Morgan v. GREEN-SAVE, INC.

2 So. 3d 648, 2008 Miss. App. LEXIS 252, 2008 WL 1795027
CourtCourt of Appeals of Mississippi
DecidedApril 22, 2008
Docket2006-CA-01174-COA
StatusPublished
Cited by8 cases

This text of 2 So. 3d 648 (Morgan v. GREEN-SAVE, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Mississippi primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Morgan v. GREEN-SAVE, INC., 2 So. 3d 648, 2008 Miss. App. LEXIS 252, 2008 WL 1795027 (Mich. Ct. App. 2008).

Opinion

CARLTON, J.,

for the Court.

¶ 1. This is an appeal from the Circuit Court of Lee County wherein Green-Save, Inc., and Walter J. Fleishhacker (collectively “Green-Save”) filed suit against Tommy Morgan, seeking damages for alleged fraud in the sale of 2.1 acres of land. Specifically, Green-Save claimed that Morgan concealed that a portion of the property was situated in a flood plain and misrepresented that natural gas would be available to the property. At the conclusion of trial, the jury returned a verdict in favor of Green-Save in the amount of $325,000. The trial court denied Morgan’s post-trial motions.

¶ 2. Aggrieved, Morgan appeals and argues that the trial court erred in denying his motions for judgment notwithstanding the verdict, a new trial, and remittitur. Green-Save cross-appeals and claims that the trial court erred in failing to award *651 attorney’s fees and refusing to submit the issue of punitive damages to the jury.

¶ 3. We find that Green-Save failed to establish fraud and that Morgan was entitled to judgment notwithstanding the verdict. Therefore, we reverse and render judgment in favor of Morgan and do not reach the other assignments of error.

FACTS

¶ 4. In 1998, Morgan, a real estate developer, purchased approximately 319 acres of undeveloped land in Lee County, Mississippi. Several years later, Morgan began to develop the property by dividing it into two planned development areas: “The Summit,” a residential subdivision consisting of approximately 140 acres, and “South Ridge Commons,” a commercial development consisting of the remaining acreage.

¶ 5. In the spring of 2001, Fleishhacker, the owner of Green-Save, Inc., 1 contacted Morgan and asked him if he had any property available on which Green-Save could construct a new manufacturing facility. Morgan met with Fleishhacker at the South Ridge Commons development and showed him the 2.14 acre lot, which Green-Save later purchased. At the time, South Ridge Commons was in the early stages of development; Morgan had sold only one other lot, which was located adjacent to lot he showed Fleishhacker. Morgan explained to Fleishhacker that light industrial development was planned to the east of the lot and commercial and retail development was planned to the west of the lot. No discussion was had regarding whether the property was situated in a flood plain. On this occasion, Morgan and Fleishhacker agreed on a price of $32,100 and “shook hands and had a deal.” Several days later, Morgan met with Fleishhacker and Les Ellis, the manager of Green-Save, at the lot. According to Fleishhacker, he told Morgan that Green-Save planned to utilize natural gas instead of electricity at the new manufacturing facility, and Morgan stated that “all utilities” would be available to the property. The parties ultimately closed on the property in April 2002. Green-Save purchased the property without financing.

¶ 6. In late summer of 2002, Green-Save moved forward with plans to construct the manufacturing facility. Green-Save hired Gerald Warfield, owner of Southland Construction, to build the facility. The site was graded and construction began without any efforts by either Warfield or Green-Save to ascertain whether the property was in a flood plain. In November 2002, as construction neared completion, Fleishhacker first sought financing. This required a flood certificate, the preparation of which revealed that a portion of the property was located in a flood plain. The facility as constructed was situated one inch below the requisite elevation necessary to avoid the purchase of flood insurance — one foot above the designated flood plain elevation. Consequently, financing could not be obtained without the purchase of flood insurance at an annual cost of approximately $2,500.

¶ 7. Nevertheless, the new manufacturing facility opened and began operating in January 2003. Around this time, Green-Save contacted Mississippi Valley Gas (MVG), seeking to have a natural gas line installed. However, MVG refused because only two lots had been developed in South Ridge Commons, a fact that, in MVG’s estimation, rendered the running of a gas line to Green-Save’s facility economically infeasible. Green-Save continued to operate the manufacturing facility on electricity, which proved to be less expensive than natural gas.

*652 ¶ 8. In April 2004, Green-Save filed suit, alleging that Morgan fraudulently concealed that the property was in a flood plain and fraudulently misrepresented that natural gas would be available to the property. The case was submitted to the jury on these two issues. After deliberation, the jury returned a general verdict in favor of Green-Save and awarded damages in the amount of $325,000. Morgan’s motions for judgment notwithstanding the verdict, new trial, and remittitur were denied. Morgan now appeals to this Court.

DISCUSSION

I. Whether the trial court erred in denying Morgan’s motion for judgment notwithstanding the verdict.

¶ 9. We review the denial of a motion for judgment notwithstanding the verdict (JNOV) de novo. Wilson v. Gen. Motors Acceptance Corp., 883 So.2d 56, 64(24) (Miss.2004). A motion for JNOV tests the legal sufficiency of the evidence. White v. Yellow Freight Sys. Inc., 905 So.2d 506, 510(6) (Miss.2004). On appeal, we “consider the evidence in the light most favorable to the non-moving party, giving that party the benefit of all favorable inferences that reasonably may be drawn therefrom.” Wilson, 883 So.2d at 63(21). We will affirm the denial of a motion for JNOV where “the evidence is of such quality that reasonable and fairminded jurors in the exercise of fair and impartial judgment might reach different conclusions.” Poole v. Avara, 908 So.2d 716, 726(24) (Miss.2005). However, we must reverse and render “[i]f the facts so considered point so overwhelmingly in favor of the appellant that reasonable men could not have arrived at a contrary verdict.” Wilson, 883 So.2d at 63(22) (quoting Corley v. Evans, 835 So.2d 30, 37(19) (Miss.2003)).

¶ 10. Generally, in order to establish fraud under Mississippi law, a plaintiff must show the following by clear and convincing evidence:

(1) a representation, (2) its falsity, (3) its materiality, (4) the speaker’s knowledge of its falsity or ignorance of its truth, (5) his intent that it should be acted on by the hearer and in the manner reasonably contemplated, (6) the hearer’s ignorance of its falsity, (7) his reliance on its truth, (8) his right to rely thereon, and (9) his consequent and proximate injury.

Mabus v. St. James Episcopal Church, 884 So.2d 747, 762(32) (Miss.2004) (quoting Franklin v. Lovitt Equip. Co., 420 So.2d 1370, 1373 (Miss.1982)). The instant case was submitted to the jury on two specific claims: (1) whether Morgan fraudulently concealed that a portion of the property was in a flood plain and (2) whether Morgan fraudulently misrepresented that natural gas would be available to the property. We will consider each separately.

1. Whether Morgan fraudulently concealed that a portion of the property was in a flood plain.

¶ 11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State of Louisiana v. Uralle A. Price, Jr.
Louisiana Court of Appeal, 2025
J.P. Milam v. Ann Kelly
Court of Appeals of Mississippi, 2019
Anita White v. Omar L. Nelson
Court of Appeals of Mississippi, 2016
Cooper v. Gilder
156 So. 3d 262 (Court of Appeals of Mississippi, 2009)

Cite This Page — Counsel Stack

Bluebook (online)
2 So. 3d 648, 2008 Miss. App. LEXIS 252, 2008 WL 1795027, Counsel Stack Legal Research, https://law.counselstack.com/opinion/morgan-v-green-save-inc-missctapp-2008.