Montgomery Bros. & Co. v. G. L. Cole, Inc.

138 Misc. 53, 244 N.Y.S. 702, 1930 N.Y. Misc. LEXIS 1551
CourtNew York Supreme Court
DecidedOctober 8, 1930
StatusPublished

This text of 138 Misc. 53 (Montgomery Bros. & Co. v. G. L. Cole, Inc.) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montgomery Bros. & Co. v. G. L. Cole, Inc., 138 Misc. 53, 244 N.Y.S. 702, 1930 N.Y. Misc. LEXIS 1551 (N.Y. Super. Ct. 1930).

Opinion

Charles B. Wheeler, Official Referee. This action is brought to foreclose a mechanic’s lien on funds in the hands of the Union School District No. 1 of the town of Wayland, growing out of the erection of an addition to the Wayland high school building in the village of Wayland, N. Y.

On August 3, 1928, the defendant G. L. Cole, Inc., entered into a contract with the board of trustees of said district to erect said building according to plans and specifications for the sum of $93,539. The G. L. Cole, Inc., hereafter termed the contractor, proceeded with the erection of the building. The contract provided for the completion of the building on or before January 15, 1929. This the contractor failed to do. The contract further provided the contractor should immediately discharge liens filed against the fund. Liens to the extent of nearly $35,000 were filed and not discharged and in April, 1929, the school board with the apparent consent of the contractor terminated the contract and took over the completion of the work, charging the contractor with the cost of such completion.

Certain funds remain in the hands of the school board and this action isibrought to determine the amount and validity of such liens and their priority of payment.

[55]*55The first question presented for the determination of the referee is the amount of the fund available for the payment of hens asserted by various claimants.

Counsel for Union School District No. 1 of the town of Way-land concedes that there is due and owing and in the hands and under the control of the school board the sum of $7,084.45.

The following is a summary statement showing the manner in which said amount is arrived at by said counsel:

It will be noted that this statement of $7,084.45 includes the sum of $573.90 allowed by the board for extras furnished by the contractor, to wit, for the following items:

It will be also noted that in the above statement the counsel for the school board in his computation showing the amount admittedly due. on the contract has deducted from the contract price of $93,539 [56]*56the sum of $3,000 as a credit on said contract by virtue of the letter of the G. L. Cole, Inc., to the board of education dated July 31, 1928, attached to and forming a part of the contract.

The referee is unable to concur in this claim for deduction by the school board. The letter refers to certain contemplated changes in the specifications and makes deductions by reason of these changes amounting to $3,000. After this letter was written and on August 3, 1928, the contract itself was made to do the work for $93,538. The contract itself refers to the letter and statement attached to the contract and states the board has “ the privilege of restoring any of the omitted items listed in the attached statement at the same price as allowed in the statement for the omissions of the same provided the contractor is notified of such restoration before the work has progressed to a point where the restoration would create a hardship to the contractor.” It is quite plain, therefore, that the $93,539 specified in the contract was the price agreed on for doing the work with the omissions stated, and that if it was subsequently determined to include the items omitted, then the contract price was to be increased just so much.

Therefore, the referee finds that there is in the hands of the board subject to the payment of Hens and assignments the total sum of $10,084.45 plus certain claims for extras not conceded by the school board. This sum of $10,084.45 does not include a payment made by the board to Rogers & Tenbrook of $8,220.88 which is challenged by lienors as unauthorized.

The referee will refer to this payment later in his opinion. If this sum of $8,220.88 is added to the sum of $10,084.45 we then have a total for distribution of $18,305.33.

In addition to this we are of the opinion that certain items for extras should be added which the counsel for the school board is not ready to concede. The referee is of the opinion that the fund should be charged with the following extras not so allowed or conceded, to wit:

Other claims for extras are disallowed.

One of the important questions in this case is the proper disposition of the item of $8,220.88 above referred to as the claim of Rogers & Tenbrook. The history of this claim is that Rogers & [57]*57Tenbrook is a firm doing business at Wayland. This firm furnished the contractor material for the doing of his work which on February 1, 1929, amounted to $8,220.88. On January tenth Rogers & Tenbrook filed with the clerk of the school board and with its treasurer an assignment of $8,000 in amount of moneys payable to the contractor by reason of his contract for the erection of the school building. This assignment is without date, but the referee is of the opinion that the evidence justifies the finding that the assignment was in fact executed within ten days of its fifing. However, on February 1, 1929, Rogers & Tenbrook filed a notice of fien with the clerk and treasurer for $8,220.88. This was for the full amount owing the firm. However, this notice of lien was not signed at all, but attached to and forming a part of the notice was a verification of the notice of lien signed and sworn to by a member of the firm. Later and on March 18, 1929, Rogers & Tenbrook filed a second notice of lien for the same amount. This second lien was doubtless filed to cure defects, if any existed, in the notice of lien filed February 1, 1929.

Other lienors contend that both the assignment for $8,000 and notices of liens are invalid as against them for reasons that will be later discussed in this opinion. If their contentions are right, the effect will be to give such objecting lienors prior claims to the fund over the claim of Rogers & Tenbrook.

However, it appears that the school board actually paid Rogers & Tenbrook $8,220.88, the amount of their claim, under an agreement that if the court should find the payment unauthorized the firm would refund to the board the amount so paid.

This brings the referee to the discussion of the question as to whether the assignment filed January tenth is invalid.

It is urged as one ground of invalidity that it was not filed with the proper party, in that it was filed with the clerk of the board instead of with the president of the board, and did not, therefore, comply with the requirements of section 16 of the Lien Law (as amd. by Laws of 1929, chap. 515; since amd. by Laws of 1930, chap. 859).

Lienors contend that this order or assignment was invalid and inoperative as to them because it was not served on the president or chairman of the school board as required by section 16 of the Lien Law. This section provides that no such order or assignment shall be valid unless such assignment or order, or a copy thereof, be filed within ten days after the date of such assignment of contract, or such assignment of money, or such order, with the head of the department or bureau having charge of such construction, and with the financial officer of the municipal corporation or other officer or person charged with the custody and disbursement of the corporate [58]*58funds applicable to the contract for such public improvement, and such assignment or order shall have effect and be enforceable from the time of such filing, and no such assignment or order shall have any validity until the same shall have been so filed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bell v. . Mayor, Etc., of N.Y.
11 N.E. 495 (New York Court of Appeals, 1887)
Albany Builders' Supply Co. v. Eastern Bridge & Structural Co.
139 N.E. 565 (New York Court of Appeals, 1923)
Reeves v. Seitz
47 A.D. 267 (Appellate Division of the Supreme Court of New York, 1900)
Clapper v. Strong
90 A.D. 536 (Appellate Division of the Supreme Court of New York, 1904)
Kingston v. M. S. Construction Corp.
222 A.D. 837 (Appellate Division of the Supreme Court of New York, 1928)
Glens Falls Portland Cement Co. v. Van Wirt Construction Co.
225 A.D. 159 (Appellate Division of the Supreme Court of New York, 1929)
J. J. Newman Lumber Co. v. Wemple
56 Misc. 168 (New York Supreme Court, 1907)
Italian Mosaic & Marble Co. v. City of Niagara Falls
131 Misc. 281 (New York Supreme Court, 1928)
Moore v. McLaughlin
21 N.Y.S. 55 (New York Supreme Court, 1892)

Cite This Page — Counsel Stack

Bluebook (online)
138 Misc. 53, 244 N.Y.S. 702, 1930 N.Y. Misc. LEXIS 1551, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montgomery-bros-co-v-g-l-cole-inc-nysupct-1930.