Morrin v. Robert White Engineering Works

138 F. 68, 1905 U.S. App. LEXIS 4587
CourtU.S. Circuit Court for the District of Eastern New York
DecidedMay 10, 1905
StatusPublished
Cited by12 cases

This text of 138 F. 68 (Morrin v. Robert White Engineering Works) is published on Counsel Stack Legal Research, covering U.S. Circuit Court for the District of Eastern New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morrin v. Robert White Engineering Works, 138 F. 68, 1905 U.S. App. LEXIS 4587 (circtedny 1905).

Opinion

THOMAS, District Judge.

The complainant is the owner of letters patent No. 463,307, issued to Thomas F. Morrin on November 17, 1891. The bill charges that the defendant has infringed claim 2, which is as follows:

“(2) A steam-generator having an upright generator-cylinder provided with tiers of generating-tubes, b, of loop-like form, said loop having a pear-shaped outline when seen in plan, and each loop having at one side a lobe formed by the short out-curve at bx, and the short in-curve at bxx, the planes of the loops in the tubes being set obliquely to the axis of the generator-cylinder, substantially as set forth.”

This claim was sustained in the suit of Morrin v. Lawlor and Morrin v. Edison Electric Illuminating Co. (C. C.) 90 Fed. 285, on appeal 99 Fed. 977, 40 C. C. A. 204. The patentability of the structure, as shown in the. claim, is found in the loop described in claim 2, and it was so held. The Clonbrock Steam Boiler Company, a former licensee of the complainant, installed at the establishment of the 'Terre Haute Electric Company between December, 1894, and July, 1895, two boilers constructed pursuant to the claim, and two of the same type of boilers at the establishment of the American Manufacturing Company — one in 1895 and one in 1898. On April 8, 1904, á receiver of the Clonbrock Company was appointed in bankruptcy, and thereupon one Jones, who had been the vice president of such company, canceled a contract which he had made on December 29,1903, with the Terre Haute Company, whereby he was to supply for its boilers the following:

050, 3" Boiler Tubes for 500 H. P. Olimax Boilers at 3.50 each.
1000 %xl" Bolts at lVzC. each.
50 Casing Brick for lining Casing at 15c. each.

On March 3, 1904, Jones left the Clonbrock Company, and on March 16th procured the Terre Haute Company to give the contract for the work to the defendant. Pursuant to its contract the [70]*70defendant replaced in each boiler at Terre Haute 450 tubes, which was 25 less for each cylinder than the amount originally provided; ,the cylinder at some previous time having been so repaired as to prevent further replacement. The defendant calked part of the shell of one of the boilers, and put in new bricks in an outer casing where necessary, and furnished 1,000 bolts. The defendant actually sent to the Terre Haute Company 950 new tubes. The American Manufacturing Company negotiated with both the defendant and the receiver of the Clonbrock Company for work upon its boilers. On July 5, 1904, that company requested the receiver to estimate on the cost of furnishing from 900 to 1,000 tubes and other parts, and on July 17th the receiver agreed to do the work at $4.75 per tube, which included the cost of the tube and labor. On June 20, 1904, the defendant offered to supply 475 tubes for one of the American Manufacturing Company’s boilers, and 588 tubes for the other, at the cost of $3.25 each, and an additional sum of $400 for labor on one boiler, and $600 for the other boiler, which offer was repeated on July 20, 1904, and thereafter was accepted by the American Manufacturing Company. In addition to the above work the defendant also renewed about 4 tiers out of 19 for the Wurster & Company boiler, when it was enjoined and stopped. The boiler was taken down, moved, and put up again. The defendant did the work for these three several companies according to the contract, although the receiver gave due notice that he contested the legality of its proposed action.

The first question is whether the practical replacement of all the tubes by the defendant was unlawful renewal or authorized repair? The defendant’s brief states that, as to the Terre Haute boilers, the reason for replacing the tubes was “that there were already many stop tubes and tubes in bad condition, and it was difficult to pick out the good tubes, since they were only 3-inch tubes, and bent or bowed so that one could not see inside of them”; and, as to the American Manufacturing Company boilers, that “there were two boilers that were retubed by the defendant. This was done because many of the tubes were in bad condition, and it seemed cheaper to replace all than to undertake to pick out the bad tubes.” The “generator cylinder,” of the 500 horse power class, is about 28 feet in height, and about 3^2 feet in diameter. The original cost of the cylinder alone was about the same as that of the tubes. There was an outer casing, not mentioned in claim 2, which, with its fire-brick lining and fire box, cost about the same as each of such elements. The price of the tubes used to retube, the boilers was about one-third of the original first cost of the entire structure, including cylinder, tubes, and outer casing. The evidence of Ormond, who did the work on the Terre Haute boilers for the defendant, is to the effect that the life of such a .boiler is “about fourteen years; that is, if the boilers are kept repaired with tubes if they need it.”

“Q. When you left these boilers at the Terre Haute Company, did you, or did you not, consider them as good as new? A. I did not consider them as-[71]*71good as new. Q. Could you give any estimate as to how long they would probably run? A. Well, about two years I would give them.”

Wilson, complainant’s witness, states:

“Twenty years should be the lifetime of any shell boiler under certain conditions. Q. And those conditions are conditions of proper attention? A. Well, in a building of this character, I shouldn’t feel justified in running boilers over twenty years, whereas, in an isolated factory, or something of that kind, with good care, a boiler would last twenty-five or thirty years. The question of crystallization creeps in, and, you can’t determine.”

The life of the cylinder and tubes is affected by the water used in them. The Terre Haute tubes were from the beginning peculiarly clogged, impaired, and destroyed by the use of water having a large amount of carbonates and deposits, which necessitated an unusually large replacement of tubes. The American Company’s boilers were used under more favorable, and perhaps ordinarily favorable, conditions, and were not fully retubed until the defendant supplied tubes therefor, although tubes failed from time to time; and in such instances the holes in the boiler were closed by stop tubes, or new tubes furnished by the Clonbrock Company were inserted, amounting in all to 50 or 60. Only a very limited number of stop tubes could be used, or the efficiency of the boiler would be seriously limited. The evidence shows that the life of a whole set of tubes is somewhat shorter than that of the cylinder, and that some of the entire set of tubes fail from time to time before the entire set becomes unserviceable.

The question to be determined requires an examination of the decisions, for the difficulty is not in discovering the general rule, but, rather, its application. Hence what the courts have regarded as reconstruction, and what justifiable repair, aids decision, and the pertinent cases must be considered carefully.

In Thomson-Houston Electric Co. v. Kelsey Electric Ry. Specialty Co., 75 Fed. 1005, 22 C. C. A. 1, the Circuit Court of Appeals modified the order of the Circuit Court (72 Fed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Ruth v. Stearns-Roger Mfg. Co.
13 F. Supp. 697 (D. Colorado, 1935)
Electric Auto-Lite Co. v. P. & D. Mfg. Co.
8 F. Supp. 314 (E.D. New York, 1934)
Eclipse MacH. Co. v. J. H. Specialty Mfg. Co.
4 F. Supp. 306 (E.D. New York, 1933)
Neptune Line, Inc. v. Stone & Cooper
34 F.2d 226 (D. Maine, 1926)
Wilson v. Union Tool Co.
265 F. 669 (Ninth Circuit, 1920)
National Malleable Casting Co. v. American Steel Foundries
182 F. 626 (U.S. Circuit Court for the District of New Jersey, 1910)
Union Special Mach. Co. v. Maimin
161 F. 748 (E.D. Pennsylvania, 1908)
O'Rourke Engineering Const. Co. v. McMullen
150 F. 338 (U.S. Circuit Court for the District of Southern New York, 1907)
National Cash Register Co. v. Grobet
148 F. 385 (S.D. New York, 1906)
Wagner Typewriter Co. v. F. S. Webster Co.
144 F. 405 (U.S. Circuit Court for the District of Southern New York, 1906)

Cite This Page — Counsel Stack

Bluebook (online)
138 F. 68, 1905 U.S. App. LEXIS 4587, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morrin-v-robert-white-engineering-works-circtedny-1905.