Moore v. Bird Engineering Co.

41 P.3d 755, 273 Kan. 2, 2002 Kan. LEXIS 77
CourtSupreme Court of Kansas
DecidedMarch 8, 2002
Docket83,302
StatusPublished
Cited by16 cases

This text of 41 P.3d 755 (Moore v. Bird Engineering Co.) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore v. Bird Engineering Co., 41 P.3d 755, 273 Kan. 2, 2002 Kan. LEXIS 77 (kan 2002).

Opinion

The opinion of the court was delivered by

Allegrucci, J.:

William P. Moore, III, contacted Bruce Bird, an engineer, regarding his ability to design a bridge that would meet Moore’s needs. Moore sued Bird Engineering Company, P.A., (Bird Engineering) alleging defects in Bird’s design for a bridge built on Moore’s residential property. After a bench trial, the district court entered judgment in favor of Moore. The district court found against Bird Engineering for breach of contract, breach of express warranty, violation of the Kansas Consumer Protection Act (KCPA), and negligence. Bird Engineering appealed. Disagreeing with the district court’s view that Bird Engineering engaged in a deceptive act or practice in violation of the KCPA, the Court of Appeals affirmed the judgment in part, reversed in part, and vacated in part. This court granted Moore’s petition for review and Bird Engineering’s cross-petition for review.

On appeal to the Court of Appeals, Bird Engineering argued that there was a lack of substantial competent evidence supporting the district court’s conclusion that it engaged in a deceptive act or practice under the KCPA. The Court of Appeals disagreed with the district court’s conclusion that motive was immaterial to a violation of K.S.A. 50-626(b)(l) and, therefore, agreed with Bird Engineering that the district court’s failing to find “intent to deceive” was erroneous.

In these circumstances and because the court does not weigh conflicting evidence, pass on credibility, or redetermine questions of fact, Garvey Elevators, Inc. v. Kansas Human Rights Comm’n, 265 Kan. 484, 496-97, 961 P.2d 696 (1998), the district court’s findings of fact appropriately furnish the basis for the following statement of facts:

In early 1993, Moore began a search for a home site in the country. His ex-wife, who was a real estate agent, located the property he ultimately purchased, through which Wolf Creek runs. Moore was interested in the property if an appropriate bridge could be built across the creek to the proposed home site.

*4 Moore’s ex-wife made the initial contact with Bird. Hoping to make the sale at a price Moore would agree to, she indicated to Bird that she was looking to see if a bridge could be built for $20,000, at which price she said she could make the sale to Moore.

Subsequently, Moore and Bird met directly to discuss getting a cost estimate together for a bridge. Bird claims that his understanding from his initial meeting with Moore’s ex-wife was that the bridge would only need to be able to'carry a single car to the home site — a separate, low-water bridge elsewhere on the property could be used for trucks or other, heavier vehicles. Bird contends that this was also the explicit or implicit understanding in his discussions with Moore. Bird testified that the first discussion he had with Moore regarding specific weight capacities did not occur until sometime in mid-to late 1994, after Moore had consulted with the engineering firm of Shafer, Kline & Warren, P.A. (Shafer, Kline) about the project. The exact date of the first discussion between Moore and Bird about weight requirements is unknown. The district court concluded that Bird’s recollection was in error and that weight requirements were discussed between them, at the latest, before Bird proceeded to develop detailed engineering plans for construction of the bridge. .

Moore’s initial request to Bird Engineering was to prepare a preliminary cost estimate for a bridge that would provide access to the home site even during periods of veiy heavy rain, specifically sufficient to allow access at the 100-year flood level. Bird Engineering agreed to provide that cost estimate. There may or may not have been discussion at that point about the load limits for the bridge. Moore believes that he told Bird even in that initial conversation that he wanted emergency equipment to be able to use the bridge. It is not clear whether those discussions took place before or after the initial cost estimate had been prepared, but that does not need to be determined to decide the issues before the court. There were discussions about another means of driving to and from the home site via a low-water , entry point, which would be inaccessible in periods of heavy rain or high water.

On May 21, 1993, Bird faxed a “rough cost” estimate to Moore, quoting a $2,000 engineering fee for bridge design, flood plain *5 computations, and to submit for approval of the plans. Total cost of the bridge, with a $3,000 contingency, was estimated to be $25,000.

After receiving the cost estimate, Moore proceeded to purchase the property. From his viewpoint, the cost estimate gave him sufficient assurance that the cost of the bridge would be reasonable and within his intended budget.

After purchasing the property, Moore asked Bird to proceed with design work and permit requests. By this time, the parties discussed the types of vehicles that should be able to use the bridge. Moore specifically noted that emergency equipment, including small fire trucks, should be able to use the bridge. Bird agreed to proceed with the design of a bridge to suit Moore’s intended purposes.

On July 2, 1993, Bird transmitted an application for a permit to construct the bridge over Wolf Creek to the Johnson County Planning Office and, either directly or through the Johnson County Planning Office, to various state agencies with relevant regulatory authority.

Bird completed engineering drawings for the bridge on about September 9, 1993. The plans were submitted to Moore soon thereafter.

On September 24, 1993, Moore wrote the following notes in his spiral-bound Day-Timer planning calendar: “Bruce Bird[.] Bridge Max Design Load 16 Tons[.] Fire dept. 592-3926[.] Tanker -largest trucks. Largest tanker 1630 gal. Gross Wt. Loaded 31,000 lb. Routinely cross 8 + 10 ton bridges.” The district court concluded that this entry was, in fact, made by Moore on September 24, 1993, as shown. It was not “manufactured evidence” created by Moore after the dispute between the parties arose.

Moore proceeded to hire a contractor to do the construction work in accordance with the Bird Engineering plans. As the project went along, there was consultation with Bird on a number of aspects of the work. Bird set stakes to show the site for the bridge abutments. He also examined some of the soils to determine their suitability and gave advice on some other aspects of the work.

*6 Bird’s plans did not call for “hooking” vertical steel rods into the pads of the bridge abutments. Nor did his plans specify the depth to which these vertical rods were to be embedded into the pads even without hooks. Bird was consulted about this during the construction phase. He said that hooking was not required and advised drilling some holes and anchoring the steel into the pads with epoxy. That was done as instructed. However, the method used was insufficient, either because hooking should have been done or because the steel rods were not sufficiently embedded into the pads.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

POOLE VS. NEV. AUTO DEALERSHIP INV.'S, LLC
2019 NV 39 (Nevada Supreme Court, 2019)
Poole v. Nev. Auto Dealership Invs.
Court of Appeals of Nevada, 2019
Hays v. Ruther
313 P.3d 782 (Supreme Court of Kansas, 2013)
Golden v. Den-Mat Corp.
276 P.3d 773 (Court of Appeals of Kansas, 2012)
Unruh v. PURINA MILLS, LLC
221 P.3d 1130 (Supreme Court of Kansas, 2009)
Berry v. National Medical Services, Inc.
205 P.3d 745 (Court of Appeals of Kansas, 2009)
Williamson v. Amrani
152 P.3d 60 (Supreme Court of Kansas, 2007)
Crandall v. Grbic
138 P.3d 365 (Court of Appeals of Kansas, 2006)
Attorney General Opinion No.
Kansas Attorney General Reports, 2003

Cite This Page — Counsel Stack

Bluebook (online)
41 P.3d 755, 273 Kan. 2, 2002 Kan. LEXIS 77, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-v-bird-engineering-co-kan-2002.