Moore Construction Co. v. Story Engineering

CourtCourt of Appeals of Tennessee
DecidedJuly 10, 1998
Docket01A01-9606-CV-00267
StatusPublished

This text of Moore Construction Co. v. Story Engineering (Moore Construction Co. v. Story Engineering) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore Construction Co. v. Story Engineering, (Tenn. Ct. App. 1998).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT NASHVILLE FILED MOORE CONSTRUCTION COMPANY, ) July 10, 1998 INC., and PAUL W. MOORE, ) ) Cecil W. Crowson Plaintiffs/Appellants, ) Appellate Court Clerk ) Montgomery Circuit ) No. C9-31 VS. ) ) ) Appeal No. STORY ENGINEERING COMPANY, ) 01A01-9606-CV-00267 INC., and RODDY L. STORY, ) ) Defendants/Appellees. )

APPEAL FROM THE CIRCUIT COURT FOR MONTGOMERY COUNTY AT CLARKSVILLE, TENNESSEE

THE HONORABLE JAMES E. WALTON, JUDGE

For Plaintiffs/Appellants: For Defendants/Appellees:

Thomas N. Bateman John T. Horton Robert T. Bateman Brewer, Krause, Brooks & Mills Bateman, Bateman & Darnell Nashville, Tennessee Clarksville, Tennessee

AFFIRMED AND REMANDED

WILLIAM C. KOCH, JR., JUDGE OPINION

This appeal stems from a construction contract to improve the natural gas transmission system in the City of Clarksville. After the City awarded the contract, an unsuccessful bidder sued the project engineer in the Circuit Court for Montgomery County, claiming interference with prospective economic advantage, defamation, and disparagement. The trial court granted the project engineer’s motion for summary judgment, and the unsuccessful bidder has appealed to this court. We have determined that the summary judgment was appropriate because Tennessee does not recognize the tort of interference with prospective economic advantage and because the project engineer’s statements concerning the unsuccessful bidder were true.

I.

In the early 1990's, the City of Clarksville hired Story Engineering Co., Inc. to perform a feasibility study concerning the capacity of its natural gas transmission system. Roddy L. Story, the principal of Story Engineering who was to perform the work, is a Vanderbilt-trained engineer who had been employed by Nashville Gas Company for thirty-two years. Mr. Story had assisted with the design of Clarksville’s existing system in the 1950's.

After Mr. Story reported that Clarksville’s system was no longer adequate to meet the expected demand in the case of severe weather, the City retained him as project engineer to design the improvements and to prepare the plans and specifications and other contract documents for the project. The project Mr. Story designed called for the installation of 116,900 linear feet of 12¾-inch O.D. coated steel natural gas pipe with fittings, 600 linear feet of 6e-inch O.D. coated steel gas pipe, and various regulator stations, bridge crossings, tie-ins, and related appurtenances.

Because the quality of the workmanship on the project was extremely important, Mr. Story included in the specifications and contract documents a requirement that the successful bidder must have constructed a similar natural gas

-2- transmission pipeline project within three years preceding the date of the Clarksville project.1 Moore Construction Company, Inc. was one of the nine companies submitting bids on the project. Mr. Story requested Moore Construction Company to provide additional information because its original bid did not contain sufficient information about its prior jobs or the personnel who would perform the work. Moore Construction Company’s supplemental information revealed that the last gas pipeline it had constructed was in 1984 in Louisiana.

After evaluating the bids, Mr. Story informed the City that King Pipeline and Utility Company, Inc. had submitted the lowest bid of $3,398,808 and that it had recently completed four similar projects. He also informed the City that Moore Construction Company had submitted the second lowest bid of $3,432,378 but that it had not completed a similar project within the past three years. Moore Construction Company appeared at a meeting of the Clarksville Utility Committee shortly after the bids were opened and requested that it be awarded the contract in accordance with the City’s procurement rule that favors local contractors when there is less than a five percent difference between their bid and the lowest bid. The committee declined to recommend Moore Construction Company because it did not meet the specification’s qualifications for performing the work. When the matter came before the Clarksville City Council, Mr. Story informed the council members that Moore Construction Company was “not qualified to construct the project and that the City of Clarksville, Tennessee, and its individual council members . . . would expose itself and themselves to liability should it award the contract to [Moore

1 The Specifications and Contract Documents stated:

The Owner will require as minimum qualification for Bidder to have successfully completed within the last thirty-six months the installation of a natural gas transmission pipeline and regulator station system similar in size and complexity to this Project. Bidder must have previous experience in welding on high pressure gas lines, hydrostatic pressure testing, and filling of pipelines with high pressure natural gas.

-3- Construction Company] . . . instead of following [his] recommendation . . ..” 2 Thereafter, the City Council awarded the contract to King Pipeline.

In November 1992, Moore Construction Company and its president filed suit against Mr. Story and Story Engineering in the Circuit Court for Montgomery County alleging that Mr. Story’s statements to the City Council had defamed and disparaged them and had interfered with their prospective economic advantage. They requested $300,000 in actual and $600,000 in punitive damages. Mr. Story later moved for summary judgment. The trial court granted the motion and dismissed each of Moore Construction Company’s claims on the ground that Mr. Story’s statements to the City Council concerning Moore Construction Company’s qualifications under the project’s specifications were true.

II.

Summary judgments enjoy no presumption of correctness on appeal. See City of Tullahoma v. Bedford County, 938 S.W.2d 408, 412 (Tenn. 1997); McClung v. Delta Square Ltd. Partnership, 937 S.W.2d 891, 894 (Tenn. 1996). Accordingly, reviewing courts must make a fresh determination concerning whether the requirements of Tenn. R. Civ. P. 56 have been satisfied. See Hunter v. Brown, 955 S.W.2d 49, 50-51 (Tenn. 1997); Mason v. Seaton, 942 S.W.2d 470, 472 (Tenn. 1997). Summary judgments are appropriate only when there are no genuine factual disputes with regard to the claim or defense embodied in the motion and when the moving party is entitled to a judgment as a matter of law. See Tenn. R. Civ. P. 56.04; Bain v. Wells, 936 S.W.2d 618, 622 (Tenn. 1997); Carvell v. Bottoms, 900 S.W.2d 23, 26 (Tenn. 1995).

Courts reviewing summary judgments must view the evidence in the light most favorable to the nonmoving party and must also draw all reasonable inferences in the nonmoving party’s favor. See Robinson v. Omer, 952 S.W.2d 423, 426 (Tenn. 1997);

2 The City Council’s resolution awarding the contract to King Pipeline recited that

There was extended discussion regarding the option of awarding the contract to Moore Construction Co., a local contractor and the second low bidder, under the 5% provision. Mr. Story stated that in accordance with the bid specifications, it was his opinion that Moore Construction Co.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Robinson v. Omer
952 S.W.2d 423 (Tennessee Supreme Court, 1997)
Mason v. Seaton
942 S.W.2d 470 (Tennessee Supreme Court, 1997)
Mike v. Po Group, Inc.
937 S.W.2d 790 (Tennessee Supreme Court, 1996)
Alexander v. Memphis Individual Practice Ass'n
870 S.W.2d 278 (Tennessee Supreme Court, 1994)
Nelson v. Martin
958 S.W.2d 643 (Tennessee Supreme Court, 1997)
Strauss v. WYATT, TARRANT, COMBS
911 S.W.2d 727 (Court of Appeals of Tennessee, 1995)
McClung v. Delta Square Ltd. Partnership
937 S.W.2d 891 (Tennessee Supreme Court, 1996)
Carvell v. Bottoms
900 S.W.2d 23 (Tennessee Supreme Court, 1995)
Stones River Motors, Inc. v. Mid-South Publishing Co.
651 S.W.2d 713 (Court of Appeals of Tennessee, 1983)
City of Tullahoma v. Bedford County
938 S.W.2d 408 (Tennessee Supreme Court, 1997)
Byrd v. Hall
847 S.W.2d 208 (Tennessee Supreme Court, 1993)
Alexander v. Inman
825 S.W.2d 102 (Court of Appeals of Tennessee, 1991)
McCall v. Wilder
913 S.W.2d 150 (Tennessee Supreme Court, 1995)
Bain v. Wells
936 S.W.2d 618 (Tennessee Supreme Court, 1997)
Hunter v. Brown
955 S.W.2d 49 (Tennessee Supreme Court, 1997)
Press, Inc. v. Verran
569 S.W.2d 435 (Tennessee Supreme Court, 1978)
Quality Auto Parts Co. v. Bluff City Buick Co.
876 S.W.2d 818 (Tennessee Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
Moore Construction Co. v. Story Engineering, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-construction-co-v-story-engineering-tennctapp-1998.