Monterey Consultants, Inc. v. United States

120 Fed. Cl. 567, 2015 U.S. Claims LEXIS 331, 2015 WL 1395921
United States Court of Federal Claims·Decided March 26, 2015·No. 14-1164C·Published·Cited by 2 cases

Opinion

OPINION

ERIC G. BRUGGINK, Judge

This is a protest of the Department of Veteran Affair’s recision of a task order to Monterey Consultants, Inc. for services in support of the agency’s program to verify the status of small and veteran-owned businesses. The task order to Monterey was cancelled as a corrective action because the agency concluded that Monterey had a potential or actual organizational conflict of interest. Plaintiff alleges that neither is true. The parties have filed cross-motions for judgment on the administrative record. The matter is fully briefed, and oral argument was held on March 4, 2015. Because the agency was not irrational in its belief that Monterey’s access to solicitation documents created at least the appearance of a conflict of interest, we grant defendant’s and interve-nor’s motions for judgment and deny plaintiffs.

BACKGROUND

Plaintiff, Monterey Consultants, Inc. (“Monterey”), held a blanket purchase agreement (“BPA”) with the Department of Veteran Affairs (“VA”) under which it provided support services to the VA’s Center for Verification and Evaluation (“CVE”) and Office of Small and Disadvantaged Business Utilization (“OSDBU”). 2 This BPA, called the Integrated Product Team (“IPT”) Facilitation and Acquisition Services Blanket Purchase Agreement was the agency’s long-standing contract vehicle for procuring a wide variety of services in support of all of OSDBU’s various missions (e.g., research, verification, analysis, outreach, and training). Monterey was awarded the BPA in February 2013. It did work under a variety of call orders, including processing and verification services for the CVE and administrative support of the OSDBU’s acquisition efforts.

In an effort to reduce the scope of the work procured with a single contracting vehicle, the IPT BPA, the agency let the BPA expire on its terms and sought to replace its acquisition of some of those services through two separate contracts placed as task orders under the GSA’s Federal Supply Schedule (“FSS”). 3 The solicitation at issue in this protest was identified by the agency as a follow-on for two specific BPA call orders, 18 and 19. Administrative Record (“AR”) 91 (Acquisition Plan). Call orders 18 and 19 were for support services related to the CVE’s verification of small business status. Monterey had performed under both of those orders pursuant to the BPA. Monterey also provided support for other OSDBU work, including acquisition support under call order 17.

The VA issued Request for Quote No. VA119A-14-Q-0324 (“RFQ” or “solicitation”) on June 13, 2014, as a 100 percent set-aside *569 for service-disabled veteran owned small businesses holding one or both of two GSA FSS contracts for support services. 4 The RFQ sought “administrative, paralegal, project management, and professional support” for the CVE. AR 91. Specifically, these services were to be in support of the CVE’s verification processing and management of that processing. 5 See AR 916.

The solicitation called for a best value award to the offeror “determined to be the most beneficial to the Government.” AR 158. Offerors were evaluated based on four factors: 1) Technical Approach, 2) Management Approach, 3) Past Performance, and 4) Price. The non-price factors, combined, were more important than price, which meant that the agency reserved the right to award to a higher-priced offeror who offered superior non-price elements. AR 158.

The RFQ addressed Organizational Conflicts of Interest (“OCIs”) in section 18:

It is recognized by the parties that the efforts to be performed by the contractor under this contract are of such a nature that they may create a potential Organizational Conflict of Interest (OCI) as contemplated by Subpart 9.5 of the FAR. It is the intention of the parties that the contractor shall not engage in any contractual activities which may impair its ability to render unbiased advice and recommendations, or in which it may gain an unfair competitive advantage as a result of the knowledge, information and experience gained during the performance of this contract. It does not include the normal flow of benefits from incumbency. Contractors performing on other contracts in support of Verification shall be presumed to have an OCI with respect to this contract and are ineligible to quote on this requirement, due to the integrated nature of work perform[ed] under this solicitation and existing contracts.

AR 953 (emphasis supplied).

A further condition for bidding on the RFQ was that offerors were required to “agree not to participate ... in any acquisition wherein: (1) The contractor has participated in the analysis and recommendation leading to the acquisition decision to acquire such services; or (2) the Contractor may have an unfair competitive advantage resulting from information gained during the performance of this contract.” AR 953. The solicitation went on to instruct offerors who believed that their participation would cause an OCI to “include in [their] proposals] an appropriate discussion and mitigation plan.” AR 954. The VA would review such materials, make a determination of whether there was an OCI, and, if so, determine whether the mitigation plan was sufficient to allow the offeror to participate. Id.

Three offerors submitted proposals, including plaintiff and intervenor, Loch Harbour Group, Inc. (“Loch Harbour”). Monterey was initially awarded the contract on September 8, 2014, based on its higher technical scores, which, in the agency’s eyes, made it a better value despite its higher price. The base contract was for a period of 16 weeks from September 10, 2014-December 24,2014, with an agency option to extend up to four years thereafter. On September 29, 2014, Loch Harbour filed a protest in this court, the principal ground of which was that Mon-terey was ineligible for award because it had an OCI stemming from its prior work under the BPA. Upon reviewing the complaint, the Contracting Officer (“CO”), James Boughner, began an investigation into the possible OCI based on Monterey’s prior work for OSDBU and CVE.

The CO interviewed several agency officials in CVE and OSDBU, including Eugene Skinner, the Deputy Director of Acquisitions at OSDBU, John Perkins, Program Manager for Evaluation at CVE, and Jeffrey Gault, the Acting Director of CVE. See AR 1560-66. The CO made email inquiries and communicated with other contracting personnel in *570 volved, asking questions regarding both Monterey’s prior work and its proposal. See AR 1560-66, 1580-81. In addition, Mr. Boughner corresponded directly with Monte-rey by email on several occasions.

Free access — add to your briefcase to read the full text and ask questions with AI

Monterey Consultants, Inc. v. United States, 120 Fed. Cl. 567, 2015 U.S. Claims LEXIS 331, 2015 WL 1395921 (uscfc 2015).

120 Fed. Cl. 567 (Monterey Consultants, Inc. v. United States) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related