Montgomery County Community College District v. Donnell, Inc.

752 N.E.2d 342, 141 Ohio App. 3d 593, 2001 Ohio App. LEXIS 1488
CourtOhio Court of Appeals
DecidedMarch 30, 2001
DocketC.A. Nos. 18481, 18484, T.C. Case No. 99-3618.
StatusPublished
Cited by5 cases

This text of 752 N.E.2d 342 (Montgomery County Community College District v. Donnell, Inc.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montgomery County Community College District v. Donnell, Inc., 752 N.E.2d 342, 141 Ohio App. 3d 593, 2001 Ohio App. LEXIS 1488 (Ohio Ct. App. 2001).

Opinion

Grady, Judge.

This is an appeal from an order of the court of common pleas entered pursuant to R.C. 2711.02 staying proceedings in an action for declaratory judgment and breach of contract pending arbitration of the issues and disputes involved.

The declaratory judgment was sought by Montgomery County Community College District. It asked the court to construe its contract with Donnell, Inc. (“Donnell”), which had made physical improvements at Sinclair Community College. Donnell had asked for additional compensation as an “equitable adjustment” pursuant to the contract. Montgomery County Community College District (“Sinclair”) asked the court to determine its rights and duties in that respect. It also pleaded breach-of-contract and bad-faith claims against Donnell.

Donnell invoked an arbitration provision in its contract with Sinclair, asking the court to enforce the arbitration agreement pursuant to R.C. 2711.01 and to stay the proceedings pursuant to R.C. 2711.02. Sinclair opposed Donnell’s request, arguing that the arbitration agreement was void.

*596 Sinclair’s attack on its arbitration agreement with Donnell relied on a condition subsequent attached to that agreement. The condition provides that if either party asks any third party to participate in a requested arbitration and the third party does not agree to be included, the requesting party may in its discretion elect to void the arbitration clause and proceed to litigation. In this instance, according to Sinclair, it requested three such parties who were also involved in the work that Donnell had performed to join in the arbitration, and none had agreed to do so. Therefore, according to Sinclair, the arbitration agreement was not enforceable by Donnell because Sinclair had exercised its power to void the arbitration clause and proceed to litigate.

The three third parties that Sinclair had requested to join in the arbitration are Lorenz & Williams Associates, Inc., the architects on the project; Turner Construction Co., the project manager; and Stan and Associates, Inc., a subcontractor of Donnell. Each was a “third party” to the bilateral agreement between Sinclair and Donnell. Each is also subject to its own contract with Sinclair containing the same arbitration and voiding clause.

The trial court took no evidence on either Donnell’s motion to enforce the arbitration agreement and stay the proceedings or Sinclair’s opposition to Donnell’s requests. Nevertheless, the court found that Sinclair had breached its duty of good faith when it sought to join the other parties in the arbitration, having done so solely to avoid arbitration. On that basis, the court granted Donnell’s motions to compel arbitration and stay the proceedings.

Sinclair filed a timely notice of appeal from the stay order, which is a final, appealable order per R.C. 2711.02. Lorenz & Williams Associates, Inc. (“Lorenz & Williams”), also a party to this action, filed a notice of appeal from the order compelling arbitration.

SINCLAIR’S ASSIGNMENTS OF ERROR

FIRST ASSIGNMENT OF ERROR

“The trial court erred by failing to correctly interpret and apply the arbitration clause in the dispute between Sinclair and Donnell”

SECOND ASSIGNMENT OF ERROR

“The trial court committed reversible error by imposing an ‘inherent good faith obligation’ upon Sinclair regarding Sinclair’s discretionary designation of third parties ‘deemed appropriate to aid in the resolution of the dispute.’ ”

R.C. 2711.01 creates a right to enforce an arbitration clause in a contract when claims for relief pleaded in an action present issues for the court’s determination *597 that are referable to arbitration pursuant to the terms of the agreement to arbitrate. If the court finds that they are, the court must stay the proceedings before it upon the application of one of the parties to the action until arbitration “has been had in accordance with the agreement.” R.C. 2711.02. However, the applicant cannot be “in default in proceeding with arbitration.” Id.

The relief that 2711.01 and 2711.02 create requires the court to engage in a summary form of proceeding to determine two issues. The first is whether an enforceable arbitration agreement exists. Because that presents a question of fact, an ambiguity in the agreement or a dispute in that regard must be resolved by an evidentiary hearing. See ABM Farms, Inc. v. Woods (1998), 81 Ohio St.3d 498, 692 N.E.2d 574. If the court finds an enforceable agreement, it must then determine whether the issues involved in the claims for relief pleaded in the action are referable to arbitration. In most instances, that question may be determined from the face of the pleadings. When that is possible, no evidence is required for the determination.

In ABM Farms, Inc., supra, the party resisting arbitration claimed that she had been fraudulently induced to enter into the contract containing the arbitration clause. That particular claim related “ ‘not to the nature or purpose of the [contract], but to the facts inducing its execution.’ ” Id. at 502, 692 N.E.2d at 578, quoting Haller v. Borror Corp (1990), 50 Ohio St.3d 10, 14, 552 N.E.2d 207, 210-211. The Supreme Court held that the party resisting arbitration “must demonstrate that the arbitration provision itself in the contract at issue, and not merely the contract in general, was fraudulently induced.” Id. at syllabus. Because the facts which the trial court had adduced failed to demonstrate fraud with respect to the arbitration agreement itself, an arbitration and stay were proper. Id.

In ABM Farms, Inc., supra, the court observed that “R.C. 2711.01 more generally acknowledges that an arbitration clause is, in effect, a contract within a contract, subject to revocation on its own merits.” Id. at 502, 692 N.E.2d at 577. The issue presented here is whether the arbitration clause in the contract between Sinclair and Donnell was revocable, not for fraud but because Sinclair had exercised its rights under the condition subsequent concerning third parties and elected to litigate, instead of arbitrate, Donnell’s claim for additional compensation.

The court rejected Sinclair’s claim that the arbitration clause was revocable, not because Sinclair had failed to satisfy the conditions for revocation but because Sinclair had breached its duty of good faith in exercising its option to litigate. The court stated:

“The Court determines that the facts of this matter could be construed to demonstrate that Sinclair, in breach of their inherent, good faith obligation, has *598 asserted joinder of parties, whom they argue are unnecessary, solely to escape arbitration. Signs of this endeavor are: 1) Sinclair makes no claims

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
752 N.E.2d 342, 141 Ohio App. 3d 593, 2001 Ohio App. LEXIS 1488, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montgomery-county-community-college-district-v-donnell-inc-ohioctapp-2001.