Moody National Buffalo Speedway Mt, L.P. v. Sirus Solutions, LLLP

CourtCourt of Appeals of Texas
DecidedJune 20, 2013
Docket01-12-00047-CV
StatusPublished

This text of Moody National Buffalo Speedway Mt, L.P. v. Sirus Solutions, LLLP (Moody National Buffalo Speedway Mt, L.P. v. Sirus Solutions, LLLP) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moody National Buffalo Speedway Mt, L.P. v. Sirus Solutions, LLLP, (Tex. Ct. App. 2013).

Opinion

Opinion issued June 20, 2013.

In The

Court of Appeals For The

First District of Texas ———————————— NO. 01-12-00047-CV ——————————— MOODY NATIONAL BUFFALO SPEEDWAY MT, L.P., Appellant V. SIRIUS SOLUTIONS, LLLP, Appellee

On Appeal from the 152nd District Court Harris County, Texas Trial Court Case No. 2009-38998

MEMORANDUM OPINION

Moody National Buffalo Speedway MT, L.P., the landlord in this dispute,

appeals a judgment ordering that it take nothing on its claims for breach of a lease

and awarding Sirius Solutions, LLLP, the tenant, actual damages of $56,278.11 on its counterclaim for breach of the same lease, plus attorney’s fees, pre- and post-

judgment interest, and costs.

Hurricane Ike damaged the leased premises during the last year of the

parties’ multi-year lease. Within days, Sirius moved to a temporary office space,

and the parties agreed that Sirius’s duty to pay rent for the damaged office space

was abated. This dispute is about whether Moody’s subsequent repair of the

damage caused by Hurricane Ike triggered Sirius’s obligation to resume paying

rent for the remainder of the lease’s term.

Sirius refused to pay, the lease terminated, and Moody withheld Sirius’s

deposits and other advance payments and sued for the balance it claimed was due.

Sirius countersued for the return of its deposits and other advance payments. After

a bench trial, the trial court rendered a take nothing judgment on Moody’s claims

and awarded Sirius $56,278.11 in actual damages, $135,000 in attorney’s fees and

costs, conditional attorney’s fees on appeal, and interest. On appeal, Moody

asserts the trial court’s findings of fact are legally erroneous and legally and

factually insufficient to support its conclusions of law.

We affirm.

Background

Sirius is a business consulting firm. It leased office space from Moody in an

eleven-story building at 3700 Buffalo Speedway in Houston. Sirius leased the

2 entire eleventh floor, most of the tenth floor, and a small space on the third floor.

The parties’ multi-year lease was to expire on July 31, 2009. Before Hurricane Ike

struck in September 2008, the parties were already negotiating a possible extension

of the lease. But Sirius was also exploring the possibility of relocating after the

lease expired.

Hurricane Ike struck on September 13, 2008. It damaged the roof of 3700

Buffalo Speedway, rendering Sirius’s office space uninhabitable. Sirius was able

to quickly lease temporary space in a building owned by a Moody affiliate. The

parties agreed that, under the terms of the lease, Sirius’s obligation to pay rent for

the damaged office space was abated to the extent the making of the repairs

interfered with Sirius’s business. However, they ultimately sued one another over

whether and when Moody’s repair of the space triggered Sirius’s obligation to

resume paying rent for the remainder of the lease’s term.

The lease expressly addressed the parties’ obligations in the event of a

partial destruction of the building. Under section 20.1, Moody was obligated to

repair a partial destruction “within 60 days from receipt of [insurance proceeds]”

or, if the repairs could not be made within 60 days, Moody, at its option, could

make the repairs “within a reasonable time.” The lease expressly provided that a

partial destruction of the building would not terminate the lease; however, it would

entitle Sirius to a “proportionate reduction of rent while such repairs are being

3 made, based upon the extent to which the making of such repairs shall interfere

with the business of [Sirius] on the Premises.”

Moody and Sirius presented sharply contrasting accounts of what happened

after Ike. Stephen Woods, the vice president of Moody’s commercial office

division, stated that the repairs to Sirius’s leased space were completed by April 1,

2009, and that, as of that date, Sirius was both free to move back into the space and

obligated to pay rent for the last four months of the lease’s term. According to

Moody, when Sirius refused to pay, Moody was justified in retaining Sirius’s

deposits and advance payments and in bringing suit for the balance of the unpaid

rent and late charges.

To support this contention, Moody’s construction expert relied on

certificates of substantial completion dated March 27 and April 1, within eight

weeks of the date construction began. He also testified that the eight weeks it took

to rebuild Sirius’s space was “reasonable and normal” and, considering the

circumstances in Houston at the time, “probably better than normal[,] honestly.”

While Moody acknowledged that tenants other than Sirius had their spaces

rebuilt earlier, Woods attributed the delay in repairing Sirius’s space to Sirius.

Woods testified that Sirius informed Moody by email that “[t]he optimal rebuild

for Sirius Solutions would include modifications from their former conditions” and

that rebuilding to the pre-Ike condition “would likely prompt a move next summer

4 when [Sirius’s] lease expires.” Woods testified that, based on these

communications, he understood that Sirius did not want its space rebuilt to the

exact configuration that existed before Ike. But, according to Woods, Sirius would

not communicate its wishes to Moody to allow Moody to complete the repairs to

Sirius’s satisfaction. Woods stated that Moody finally decided to move forward

with the repairs without Sirius’s input. Due to Sirius’s delay, Moody was not able

to meet its anticipated goal of substantial completion by February 1, 2009. Instead,

it was February 3, 2009 before the construction permits for Sirius’s space were

issued.

Sirius painted a different picture. Its CEO, Kristi Chickering, testified that

no one from Moody ever asked for Sirius’s input in the rebuilding process. She

said Woods told her that Moody would rebuild the space to its pre-Ike

configuration, adding that use of the same layout would speed up the process

because it would eliminate the need for building permits. Chickering’s testimony

in this regard was consistent with a November 21 email from Woods: “Today I

gave the contractor permission to start build back of the 10th and 11th floors to the

same specifications that they were prior to Hurricane Ike.”

Chickering also testified that Moody did not notify Sirius in advance that the

space was repaired and ready for move-in on April 1. Instead, according to

Chickering, Sirius’s first notice that the space was ready came in form of a late rent

5 payment notice dated April 14. Chickering and another Sirius employee visited

3700 Buffalo Speedway shortly after receiving that notice. Chickering testified

that, during that April visit, Sirius’s space was designated a hard-hat area and

construction workers were still active on the tenth and eleventh floors. She also

said wires and cables were hanging from the ceiling, and a dumpster was collecting

leaking water. Chickering stated the space was not ready for Sirius to return and

that Sirius could not use the space to conduct its business at that time.

Documentary evidence supports Chickering’s testimony: the Certificates of

Occupancy for various portions of Sirius’s space, without which a tenant is

prohibited from occupying a space, were not issued until May 15, May 20, and

June 23, 2009.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BMC Software Belgium, NV v. Marchand
83 S.W.3d 789 (Texas Supreme Court, 2002)
Humane Society of Dallas v. Dallas Morning News, L.P.
180 S.W.3d 921 (Court of Appeals of Texas, 2006)
Plas-Tex, Inc. v. U.S. Steel Corp.
772 S.W.2d 442 (Texas Supreme Court, 1989)
Dorsett v. Cross
106 S.W.3d 213 (Court of Appeals of Texas, 2003)
Catalina v. Blasdel
881 S.W.2d 295 (Texas Supreme Court, 1994)
Enron Oil & Gas Co. v. Joffrion
116 S.W.3d 215 (Court of Appeals of Texas, 2003)
City of Keller v. Wilson
168 S.W.3d 802 (Texas Supreme Court, 2005)
Nguyen v. Yovan
317 S.W.3d 261 (Court of Appeals of Texas, 2009)
Cain v. Bain
709 S.W.2d 175 (Texas Supreme Court, 1986)
Star-Telegram, Inc. v. Doe
915 S.W.2d 471 (Texas Supreme Court, 1996)
United States Fidelity & Guaranty Co. v. Allen
14 S.W.2d 724 (Tennessee Supreme Court, 1929)
Pitts & Collard, L.L.P. v. Schechter
369 S.W.3d 301 (Court of Appeals of Texas, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
Moody National Buffalo Speedway Mt, L.P. v. Sirus Solutions, LLLP, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moody-national-buffalo-speedway-mt-lp-v-sirus-solu-texapp-2013.