Morgan v. Plotkin

189 N.W. 63, 219 Mich. 265, 1922 Mich. LEXIS 779
CourtMichigan Supreme Court
DecidedJuly 20, 1922
DocketDocket No. 28
StatusPublished
Cited by1 cases

This text of 189 N.W. 63 (Morgan v. Plotkin) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan v. Plotkin, 189 N.W. 63, 219 Mich. 265, 1922 Mich. LEXIS 779 (Mich. 1922).

Opinion

Steere, J.

On March 25, 1916, plaintiff, who was engaged in the business of manufacturing and installing piping and boiler covering, entered into a contract with defendant Plotkin to furnish material and perform required work of that kind in a building which the latter was constructing, under a contract by which he agreed for a consideration of $1,325 to—

“provide all the materials and perform all the work for the pipe covering for the following:

“All steam risers in outside walls.
“All return risers in outside walls.
“All hot and cold water piping throughout.
“All steam piping in attic and basement.
“All underground returns to be encased, in crock.”

The work was to be commenced at once, “pushed” as fast as conditions permitted “to avoid all delay;” 85% of the value of completed work was to be paid for as performance was in progress, on estimates by the architect, and final payment of 15% within 30 days after entire completion and acceptance of the job by the architect. The work was to be done, “in ac[267]*267cordance with general conditions,” as shown in the contract and drawings prepared by the architect made a part thereof. Plaintiff commenced performance promptly and on April 17,1916, received an architect’s certificate for $800 upon which he was only able to obtain from defendant $600. He claims to have completed his contract when and so far as conditions in the erection of the building would permit, his last day’s work being done on October 31, 1916. Unable to otherwise collect further payment therefor he filed a claim of mechanic’s lien on December 19, 1916, and served a statement on defendant Plotkin on December 23, 1916, showing first work and material furnished March 30, 1916, and the last work done on October 31, 1916. No question is raised against the regularity of the steps taken to establish his lien, except the time in which it was filed. • This bill was filed to enforce said lien. Defendant Plotkin answered with denial and counter-claim for damages resulting from plaintiff’s failure to carry out the contract according to its terms.' The case was heard on pleadings and proofs taken in open court resulting in a decree in favor of plaintiff for the sum of $715, with interest amounting to $78.50. Defendant appealed.

The questions raised in the court below and here as interrogatively stated in the brief of defendant’s counsel are:

“(1) Is there any competent evidence of the last date on which work was done, and hence of the validity of the lien? (Raised by motion to dismiss.)
“(2) Is there evidence of such performance of Morgan’s contract as to entitle him to a decree?
“(3) Was Morgan’s breach of his contract waived by Plotkin?”

Upon the contention there was no competent evidence of when the last work was done defendant’s counsel urge that plaintiff’s testimony is in its nature [268]*268hearsay, in support of which the following excerpts are quoted:

“The last work was done October 31st; I would not say positively whether I was on the job that day.”

Cross-examination:

“My records show the last work was done on October 31st.
“Q. What records are they?
“A. Ordinary business records for delivery tickets and the time tickets, records made by my employees, but not by myself, although the final records were made by me. The record as showing October 31st was made by me personally, but was copied from the records of my employees and the pay book, so that When I say October 31st was the last day, I mean that I took from my employees’ report the last day they were there.”

He also testified upon that subject in part as follows:

“I was frequently on the job as it progressed. The last time on October 31st, at which date I completed the job so far as it could be completed. * * *
“I know of my own knowledge that on the 3-lst the men worked on that job because my superintendent reports him on the job. Mr. Cassidy is the superintendent, but is not in the city; in the service. I was on the job after that day, but I cannot name any particular time, only I know I was on after the men left because of the fact that this little heater was not in.
“Q. Do you know how many days it was you were on, afterwards?
“A. Probably a week.
“Q. Not later than a week?
"A. It might have been longer, I could not name the time as to that, I can’t remember the specific instance.”

In connection with plaintiff’s oral evidence was the verified claim of lien filed December 19, 1916, and bill of complaint under oath filed April 28,1917, showing the last work done October 31, 1916. No evi[269]*269dence was offered to the contrary. We think the record contained evidential support for the trial court’s finding that “the lien was filed within the statutory period.”

Plaintiff’s evidence showed that he faithfully completed his contract as closely as conditions permitted, with two exceptions, and did some extra work because of repairs and changes for which he made no charge. The first, as he testified, was failure to cover the little heater he went there to see about “possibly a week” or longer after they quit, which was not there when his men had otherwise finished the job and left, the second being that he did not encase the underground returns in crock as specified, but instead applied a, thick insulated covering protected by a roofing and: asphalt jacket, which he claimed was the customary method in such cases and better than the method specified by the architect in his contract, which simply called for crock with no provision for filling and sealing the joints. He testified this change was made with the approval of the steam fitter and plumber, named Applebaum, who was in charge of the work and gave him instructions, and also with defendant’s knowledge, while the work progressed, before the underground returns were covered.

The cost of covering the little heater, shown not to exceed $10, was apparently allowed to defendant in the trial court’s decree. The serious contention as indicated by the testimony taken and argument of counsel is plaintiff’s failure to encase the underground returns in crock, which defendant claims materially shortened the life of the pipes and diminished the value of his building.

Plaintiff’s contention is that the covering or encasing which he adopted was an approved method and a better job for protecting the underground piping than the faulty specification of the architect [270]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bradley v. O'Brien
183 N.W.2d 411 (Michigan Court of Appeals, 1970)

Cite This Page — Counsel Stack

Bluebook (online)
189 N.W. 63, 219 Mich. 265, 1922 Mich. LEXIS 779, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgan-v-plotkin-mich-1922.