaintiffs also claimed that GSA, by not preparing an EIS, acted unreasonably, arbitrarily, capriciously, and in violation of NEPA.

The court previously denied plaintiffs’ Motion for Preliminary Injunction and Motion for Preliminary Injunction Pending Appeal, finding that plaintiffs did not show that GSA acted unreasonably, arbitrarily, capriciously, or contrary to law in reaching its Finding of No Significant Impact, and concluding that plaintiffs had not shown sufficient cause to merit a preliminary injunction. Defendants now move to dismiss for failure to state a claim or, in the alternative, for summary judgment. Their legal arguments may be summarized as follows:

(1) Plaintiffs lack standing to bring these actions because the alleged injuries to their interest in low-income housing are not redressable under NEPA and are outside of the zone of interests that NEPA seeks to protect.

(2) Plaintiffs failed to state a claim under NEPA because their interests in low-income housing are outside NEPA’s zone of interests.

(3) Plaintiffs waived the right to litigate any interests other than low-income housing by not providing timely comments to GSA regarding other alleged NEPA deficiencies.

(4) Defendants are entitled to summary judgment because GSA’s decision-making .process under NEPA was not arbitrary or capricious and because the agency acted within its discretion in deciding not to prepare an EIS.

STANDING

Defendants challenge plaintiffs’ standing to bring this action. Because the *754 standing issue is part of both alternative motions, and because it is a basic requirement for the court to have jurisdiction, Idaho Conservation League v. Mumma, 956 F.2d 1508, 1513 (9th Cir.1992), the court will address the issue of standing at the outset.

To establish standing, plaintiffs’ claims must satisfy three requirements: (1) plaintiffs must allege an injury in fact, that is, an invasion of an actual or imminent legally-protected interest which is concrete and particularized and not a generalized grievance nor a conjectural or hypothetical one; (2) there must be a causal connection between the injury and the conduct complained of; and (3) it must be likely that the injury can be redressed by a favorable decision. Lujan v. Defenders of Wildlife, — U.S.-,-, 112 S.Ct. 2130, 2137, 119 L.Ed.2d 351, 364 (1992); Idaho Conservation League, 956 F.2d at 1513-18. Where plaintiffs’ claims arise under a particular statute, they must allege that their injury falls within the zone of interests to be protected by the statute in question. Association of Data Processing Service Orgs. v. Camp, 397 U.S. 150, 153, 90 S.Ct. 827, 829, 25 L.Ed.2d 184 (1970).

Defendants argue that plaintiffs’ claims resolve into a single injury, the loss of low-income housing, which is not redressable under NEPA because the sole remedy, an order to prepare an EIS, would not replace the low-income housing lost as a result of the federal courthouse construction. Defendants also argue that this injury does not fall within the zone of interests sought to be protected by NEPA.

NEPA is essentially a procedural statute designed to ensure that environmental issues are given proper consideration in the decision-making process; injury alleged to have resulted from violating this procedural right confers standing. Idaho Conservation League, 956 F.2d at 1514. The court has the power to enforce this procedural right. Plaintiffs’ alleged NEPA claims, if properly pleaded and supported by sufficient evidence, are redressable; that is, the court can halt construction until an EIS is prepared.

Furthermore, as will be discussed more fully below, NEPA encompasses social or economic impacts that are interrelated with or caused by natural or physical impacts flowing from a major federal action. 40 C.F.R. § 1508.14; Port of Astoria, Oregon v. Hodel, 595 F.2d 467, 475 (9th Cir.1979).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Agdaagux Tribe of King Cove v. Jewell
128 F. Supp. 3d 1176 (D. Alaska, 2015)
Shoreline Alliance v. Tennessee Valley Authority
961 F. Supp. 2d 890 (W.D. Tennessee, 2013)
Methow Forest Watch v. United States Forest Service
383 F. Supp. 2d 1263 (D. Oregon, 2005)
Sierra Club v. Marita
46 F.3d 606 (Seventh Circuit, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
845 F. Supp. 750, 24 Envtl. L. Rep. (Envtl. Law Inst.) 20165, 1993 U.S. Dist. LEXIS 19918, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morris-v-myers-ord-1993.