Moose Coal Co. v. Clark

687 F. Supp. 244, 28 ERC (BNA) 1196, 1988 U.S. Dist. LEXIS 5389, 1988 WL 58429
CourtDistrict Court, W.D. Virginia
DecidedJune 8, 1988
DocketCiv. A. No. 84-0185-B
StatusPublished
Cited by1 cases

This text of 687 F. Supp. 244 (Moose Coal Co. v. Clark) is published on Counsel Stack Legal Research, covering District Court, W.D. Virginia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moose Coal Co. v. Clark, 687 F. Supp. 244, 28 ERC (BNA) 1196, 1988 U.S. Dist. LEXIS 5389, 1988 WL 58429 (W.D. Va. 1988).

Opinion

MEMORANDUM OPINION

GLEN M. WILLIAMS, District Judge.

This case is before the court on a complaint filed by Moose Coal Company, Inc. (“Moose”) seeking a permanent injunction of a cessation order issued by the Office of Surface Mining Reclamation and Enforcement (“OSM”). The Interior Board of Land Appeals (“Board”) directed OSM to issue the Order pursuant to the Surface Mining Control and Reclamation Act of 1977, 30 U.S.C. §§ 1201-1328 (1986). Jurisdiction of the court is based upon 30 U.S.C. § 1276(a)(2), (c) (1986). Under Section 1276(b), the court must hear the complaint solely on the record before the Secretary and the Secretary’s findings, if supported by substantial evidence on the record considered as a whole, shall be conclusive. For the reasons stated herein, the court is of the opinion that the Secretary’s findings, as represented by the Board’s decision, are not supported by substantial evidence and accordingly, the court will vacate the cessation order. This is not the end of this case, however, since the Secretary has filed a counterclaim founding jurisdiction upon 30 U.S.C. § 1271(c) (1986). The Secretary has asked for injunctive relief prohibiting Moose from further violating the act or failing to comply with orders issued by the Secretary. The court has the authority pursuant to Sections 1271(c) and 1276(b) to modify the Board’s decision and to issue appropriate and equitable relief to both the plaintiff and the defendants. Accordingly, the court will proceed to adjudicate the dispute.

Finally, the court should note that, to its knowledge, Moose has exhausted its administrative remedies. Although the defendants asserted in their Answer that Moose had not exhausted administrative remedies, neither party has briefed the issue. Moreover, in light of the case’s extensive administrative procedural history, the court feels that further pursuit of administrative remedies would be a futile gesture.

HISTORY OF THE CASE

The administrative proceedings leading up to this suit are lengthy and complicated because both the Commonwealth of Virginia and OSM have acted, and failed to act, as to several matters. The July 10, 1984 Opinion of Chief Administrative Law Judge Horton furnishes a relatively accurate description of the various administrative proceedings. His opinion is the aforementioned decision of the Office of Hearings and Appeals, Interior Board of Land Appeals, a branch of the United States Department of the Interior, Arlington, Virginia. In addition, the Secretary has offered in support of the counterclaim the affidavit of Earl D. Bandy, Jr., a reclamation specialist with OSM. This affidavit also outlines the history of the case. In view of the complexity involved, the court will relate only the essential history of this case, emphasizing those portions that the court finds most significant in arriving at its decision.

On March 17, 1980, Moose was issued Interim Permit Number 3140, located in Wise County, Virginia. Moose then began [246]*246operating its mine and was legally doing so pursuant to the Interim Permit. On December 16, 1981, the Commonwealth of Virginia, Division of Mined Land Reclamation (“DMLR”) became the primary regulatory authority in Virginia for all surface coal mining and reclamation operations. The DMLR adopted and implemented a phased submittal program for filing permanent program surface coal mining permit applications. Pursuant to this program, it required Moose to submit the first phase of its application by February 3, 1982, the second phase by April 3, 1982, and the third phase by July 3, 1982. Virginia regulations required that in order for a person to continue to operate a surface coal mine under an interim permit, he must make a timely and complete permit application under the permanent program requirements. Moose complied with the deadlines. Upon concluding its initial review, DMLR returned the application for corrections on December 30, 1982 due to certain deficiencies. Moose resubmitted its application to DMLR on February 28, 1983 and the DMLR again noted deficiencies. DMLR then ruled on March 25, 1983 that Moose had failed to comply and denied the petition for a permanent program permit. Moose appealed this decision. On April 8, 1983, a state hearing officer ruled that Moose was entitled to a third review and allowed it until May 25, 1983 in which to submit a timely and complete application. By letter dated April 19, 1983, the DMLR requested a reconsideration of the hearing officer’s opinion. The hearing officer denied this request on April 25, 1983. The Commonwealth of Virginia was entitled to appeal this decision. By letter dated May 3, 1983, however, Danny R. Brown, Commissioner of the DMLR for the Commonwealth of Virginia, advised the hearing officer that “[a]fter careful consideration regarding this particular case, I have decided not to continue the administrative review process, and will accept your decision.” The hearing officer’s unappealed ruling therefore constitutes a final decision on this matter. On May 25, 1983, Moose submitted a third application in accordance with the ruling of the state hearing officer. Shortly thereafter, Moose concluded its mine operations. Having no further need for the permanent program permit, it withdrew its application on June 15, 1983.

Meanwhile, on March 16, 1983, Virginia Citizens for Better Reclamation (“VCBR”) filed a citizens complaint pursuant to 30 C.F.R. § 842.12 on behalf of Virginia D. Hill. VCBR alleged that Moose had not filed a complete application and was therefore conducting surface mining operations in violation of Virginia’s permanent program regulations. OSM investigated Moose in cooperation with DMLR. Although Moose contends that this investigation lead to DMLR’s decision on March 25, 1983 to deny Moose’s application, the Secretary denies this allegation. OSM released its report on March 29, 1983. Following the April 8, 1983 decision of the state hearing officer allowing a third review, VCBR requested on April 11, 1983 an informal review, pursuant to 30 C.F.R. § 842.15, of OSM’s action on its citizen’s complaint. On May 17, 1983, the OSM field officer deferred to the state hearing officer’s ruling and decided that further enforcement action was not necessary or appropriate at that time. VCBR then appealed the field officer’s decision. By letter dated June 16, 1983, DMLR advised VCBR that it was allowing Moose to conclude its reclamation activities under its interim permit.

On July 10, 1984, the Interior Board of Land Appeals reversed the OSM field officer’s May 17, 1983 decision. It found that Moose’s mining activities after August 15, 1982 were conducted without a valid permit. It therefore ordered OSM to issue a cessation order, assess a civil penalty, and order Moose to reapply for a permanent program permit if OSM determined that it was still engaged in mining or reclamation operations at the site in question. Finally, it required OSM to ensure that Moose’s reclamation operations satisfied the performance standards of the Virginia permanent program regulations.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Catron v. Babbitt
955 F. Supp. 627 (W.D. Virginia, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
687 F. Supp. 244, 28 ERC (BNA) 1196, 1988 U.S. Dist. LEXIS 5389, 1988 WL 58429, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moose-coal-co-v-clark-vawd-1988.