Moretti-Harrah Marble Co. v. J. C. Champagne, Inc.

158 So. 2d 317, 1963 La. App. LEXIS 2082
CourtLouisiana Court of Appeal
DecidedNovember 12, 1963
DocketNo. 5957
StatusPublished
Cited by1 cases

This text of 158 So. 2d 317 (Moretti-Harrah Marble Co. v. J. C. Champagne, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moretti-Harrah Marble Co. v. J. C. Champagne, Inc., 158 So. 2d 317, 1963 La. App. LEXIS 2082 (La. Ct. App. 1963).

Opinion

REID, Judge.

This suit was brought by Moretti-Harrah Marble Company, a furnisher of polished marble, against Union Construction Company, Inc., primary contractor; the St. James Parish School Board, the owner; Maryland Casualty Company, the surety on the contractor’s bond; and J. C. Champagne, Inc., the sub-contractor of Union Construction Company, Inc., to enforce the payment for materials sold by plaintiff to J. C. Champagne, Inc., under a contract ’awarded to Union Construction Company, Inc. for construction of a gymnasium for the St. James Parish School Board.

The facts are:

On November 4, 1959 a contract was entered into between Union Construction Company, Inc., and the St. James Parish School Board, with the Maryland Casualty Company as surety, for the construction of the Lutcher School Gymnasium at St. James School located in St. James Parish, Louisiana. The Union Construction Company, Inc., then entered into a subcontract with J. C. Champagne, Inc. for installation of marble stiles and partitions in the building.

On March 8, 1960 plaintiff sold to defendant J. C. Champagne, Inc., a shipment of marble, which was billed on June 6, 1960 and shipped to J. C. Champagne, Inc., at its Baton Rouge address. On July 6, 1960 a claim for the price of the marble was made by the plaintiff against J. C. Champagne, Inc.

On September 27, 1960 the contract was accepted and formal acceptance was recorded in the mortgage records of St. James Parish. On November 10, 1960 a lien certificate was obtained showing no liens had been filed as of that date.

[318]*318On May 1, 1961, more than eight months after filing of the acceptance, the first notice was given by plaintiff to Union Construction Company, Inc. and Maryland Casualty Company that its claim for materials sold to J. C. Champagne, Inc., was outstanding. The record discloses defendant Union Construction Company paid defendant J. C. Champagne, Inc., the full amount of its contract which would have included the purchase of the said marble.

On September 8, 1961 suit was filed by the plaintiff in the amount of $1738.00 representing the cost of marble sold to the subcontractor, J. C. Champagne, Inc.

Exceptions of no right or cause of action were filed by Union Construction Company, Inc. and Maryland Casualty Company leveled at the capacity of plaintiff to sue in the Courts of this State by virtue of LSA-R.S. 12:212. The exceptions were referred to the merits. Defendants Union Construction Company, Inc. and Maryland Casualty Company then filed an answer and third party action citing J. C. Champagne, Inc., to answer which J. C. Champagne, Inc., failed to do and on March 28, 1962 the plaintiff confirmed its default against J. C. Champagne, Inc., reserving its rights against all other defendants.

Defendants Union Construction Company, Inc. and Maryland Casualty Company filed an exception of no right or cause of action leveled at the failure of plaintiff to record its claim within 45 days after the recordation of the notice of acceptance as required by LSA-R.S. 38:2242, as amended, the record showing plaintiff at no time had ever recorded its claim in the mortgage records of St. James Parish. These exceptions of no right or cause of action were overruled and judgment signed accordingly, whereupon defendant Union Construction Company, Inc. filed additional exceptions of no right or cause of action in which it re-urged the exceptions previously overruled by the Court, that plaintiff had failed to either record its claim within 45 days after the recordation of the notice of acceptance by the owner of the work involved in the contract or to send such notice to either exceptor by registered or certified mail as required by LSA-R.S. 38:2247, and that plaintiff had no right or cause of action as against Union Construction Company, Inc. since plaintiff failed to record its claim as required by LSA-R.S. 38:2242. Defendants further excepted on the grounds plaintiff had failed to meet the test to be entitled to a lien since plaintiff did not perform any labor in attaching the materials to the building.

The case was tried and submitted and for written reasons assigned the Trial Court rendered judgment in favor of plaintiff and against defendant Maryland Casualty Company, but dismissed plaintiff's suit as against Union Construction Company, Inc. From that judgment both plaintiff and defendant Maryland Casualty Company have appealed.

The issue involved in this case is an interpretation of the provisions of the 1960 amendment to LSA-R.S. 38:2247, requiring, within 45 days of notice of acceptance, either recordation or written notice of a claim by a creditor having a contractual relationship with a subcontractor but no contractual relationship with the contractor, before the parties shall have a right of action against the contractor or surety on the bond furnished by the contractor. At the time the contract was entered into, as well as when the purchase orders were contracted, the law in this regard was as follows:

LSA-R.S. 38:2242 provided:
“Any person to whom money is due for doing work, performing labor, or furnishing materials or supplies for the construction, alteration, or repair of any public works, or furnishing materials and supplies for use in machines used in the construction, alteration, or repair of any public works, may, after the maturity of his claim and within forty-five days after the recordation of acceptance of the work by the governing authority or of notice of default of the contractor or subcontractor, file a [319]*319sworn statement of the amount due him with the governing authority having the work done and record it in the office of the recorder of mortgages for the parish in which the work is done. % ‡ * ”
and LSA-R.S. 38:2247 provides:
“Nothing in this Part shall be construed to deprive any person or claimant within the terms of this Part of his right of action on the contractor’s bond which shall accrue at any time after the maturity of his claim.”

It is clear, therefore, under the law it was not a prerequisite under the statute as then written that a materialman or supplier record his claim or serve any notice thereof in order to assert his right of action against the surety on the contractor’s bond. However, by Act 117 of 1960, which became effective on July 17, 1960, Section 2247 was amended to provide :

“Nothing in this Part shall be construed to deprive any person or claimant within the terms of this Part of his right of action on the contractor’s bond which shall accrue at any time after maturity of his claim; except that before any person having a direct contractual relationship with a subcontractor but no contractual relationship with the contractor shall have a right of action against the contractor or the surety on the bond furnished by the contractor, he shall record his claim as provided in R.S. 38:2242 or give written notice to said contractor within forty-five days from the recordation of the notice of acceptance by the owner of the work or notice by the owner of default, stating with substantial accuracy the amount claimed and the name of the party to whom the material was furnished or supplied or for whom the labor or service was done or performed. Such notice shall be served by mailing the same by registered or certified mail, postage prepaid, in an envelope addressed to the contractor at any place he maintains an office in the State of Louisiana.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Moretti-Harrah Marble Co. v. J. C. Champagne, Inc.
161 So. 2d 278 (Supreme Court of Louisiana, 1964)

Cite This Page — Counsel Stack

Bluebook (online)
158 So. 2d 317, 1963 La. App. LEXIS 2082, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moretti-harrah-marble-co-v-j-c-champagne-inc-lactapp-1963.