Morris, Inc. v. State Ex Rel. Dept. of Transp.

2011 S.D. 85, 2011 SD 85, 806 N.W.2d 894, 2011 WL 6260613
CourtSouth Dakota Supreme Court
DecidedDecember 14, 2011
Docket25779, 25786
StatusPublished
Cited by4 cases

This text of 2011 S.D. 85 (Morris, Inc. v. State Ex Rel. Dept. of Transp.) is published on Counsel Stack Legal Research, covering South Dakota Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morris, Inc. v. State Ex Rel. Dept. of Transp., 2011 S.D. 85, 2011 SD 85, 806 N.W.2d 894, 2011 WL 6260613 (S.D. 2011).

Opinion

KONENKAMP, Justice.

[¶ 1.] In this breach of contract action against the South Dakota Department of Transportation (DOT), the circuit court ruled in favor of Morris, Inc. after a nine-day bench trial. The court awarded Morris $1,528,887 in damages, with $771,238.30 in prejudgment interest, and $20,035.47 in disbursements. The DOT appeals, challenging the basis for the court’s conclusion that it breached any contractual obligations to Morris. The DOT further disputes the calculation of the court’s damages award, and prejudgment interest. On notice of review, Morris asserts that *896 the court erred when it failed to include expert witness fees as disbursements.

Background

[¶2.] In October 2004, Border States Paving, Inc. was awarded the prime contract by the DOT for a road project on U.S. Highway 88 in Lyman and Stanley Counties, South Dakota. The total contract was for $13,614,621.22. On November 24, 2004, Border States entered into a subcontract with Morris, Inc. for aggregates and work on the project for $2,923,317.99. Three asphalt mixes were to be used: base course, Superpave, and Class S. Border States scheduled the project so that all asphalt paving operations would be completed by September 15, 2005, which coincided with the end of the Class S seasonal deadline.

[¶ 3.] The relationship between Border States and the DOT was circumscribed by multiple documents. These documents, among other things, prescribed the parties’ obligations with respect to the aggregates. Thus, although Morris subcontracted to produce and procure for Border States the necessary aggregates, Border States, as the prime contractor, was the responsible party under the contract. The subcontract agreement provided that Morris’s work was subject to inspection and acceptance by the DOT. Morris’s actions are primarily at issue here. 1

[¶ 4.] On December 9, 2004, the DOT held a preconstruction meeting, at which Morris informed the DOT that it intended to provide materials for the project from the Durkin/LBT Pit, Mahutga Pit, and Richards Pit. And all Class S materials would come from the Durkin Pit. Morris was aware that regardless of where the materials came from, those materials had to meet the requirements of the controlling agreements.

[¶ 5.] As to the Class S materials, a major controlling document was the Standard Specifications for Roads and Bridges (Standard Specifications). Specification 325 provided that all Class S materials “shall conform to Section 320.2.” Section 320.2, entitled “Materials,” included a subheading, “Aggregates,” which must conform to Section 880. Standard Specifications 320.2B. Specification 880.2A provided a table listing what requirements the Class S mineral aggregate must conform to in regard to certain tests. For the sodium sulfate soundness test, the table set a maximum limit of 12% for both the plus and minus four. Specification 880.3 provided that a sodium sulfate soundness test would be conducted under the SD220, five cycles. For lightweight particles, the table allowed a maximum of one percent loss for the plus and minus four. Id. at 880.2A. Finally, the table provided the required mineral aggregate gradations. But the parties’ contract contained a specific provision overriding Specification 880.2A as it related to gradations. See Contract Plan Sheet F-3.

[¶ 6.] On March 11, 2005, Morris started crushing for the Superpave paving. Morris knew the contract required it to submit the proposed Superpave mix design at least fifteen working days before the scheduled paving start date. Moms and Border States were also aware that the contractor (Border States) must perform certain tests and submit certain test results when providing the DOT with materials to test. See Standard Specification 320(C)(2). Border States did not have its own testing lab, and therefore, hired Aaron Swan & Associates (Swan) to do all the necessary testing for the Superpave and Class S paving on the project. On June *897 13, 2005, Morris submitted a mix design to the DOT for the Superpave. Morris reported a sodium sulfate soundness result from Swan at 6.6% on the plus four and 6.1% on the minus four (passing, as the DOT sets a maximum of 15% on the plus and minus four). The DOT then tested the materials using its SD220 testing protocol and issued the results of its sodium sulfate soundness test on June 16, 2005. The submitted Superpave materials passed with a 15% on the plus four and 12% on the minus four.

[¶ 7.] While the Superpave material passed the DOT’S test, Morris was concerned with the results because the plus four was borderline failing, and the DOT runs sodium sulfate soundness testing on every 50,000 tons of Superpave. Morris planned on using similar materials for the Class S paving, which had a lower soundness requirement of 12% on the plus four. As a result of these concerns, Morris communicated with DOT personnel and questioned the DOT’S sodium sulfate soundness testing. According to Morris, this occurred around June 16, 2005, but the DOT contended that Morris did not complain until July 2005. Nonetheless, the DOT, Milt Morris, Chad Hicks (Morris’s in-house testing person), and Howard Schill of Swan met and discussed Morris’s concerns. They agreed to conduct a round robin sulfate soundness test on the plus four aggregates, using split samples from the Durkin Pit. They also agreed to depart from the SD220 and run the soundness test with a redrain/repour method. See Bowes Const., Inc. v. S.D. Dept. of Transp., 2010 S.D. 99, ¶¶ 19-24, 793 N.W.2d 36, 43-44 (discussing the SD220 and the double pour/repour method).

[¶ 8.] Sometime after July 22, 2005, Hicks, Swan, and the DOT ran a sodium sulfate soundness test on the plus four materials submitted by Morris as part of the agreed-upon round robin. On August 2, 2005, Jim Costello of the DOT orally advised Hicks that the Class S material passed the plus four soundness test. This, as it turned out, was incorrect. The materials actually failed with a 13.67% loss on the plus four. Costello testified that he told Hicks the results without first submitting them to the Central Lab, although he knew that sodium sulfate soundness test results were supposed to be reported to the DOT area engineer at the Central Lab. Costello explained that he told Hicks the results because he was trying to help speed up the process, knowing that the Class S submissions were behind schedule.

[¶ 9.] The error was ultimately discovT ered by Rick Rowen of the DOT on August 10, 2005. Costello was on vacation and Rowen was in charge of testing. Rowen reviewed the calculations from the DOT and Swan on the materials submitted for the round robin and discovered the error. After recalculating the soundness loss, the DOT’s sodium sulfate test result showed a failing loss at 13.67%, Swan a failing result at 14.36%, and Morris’s in-house test result passing at an 8.88% loss. Rowen reported the calculation error to his supervisor, Tom Grannes, who reported it to his supervisor, Joe Feller. Border States and Morris, however, were not informed of the error and ultimate failed test until August 16 or 18, 2005.

[¶ 10.] After informing Border States and Morris of the failed soundness test, the DOT directed Morris to submit a new mix design.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2011 S.D. 85, 2011 SD 85, 806 N.W.2d 894, 2011 WL 6260613, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morris-inc-v-state-ex-rel-dept-of-transp-sd-2011.