Montijo Reyes v. United States

349 F. Supp. 2d 234, 2004 U.S. Dist. LEXIS 25180, 2004 WL 2851799
CourtDistrict Court, D. Puerto Rico
DecidedDecember 13, 2004
DocketCIV. 01-2282(RLA)
StatusPublished
Cited by3 cases

This text of 349 F. Supp. 2d 234 (Montijo Reyes v. United States) is published on Counsel Stack Legal Research, covering District Court, D. Puerto Rico primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montijo Reyes v. United States, 349 F. Supp. 2d 234, 2004 U.S. Dist. LEXIS 25180, 2004 WL 2851799 (prd 2004).

Opinion

ORDER GRANTING DEFENDANT’S MOTION FOR SUMMARY JUDGMENT

ACOSTA, District Judge.

Plaintiffs filed the instant complaint under the Federal Tort Claims Act (“FTCA”) alleging that material deposited along the beach/shoreline across from their homes by the U.S. Army Corps of Engineers (“Corps”) purportedly resulted in sand and dust being blown onto their properties which in turn caused them damages.

Defendant filed a motion for summary judgment alleging that the claim asserted in the instant complaint is precluded by the discretionary function exception to the FTCA and is not viable under local law. Plaintiffs opposed claiming that the conduct at issue was carried out in violation of state law and thus, outside the ambit of the aforementioned exception and actionable under Puerto Rico negligence provisions.

The court having reviewed the arguments of the parties hereby finds as follows.

Factual Background

On January 20, 1999 the Corps proposed the emergency dredging of the Arecibo Harbor by public notice. The notice described the project as involving approximately 60,000 to 80,000 cubic yards of shoal material from the federally authorized navigation channel at the Arecibo Harbor. The material to be dredged was described as “predominantly sand with some silt and shell.” The notice further indicated that the dredged material would be temporarily stockpiled on the beach adjacent to the harbor and then hauled via dump truck to an upland disposal site on Port Authority Property inasmuch as this local agency had claimed an interest in retaining the dredged material. Near-shore placement of the dredged material was described as the next alternative had the Port Authority not shown an interest.

An Environmental Assessment was prepared for the project. The Port Authority decided it was no longer interested in retaining the dredged material. Thus, upland disposal was discarded and the option of redepositing the dredged materials into near-shore circulation was selected instead. According to the Environmental Assessment, “the material to be removed is considered suitable for downdrift beach and shore nourishment. Erosion, partly related to sea level rise, has been an ongoing problem along the Arecibo coast for many years... Therefore, it is appropriate and beneficial to dispose of the dredge material back into the natural littoral drift of the region.” ¶ 2.03. Further, the amount of the material to be dredged was calculated at 150,000 cubic yards instead.

Coordination of the Environmental Assessment was carried out with both federal and Commonwealth regulatory agencies, including the Puerto Rico Department of Natural and Environmental Resources, the Puerto Rico Ports Authority and the U.S. Fish and Wildlife Service (“USFWS”). The Puerto Rico Environmental Quality Board (“EQB”) issued a water quality certification and the Planning Board of the Office of the Governor of Puerto Rico issued a Certification of consistency with the Commonwealth’s Coastal Management Program. Declaration of Richard E. Bonner ¶ 4.

Work began on June 9, 2000 using the near-shore disposal site as described in the *237 Environmental Assessment. However, shortly thereafter the USFWS discovered that the dredged material was being deposited on a coral hard-ground community. Work was halted while the Corps consulted with the USFWS and the National Marine Fisheries and obtained an exception to the water Quality Certifícate from the EQB allowing disposal of sand on the beach itself. 1 Declaration of Richard E. Bonner ¶ 6.

The new disposal method was proposed in order to: protect essential fish habitat under the Magnuson-Stevens Fishery Conservation and Management Act and the coral hardbottoms as well as help combat the beach erosion problems along the Arecibo coast. Declaration of Richard E. Bonner ¶ 6.

A Finding of No Significant Impact was prepared on behalf of the Corps on June 30, 2000 changing the placement of material “along the shoreline/beach instead of the near-shore disposal site to minimize impacts to hardgrounds and potential sea turtle habitat.” ¶ e Further, the document limited “any additional beach placement to a berm width to 75' across the top from sea wall or beachhead (toe of fill limited to 3000' from sea wall or beachhead).” id.

As a result thereof almost the entire amount of dredged material was placed directly on the badly eroded beach in front of Paseo Victor Rojas across from plaintiffs’ properties.

Dredging work was completed approximately on July 1, 2000. The contractor continued to work along the shoreline for several days thereafter to give final grades to the beach.

As a result of the change, the beach height increased approximately fifteen feet along the entire beach area and was leveled with Paseo Victor Rojas to an estimated width of 1000 feet.

The limits on the beach placement imposed by the NMFS caused a sand pile that rose above the high tide line, but the renourished beach was never higher than the street.

When the project was complete, the sand was actually below street level. The street was protected from blowing sand by a stone concrete wall and silt fence installed by the contractor.

Protesting surfers repeatedly damaged or demolished the silt barrier and it had to be rebuilt several times.

Summary Judgment

Rule 56(c) Fed. R. Civ. P., which sets forth the standard for ruling on summary judgment motions, in pertinent part provides that they shall be granted “if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.” Sands v. Ridefilm Corp., 212 F.3d 657, 660-61 (1st Cir.2000); Barreto-Rivera v. Medina-Vargas, 168 F.3d 42, 45 (1st Cir.1999). The party seeking summary judgment must first demonstrate the absence of a genuine issue of material fact in the record. DeNovellis v. Shalala, 124 F.3d 298, 306 (1st Cir.1997). A genuine issue exists if there is sufficient evidence supporting the claimed factual disputes to require a trial. Morris v. Gov’t Dev. Bank of Puerto Rico, 27 F.3d *238 746, 748 (1st Cir.1994); LeBlanc v. Great Am. Ins. Co., 6 F.3d 836, 841 (1st Cir.1993), ce rt. denied, 511 U.S. 1018, 114 S.Ct. 1398, 128 L.Ed.2d 72 (1994). A fact is material if it might affect the outcome of a lawsuit under the governing law. Morrissey v. Boston Five Cents Sav. Bank, 54 F.3d 27, 31 (1st Cir.1995).

In cases where the non-movant party bears the ultimate burden of proof, he must present definite and competent evidence to rebut a motion for summary judgment,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Compagnie Maritime Marfret v. San Juan Bay Pilots Corp.
532 F. Supp. 2d 369 (D. Puerto Rico, 2008)
Montijo-Reyes v. United States
436 F.3d 19 (First Circuit, 2006)
Hall v. United States
233 F.R.D. 591 (D. Nevada, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
349 F. Supp. 2d 234, 2004 U.S. Dist. LEXIS 25180, 2004 WL 2851799, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montijo-reyes-v-united-states-prd-2004.