Opinion issued June 20, 2013.
In The
Court of Appeals For The
First District of Texas ———————————— NO. 01-12-00047-CV ——————————— MOODY NATIONAL BUFFALO SPEEDWAY MT, L.P., Appellant V. SIRIUS SOLUTIONS, LLLP, Appellee
On Appeal from the 152nd District Court Harris County, Texas Trial Court Case No. 2009-38998
MEMORANDUM OPINION
Moody National Buffalo Speedway MT, L.P., the landlord in this dispute,
appeals a judgment ordering that it take nothing on its claims for breach of a lease
and awarding Sirius Solutions, LLLP, the tenant, actual damages of $56,278.11 on its counterclaim for breach of the same lease, plus attorney’s fees, pre- and post-
judgment interest, and costs.
Hurricane Ike damaged the leased premises during the last year of the
parties’ multi-year lease. Within days, Sirius moved to a temporary office space,
and the parties agreed that Sirius’s duty to pay rent for the damaged office space
was abated. This dispute is about whether Moody’s subsequent repair of the
damage caused by Hurricane Ike triggered Sirius’s obligation to resume paying
rent for the remainder of the lease’s term.
Sirius refused to pay, the lease terminated, and Moody withheld Sirius’s
deposits and other advance payments and sued for the balance it claimed was due.
Sirius countersued for the return of its deposits and other advance payments. After
a bench trial, the trial court rendered a take nothing judgment on Moody’s claims
and awarded Sirius $56,278.11 in actual damages, $135,000 in attorney’s fees and
costs, conditional attorney’s fees on appeal, and interest. On appeal, Moody
asserts the trial court’s findings of fact are legally erroneous and legally and
factually insufficient to support its conclusions of law.
We affirm.
Background
Sirius is a business consulting firm. It leased office space from Moody in an
eleven-story building at 3700 Buffalo Speedway in Houston. Sirius leased the
2 entire eleventh floor, most of the tenth floor, and a small space on the third floor.
The parties’ multi-year lease was to expire on July 31, 2009. Before Hurricane Ike
struck in September 2008, the parties were already negotiating a possible extension
of the lease. But Sirius was also exploring the possibility of relocating after the
lease expired.
Hurricane Ike struck on September 13, 2008. It damaged the roof of 3700
Buffalo Speedway, rendering Sirius’s office space uninhabitable. Sirius was able
to quickly lease temporary space in a building owned by a Moody affiliate. The
parties agreed that, under the terms of the lease, Sirius’s obligation to pay rent for
the damaged office space was abated to the extent the making of the repairs
interfered with Sirius’s business. However, they ultimately sued one another over
whether and when Moody’s repair of the space triggered Sirius’s obligation to
resume paying rent for the remainder of the lease’s term.
The lease expressly addressed the parties’ obligations in the event of a
partial destruction of the building. Under section 20.1, Moody was obligated to
repair a partial destruction “within 60 days from receipt of [insurance proceeds]”
or, if the repairs could not be made within 60 days, Moody, at its option, could
make the repairs “within a reasonable time.” The lease expressly provided that a
partial destruction of the building would not terminate the lease; however, it would
entitle Sirius to a “proportionate reduction of rent while such repairs are being
3 made, based upon the extent to which the making of such repairs shall interfere
with the business of [Sirius] on the Premises.”
Moody and Sirius presented sharply contrasting accounts of what happened
after Ike. Stephen Woods, the vice president of Moody’s commercial office
division, stated that the repairs to Sirius’s leased space were completed by April 1,
2009, and that, as of that date, Sirius was both free to move back into the space and
obligated to pay rent for the last four months of the lease’s term. According to
Moody, when Sirius refused to pay, Moody was justified in retaining Sirius’s
deposits and advance payments and in bringing suit for the balance of the unpaid
rent and late charges.
To support this contention, Moody’s construction expert relied on
certificates of substantial completion dated March 27 and April 1, within eight
weeks of the date construction began. He also testified that the eight weeks it took
to rebuild Sirius’s space was “reasonable and normal” and, considering the
circumstances in Houston at the time, “probably better than normal[,] honestly.”
While Moody acknowledged that tenants other than Sirius had their spaces
rebuilt earlier, Woods attributed the delay in repairing Sirius’s space to Sirius.
Woods testified that Sirius informed Moody by email that “[t]he optimal rebuild
for Sirius Solutions would include modifications from their former conditions” and
that rebuilding to the pre-Ike condition “would likely prompt a move next summer
4 when [Sirius’s] lease expires.” Woods testified that, based on these
communications, he understood that Sirius did not want its space rebuilt to the
exact configuration that existed before Ike. But, according to Woods, Sirius would
not communicate its wishes to Moody to allow Moody to complete the repairs to
Sirius’s satisfaction. Woods stated that Moody finally decided to move forward
with the repairs without Sirius’s input. Due to Sirius’s delay, Moody was not able
to meet its anticipated goal of substantial completion by February 1, 2009. Instead,
it was February 3, 2009 before the construction permits for Sirius’s space were
issued.
Sirius painted a different picture. Its CEO, Kristi Chickering, testified that
no one from Moody ever asked for Sirius’s input in the rebuilding process. She
said Woods told her that Moody would rebuild the space to its pre-Ike
configuration, adding that use of the same layout would speed up the process
because it would eliminate the need for building permits. Chickering’s testimony
in this regard was consistent with a November 21 email from Woods: “Today I
gave the contractor permission to start build back of the 10th and 11th floors to the
same specifications that they were prior to Hurricane Ike.”
Chickering also testified that Moody did not notify Sirius in advance that the
space was repaired and ready for move-in on April 1. Instead, according to
Chickering, Sirius’s first notice that the space was ready came in form of a late rent
5 payment notice dated April 14. Chickering and another Sirius employee visited
3700 Buffalo Speedway shortly after receiving that notice. Chickering testified
that, during that April visit, Sirius’s space was designated a hard-hat area and
construction workers were still active on the tenth and eleventh floors. She also
said wires and cables were hanging from the ceiling, and a dumpster was collecting
leaking water. Chickering stated the space was not ready for Sirius to return and
that Sirius could not use the space to conduct its business at that time.
Documentary evidence supports Chickering’s testimony: the Certificates of
Occupancy for various portions of Sirius’s space, without which a tenant is
prohibited from occupying a space, were not issued until May 15, May 20, and
June 23, 2009.
Free access — add to your briefcase to read the full text and ask questions with AI
Opinion issued June 20, 2013.
In The
Court of Appeals For The
First District of Texas ———————————— NO. 01-12-00047-CV ——————————— MOODY NATIONAL BUFFALO SPEEDWAY MT, L.P., Appellant V. SIRIUS SOLUTIONS, LLLP, Appellee
On Appeal from the 152nd District Court Harris County, Texas Trial Court Case No. 2009-38998
MEMORANDUM OPINION
Moody National Buffalo Speedway MT, L.P., the landlord in this dispute,
appeals a judgment ordering that it take nothing on its claims for breach of a lease
and awarding Sirius Solutions, LLLP, the tenant, actual damages of $56,278.11 on its counterclaim for breach of the same lease, plus attorney’s fees, pre- and post-
judgment interest, and costs.
Hurricane Ike damaged the leased premises during the last year of the
parties’ multi-year lease. Within days, Sirius moved to a temporary office space,
and the parties agreed that Sirius’s duty to pay rent for the damaged office space
was abated. This dispute is about whether Moody’s subsequent repair of the
damage caused by Hurricane Ike triggered Sirius’s obligation to resume paying
rent for the remainder of the lease’s term.
Sirius refused to pay, the lease terminated, and Moody withheld Sirius’s
deposits and other advance payments and sued for the balance it claimed was due.
Sirius countersued for the return of its deposits and other advance payments. After
a bench trial, the trial court rendered a take nothing judgment on Moody’s claims
and awarded Sirius $56,278.11 in actual damages, $135,000 in attorney’s fees and
costs, conditional attorney’s fees on appeal, and interest. On appeal, Moody
asserts the trial court’s findings of fact are legally erroneous and legally and
factually insufficient to support its conclusions of law.
We affirm.
Background
Sirius is a business consulting firm. It leased office space from Moody in an
eleven-story building at 3700 Buffalo Speedway in Houston. Sirius leased the
2 entire eleventh floor, most of the tenth floor, and a small space on the third floor.
The parties’ multi-year lease was to expire on July 31, 2009. Before Hurricane Ike
struck in September 2008, the parties were already negotiating a possible extension
of the lease. But Sirius was also exploring the possibility of relocating after the
lease expired.
Hurricane Ike struck on September 13, 2008. It damaged the roof of 3700
Buffalo Speedway, rendering Sirius’s office space uninhabitable. Sirius was able
to quickly lease temporary space in a building owned by a Moody affiliate. The
parties agreed that, under the terms of the lease, Sirius’s obligation to pay rent for
the damaged office space was abated to the extent the making of the repairs
interfered with Sirius’s business. However, they ultimately sued one another over
whether and when Moody’s repair of the space triggered Sirius’s obligation to
resume paying rent for the remainder of the lease’s term.
The lease expressly addressed the parties’ obligations in the event of a
partial destruction of the building. Under section 20.1, Moody was obligated to
repair a partial destruction “within 60 days from receipt of [insurance proceeds]”
or, if the repairs could not be made within 60 days, Moody, at its option, could
make the repairs “within a reasonable time.” The lease expressly provided that a
partial destruction of the building would not terminate the lease; however, it would
entitle Sirius to a “proportionate reduction of rent while such repairs are being
3 made, based upon the extent to which the making of such repairs shall interfere
with the business of [Sirius] on the Premises.”
Moody and Sirius presented sharply contrasting accounts of what happened
after Ike. Stephen Woods, the vice president of Moody’s commercial office
division, stated that the repairs to Sirius’s leased space were completed by April 1,
2009, and that, as of that date, Sirius was both free to move back into the space and
obligated to pay rent for the last four months of the lease’s term. According to
Moody, when Sirius refused to pay, Moody was justified in retaining Sirius’s
deposits and advance payments and in bringing suit for the balance of the unpaid
rent and late charges.
To support this contention, Moody’s construction expert relied on
certificates of substantial completion dated March 27 and April 1, within eight
weeks of the date construction began. He also testified that the eight weeks it took
to rebuild Sirius’s space was “reasonable and normal” and, considering the
circumstances in Houston at the time, “probably better than normal[,] honestly.”
While Moody acknowledged that tenants other than Sirius had their spaces
rebuilt earlier, Woods attributed the delay in repairing Sirius’s space to Sirius.
Woods testified that Sirius informed Moody by email that “[t]he optimal rebuild
for Sirius Solutions would include modifications from their former conditions” and
that rebuilding to the pre-Ike condition “would likely prompt a move next summer
4 when [Sirius’s] lease expires.” Woods testified that, based on these
communications, he understood that Sirius did not want its space rebuilt to the
exact configuration that existed before Ike. But, according to Woods, Sirius would
not communicate its wishes to Moody to allow Moody to complete the repairs to
Sirius’s satisfaction. Woods stated that Moody finally decided to move forward
with the repairs without Sirius’s input. Due to Sirius’s delay, Moody was not able
to meet its anticipated goal of substantial completion by February 1, 2009. Instead,
it was February 3, 2009 before the construction permits for Sirius’s space were
issued.
Sirius painted a different picture. Its CEO, Kristi Chickering, testified that
no one from Moody ever asked for Sirius’s input in the rebuilding process. She
said Woods told her that Moody would rebuild the space to its pre-Ike
configuration, adding that use of the same layout would speed up the process
because it would eliminate the need for building permits. Chickering’s testimony
in this regard was consistent with a November 21 email from Woods: “Today I
gave the contractor permission to start build back of the 10th and 11th floors to the
same specifications that they were prior to Hurricane Ike.”
Chickering also testified that Moody did not notify Sirius in advance that the
space was repaired and ready for move-in on April 1. Instead, according to
Chickering, Sirius’s first notice that the space was ready came in form of a late rent
5 payment notice dated April 14. Chickering and another Sirius employee visited
3700 Buffalo Speedway shortly after receiving that notice. Chickering testified
that, during that April visit, Sirius’s space was designated a hard-hat area and
construction workers were still active on the tenth and eleventh floors. She also
said wires and cables were hanging from the ceiling, and a dumpster was collecting
leaking water. Chickering stated the space was not ready for Sirius to return and
that Sirius could not use the space to conduct its business at that time.
Documentary evidence supports Chickering’s testimony: the Certificates of
Occupancy for various portions of Sirius’s space, without which a tenant is
prohibited from occupying a space, were not issued until May 15, May 20, and
June 23, 2009.
Chickering also testified that Moody rebuilt Sirius’s space in a manner that
made it unacceptable to Sirius. Sirius is a consulting firm. Its employees require
private offices in which they can conduct confidential meetings. Sirius also
requires conference rooms to accommodate larger meetings and reception areas for
client visits, which are frequent. Chickering testified that Sirius conducts litigation
consulting services and, in order for its employees to render proper expert witness
services, Sirius needs to be able to keep certain documents on a secure server,
separate from other documents. Thus, Sirius needed two server rooms.
6 It is undisputed that Moody did not rebuild Sirius’s space to its pre-Ike
configuration. Moody reduced the number of rooms on the eleventh floor from
fifty to thirty-eight and on the tenth from fourteen to seven. The reception area on
the eleventh floor was removed, as was a training room. Sirius had two server
rooms before Ike; after the repairs, it had only one. For the most part, Moody
sought to justify these changes as a middle ground between returning the space to
its pre-Ike condition and incorporating the draft plans it received from Sirius in
November. However, Woods testified that the removal of the reception area was a
mistake: Moody “literally forgot to design the reception space back into the 11th
Floor.” Similarly, with respect to the reduction in the number of server rooms
from two to one, Woods testified that he did not know there were two; he thought
there was only one.
The trial court entered findings of fact and conclusions of law. Its findings
state that Moody did not “return the Leased Premises to the same specification as
prior to the destruction” and that Moody’s failure to do so impaired “Sirius’s
ability to run its business in the Leased Premises.” The trial court accordingly
concluded that Sirius did not breach the lease by failing to pay rent during the last
four months of the term of the lease, and, instead, Moody breached the lease by
failing to return $56,278.11 in deposits and other payments. It entered judgment
7 that Moody take nothing on its claim for unpaid rent and awarded Sirius the return
of its deposit and other advance payments, plus attorney’s fees, interest, and costs.
Discussion
Moody contends the trial court erred in rendering judgment for Sirius and
against Moody because the trial court’s “findings of fact are legally erroneous and
legally and factually insufficient to support its conclusions of law.”
A. Standard of Review
In an appeal from a bench trial, we review a trial court’s conclusions of law
de novo. Zenner v. Lone Star Striping & Paving, L.L.C., 371 S.W.3d 311, 314
(Tex. App.—Houston [1st Dist.] 2012, pet. denied) (citing BMC Software Belgium,
N.V. v. Marchand, 83 S.W.3d 789, 794 (Tex. 2002)). We will uphold the
conclusions on appeal if the judgment can be sustained on any legal theory
supported by the evidence. Id. at 314–15. A trial court’s conclusions of law may
not be challenged for factual sufficiency of the evidence, but we may review the
legal conclusions drawn from the facts to determine their correctness. Id. at 314.
In an appeal from a bench trial, the trial court’s findings of fact have the
same weight as a jury verdict. Catalina v. Blasdel, 881 S.W.2d 295, 297 (Tex.
1994); Nguyen v. Yovan, 317 S.W.3d 261, 269–70 (Tex. App.—Houston [1st Dist.]
2009, pet. denied). We review a trial court’s findings of fact under the same legal
and factual sufficiency of the evidence standards used when determining whether
8 sufficient evidence exists to support an answer to a jury question. Catalina, 881
S.W.2d at 297; Nguyen, 317 S.W.3d at 270.
The test for legal sufficiency is “whether the evidence at trial would enable
reasonable and fair-minded people to reach the verdict under review.” City of
Keller v. Wilson, 168 S.W.3d 802, 827 (Tex. 2005). In making this determination,
we credit evidence favoring the jury verdict if reasonable jurors could and
disregard contrary evidence unless reasonable jurors could not. Id. at 822. The
trier of fact is the sole judge of the credibility of the witnesses and the weight to
give their testimony. Id. at 819. Although we consider the evidence in the light
most favorable to the challenged findings, indulging every reasonable inference
that supports them, we may not disregard evidence that allows only one inference.
Id. at 822.
In reviewing a factual sufficiency point, we consider all the evidence
supporting and contradicting the finding. Plas–Tex, Inc. v. U.S. Steel Corp., 772
S.W.2d 442, 445 (Tex. 1989). We set aside the verdict only if the finding is so
contrary to the overwhelming weight of the evidence as to be clearly wrong and
unjust. Pitts & Collard, L.L.P. v. Schechter, 369 S.W.3d 301, 312 (Tex. App.—
Houston [1st Dist.] 2011, no pet.) (citing Cain v. Bain, 709 S.W.2d 175, 176 (Tex.
1986)). The trial court, as finder of fact, is the sole judge of the credibility of the
witnesses and the weight to be given their testimony. Salomon v. Lesay, 369
9 S.W.3d 540, 549 (Tex. App.—Houston [1st Dist.] 2012, no pet.). The fact finder
may believe or disbelieve the testimony of a witness, in whole or in part, and it
may resolve any inconsistencies in a witness’s testimony. Id.
B. Sirius’s Duty to Pay Rent was Abated While Repairs Interfered with its Business
Moody contends the Lease did not require Moody to restore Sirius’s space to
its pre-Ike configuration, and, therefore, the trial court erred in concluding that
Moody’s failure to do so constitutes a breach of the lease. Sirius responds that the
trial court properly rejected Moody’s contract claim because the lease did not
require Sirius to pay rent for a space it could not use. We agree with Sirius.
Section 20.1 of the lease provided that Sirius “shall be entitled to a
proportionate reduction of rent while such repairs are being made, based upon the
extent to which the making of such repairs shall interfere with the business of
[Sirius] on the Premises.”1 The parties advance different definitions of the term
1 In its entirety, section 20.1 provides:
10 “repair” and disagree about whether the use of the term obligated Moody to restore
the space to its exact pre-Ike specifications. We need not address these competing
definitions, however, because the plain language of the lease makes clear that the
parties agreed that Sirius had no obligation to pay rent while the repairs were being
made, to the extent the repairs prevented Sirius from using the space to operate its
business. Put differently, Sirius’s obligation to resume paying rent would begin
only when the making of the repairs no longer interfered with its business on the
premises.
The trial court made several relevant findings of fact. The trial court found
that “Moody significantly and materially altered the specifications of the Leased
Premises” and “failed to return the Leased Premises to the same specification.” It
is undisputed that Moody altered Sirius’s space by, among other things, decreasing
20.1. Partial Destruction: In the event of a partial destruction of the Premises during the term hereof, from any cause covered by insurance, Landlord must repair the same to the extent insurance proceeds are received by Landlord for such repairs, and within 60 days from receipt of such proceeds under then existing governmental laws and regulations. Such partial destruction shall not terminate this Lease and Tenant shall be entitled to a proportionate reduction of rent while such repairs are being made, based upon the extent to which the making of such repairs shall interfere with the business of Tenant on the Premises. If such repairs cannot be made within said 60 day period, Landlord, at its option, may make the repairs within a reasonable time. If Landlord elects to make said repairs, this Lease will continue in effect and the rent will be proportionately abated as stated above. If the repairs cannot be made within 60 days from receipt of insurance proceeds by Landlord, and Landlord elects not to make said repairs, this Lease may be terminated at the option of either party. 11 the amount of floor space, eliminating the reception area, reducing the number and
size of offices, and giving a small portion of the space to another tenant without
Sirius’s consent, knowledge, or approval. Viewed in the light most favorable to
the verdict, the evidence supports the trial court’s finding concerning alteration of
Sirius’s space. See City of Keller, 168 S.W.3d at 822. And, although Moody
disputes the reason it altered the Sirius’s space, it does not dispute the fact of
alteration. Because the evidence is undisputed, the trial court’s finding is not “so
contrary to the overwhelming weight of the evidence as to be clearly wrong and
unjust.” See Cain, 709 S.W.2d at 176; Pitts & Collard, L.L.P., 369 S.W.3d at 312.
We therefore conclude that the evidence is legally and factually sufficient to
support this finding.
The trial court also found that the space, as repaired by Moody, was
“unusable” by Sirius. Chickering testified that Sirius required numerous private
offices, conference rooms, and a separate, secure server room to carry out its
normal business. She also testified that the changes Moody made to the space
rendered it unusable for Sirius’s business. Chickering’s testimony was undisputed.
This undisputed evidence supports the trial court’s finding that Sirius’s space was
not usable; thus, the finding is not against the overwhelming weight of the
evidence. See City of Keller, 168 S.W.3d at 822; Pitts & Collard, L.L.P., 369
12 S.W.3d at 312. Therefore, we conclude that legally and factually sufficient
evidence supports this finding.
The parties agree that Sirius’s duty to pay rent was abated while repairs of
its space interfered with its ability to conduct its business. The findings above
show that Sirius was unable to conduct its business—or that, in terms of the lease,
the repairs interfered with Sirius’s ability to conduct its business—throughout the
remainder of the lease’s term. It therefore follows that Sirius’s obligation to pay
rent remained abated for the remainder of the lease’s term. Because it had no
contractual obligation to pay rent, Sirius did not breach the lease by failing to pay
rent. See Dorsett v. Cross, 106 S.W.3d 213, 217 (Tex. App.—Houston [1st Dist.]
2003, pet. denied) (“A breach occurs when a party fails or refuses to do something
he has promised to do.”); see also Enron Oil & Gas Co. v. Joffrion, 116 S.W.3d
215, 221 (Tex. App.—Tyler 2003, no pet.) (“It should go without saying that a
breach [of contract] is determined by comparing the terms of a contract with the
actions of the alleged breaching party.”). The trial court reached this same
conclusion, stating, “Sirius did not breach the Lease Agreement.”
In conclusion, viewed in the light most favorable to the judgment, the
evidence supports the trial court’s findings that Moody failed to provide a space
that Sirius could use to operate its business. Therefore, the lease, which obligated
Sirius to pay rent only to the extent such repairs did not interfere with the business
13 of Sirius, did not require Sirius to resume paying rent. Accordingly, we hold that
the trial court did not err by concluding that Sirius did not breach the lease by
failing to pay the rent Moody claimed was due beginning in April 2009.
C. Moody Breached by Withholding Advance Payments
Moody also challenges the trial court’s conclusion that Moody breached the
lease by withholding advanced payments made by Sirius. Moody’s argument is
premised on Sirius having breached the lease by failing to pay rent for the months
of April through July of 2009. We have concluded that the evidence supports the
trial court’s findings and conclusions that Sirius was not obligated to resume
paying rent during this period and, therefore, did not breach the lease. Because we
have rejected the premise for Moody’s argument, we overrule this argument.
D. Moody’s Other Arguments for Reversal
Moody raises a number of other challenges to the trial court’s judgment.
Moody challenges the trial court’s findings and conclusions that Moody: (1) did
not timely repair the space, (2) repudiated the Lease, and (3) caused the
consideration to fail. Each of these is an alternative basis to support the trial
court’s judgment. Because we determine the trial court properly concluded Sirius
did not breach the lease by failing to pay rent and Moody did breach by failing to
return Sirius’s advance payments, the trial court’s judgment can be upheld on that
basis. Accordingly, we need not address these issues. See Ginther v. Taub, 675
14 S.W.2d 724, 725 (Tex. 1984) (declining to address other issues after deciding
independent ground existed for supporting judgment); Reinhardt v. Walker, No.
14-07-00304-CV, 2008 WL 2390482, at *5 (Tex. App.—Houston [14th Dist.] June
12, 2008, pet. denied) (mem. op.) (declining to address challenges to trial court’s
findings providing alternative basis for judgment); Satterfield v. Vess, No. 2-04-
287-CV, 2005 WL 1838978, at *2 (Tex. App.—Fort Worth Aug. 4, 2005, no pet.)
(mem. op.) (declining to address challenge to one of trial court’s conclusions of
law after overruling challenges to other conclusions that independently supported
judgment); cf., e.g., Humane Soc’y of Dallas v. The Dallas Morning News L.P.,
180 S.W.3d 921, 923 (Tex. App.—Dallas 2005, no pet.) (citing Star–Telegram,
Inc. v. Doe, 915 S.W.2d 471, 473 (Tex. 1995)) (explaining that where trial court
does not specify basis for summary judgment, appellant must show each
independent ground for judgment is insufficient in order to prevail on appeal).
Conclusion
We affirm the trial court’s judgment.
Rebeca Huddle Justice
Panel consists of Justices Keyes, Sharp, and Huddle.