Moore Bros. Construction Co. v. State

10 Ill. Ct. Cl. 625, 1939 Ill. Ct. Cl. LEXIS 45
CourtCourt of Claims of Illinois
DecidedMay 26, 1939
DocketNo. 2794
StatusPublished

This text of 10 Ill. Ct. Cl. 625 (Moore Bros. Construction Co. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moore Bros. Construction Co. v. State, 10 Ill. Ct. Cl. 625, 1939 Ill. Ct. Cl. LEXIS 45 (Ill. Super. Ct. 1939).

Opinion

Mr. Justice Yantis

delivered the opinion of the court:

This claim arises out of the construction of a part of S. B. I. Route 177, Section 109, which extends from the Junction with S. B. 1.15 in Okawville easterly seven and one-half (7%) miles to Station 449 in Washington County. From Station 449 Route 177 continued east through New Minden where it intersects Route 153.

The original survey for Route 177 was made by the Division of Highways in 1926. Two routes out of Okawville were indicated on the survey maps, a so-called east route and a north route. The Chief Highway Engineer indicated his opinion that the north route was the most feasible. Individuals interested in these two routes procured deeds for the respective rights-of-way for as much property as they could obtain. Deeds for the north route were never delivered to the Divisions, but such deeds were procured in an effort to induce the Division to select the respective routes.

On March 24, 1931 the Director of the Department of Public Works and Buildings and the Chief Highway Engineer entered an order officially locating the road over the east route. This road began at Station 28+00 in Okawville, went due east about three miles, then northeast about four miles to Station 120, from which point the road extended eastward to Station 449. Necessary right-of-way for this route was partly obtained by voluntary conveyances, and in February, 1932 the Department caused suit to be filed in the County Court of Washington County to condemn the right-of-way for the east route over such required lands as had not been deeded. July 1, 1932 the County Court entered judgment authorizing construction over the east route and awarded damages in excess of $2,500.00, which together with court costs and other expenses was raised by the people of the community, in a total sum of over $3,500.00.

On September 30, 1932 the Department awarded a contract to George B. Richardson of Decatur for the construction of the Plum Creek Bridge just east of Okawville on said route; also a contract to claimant for constrnction of culverts, grading, concrete pavement, etc., for such east route and extending eastward from Station 120, at a total project cost of $128,329.60.

October 13, 1932 claimant began construction operations. October 20, 1932 a contract for the project was executed by the claimant and the Department of Public Works and Buildings. This contract provided that claimant would complete the project on or before June 15, 1933. Claimant sub-contracted all grading operations to A. L. Brady, and the subcontractor moved in his equipment and began operations November 7th. Richardson began operations on the Plum Creek Bridge on January 11, 1933, using a crane owned by claimant. Prior to January 17, 1933 claimant ordered cement from various companies and on the latter date cancelled the order for the unshipped balance of 23,978 barrels with the Alpha Portland Cement Company, and was authorized to order same from the Marquette Cement Manufacturing Company.

Meanwhile, citizens of the community who were interested in the north route continued their efforts for a relocation over the so-called north route. This portion would extend north out of Okawville from Station 28+00, and would then turn east for a distance of several miles until it reached Station 120, where the two disputed routes would intersect. January 18, 1933 the Highway Division ordered claimant to cease operations, and on the following day rescinded this order. The Attorney General rendered an Opinion to the Department under dates of January 25th, April 7th, and May 31, 1933; that the Department did not have power to change the location and could not acquire the right-of-way over the north route by eminent domain because it had already exhausted such power by locating the road and acquiring the right-of-way over the east route. On February 24,1933 claimant was notified by the Department through its District Engineer that no work was to be done on that portion of the contract west of Station 120, but that there were no restrictions in regard to the balance of the work. This restriction affected only the short disputed sections involved in the two proposed routes.

Article 3.2 of the Standard Specifications for Road & Bridge Construction, which was a part of the contract in question, provides that a Progress Schedule shall be filed by the contractor when requested. Under such schedule as submitted by claimant he agreed to finish the paving at Station 10+09, being a short section of pavement in Okawville just beyond the west terminal of the two disputed routes, by June 1, 1933. This date must be borne in mind when considering any change in plans, expense or any inconvenience which was caused by reason of the non-construction by claimant of the disputed section of paving. Claimant R. J. Moore testified that of the equipment that was on the job west of Station 120 none was used on any other work until after it was released on July 10, 1933; that the culvert equipment was idle until July 10th and that the other equipment was idle up to April 15,1933.

The controversy over the north and south routes was taken by appeal to the Supreme Court and on February 21, 1935 an Opinion was filed by the latter, the case being entitled “The Department of Public Works & Buildings vs. Adolph L. Bchlich, 359 Ill. 337,” wherein the court held that the Department had no authority to change the route, and the judgment of the Circuit Court of Washington County was reversed. On September 6, 1933 respondent, through the Division of Highways, notified claimant in writing that due to right-of-way difficulties it was understood that claimant would be unable to complete its paving on the portion of the work then in dispute, and that claimant was under no obligation to keep its equipment on this section after it had completed the work within the limits on which the right-of-way was settled. Claimant offered in 1935 to complete the work at an increased cost estimate, and on July 16, 1935 they were informed that if they proceeded with the work, it would have to be in accordance with the plans and at the unit prices stated in the contract. By agreement a cancellation of that portion of the contract pertaining to the section of road in dispute was effected, and claimant was released from performing such work, the release being without penalty and with the understanding that the contractors may proceed to secure judgment through the Court of Claims for any losses previously incurred, it being understood that claimant reserves all rights to file and prosecute a claim against the State for damages sustained, by reason of the failure by the State to secure the right-of-way, and for any other damages incident thereto. Conferences were had between the representatives of the Highway Department and claimant in an effort to arrive at what damages claimant may have suffered. The figures arrived at by the Highway Department, based upon rental value of equipment for the period of delay from June 19th to September 6th and for time allowance for A. P. Moore, G-eneral Superintendent, J. Gf. Moore, Foreman, and B. Stephen, Time-keeper, and workmen’s compensation insurance amounts to a total of $9,467.51. This was later corrected to $9,011.33. Sub-contractor Brady’s damages were estimated at $7,125.38. Claimant contends that its actual damages for itself and Brady by reason of extra cost for superintendents, rentals, etc., amounted to $13,483.27 and of the Sub-contractor Brady for whom it acts, of an additional sum of $11,176.35.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Hinckley v. Pittsburgh Bessemer Steel Co.
121 U.S. 264 (Supreme Court, 1887)
Guerini Stone Co. v. P. J. Carlin Construction Co.
240 U.S. 264 (Supreme Court, 1916)
Underground Construction Co. v. Sanitary District
11 N.E.2d 361 (Illinois Supreme Court, 1937)
Department of Public Works & Buildings v. Schlich
194 N.E. 587 (Illinois Supreme Court, 1935)

Cite This Page — Counsel Stack

Bluebook (online)
10 Ill. Ct. Cl. 625, 1939 Ill. Ct. Cl. LEXIS 45, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moore-bros-construction-co-v-state-ilclaimsct-1939.