Monteleone v. Boh Bros. Construction Co.

200 So. 2d 402, 1967 La. App. LEXIS 5256
CourtLouisiana Court of Appeal
DecidedJune 5, 1967
DocketNo. 2513
StatusPublished
Cited by3 cases

This text of 200 So. 2d 402 (Monteleone v. Boh Bros. Construction Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monteleone v. Boh Bros. Construction Co., 200 So. 2d 402, 1967 La. App. LEXIS 5256 (La. Ct. App. 1967).

Opinion

CHASEZ, Judge.

The petition of Dorothy Hill Monteleone, dated March 21, 1962, prayed for an award in damages which resulted to her residence at 412 Lake Avenue in New Orleans from the alleged negligent construction activity which took place across Lake Avenue from her home during the months of June, July, or at times shortly thereafter, in 1961. Named defendants were Boh Brothers Con[404]*404struction Company, Inc., Williams-McWil-liams Industries, Inc. and its insurer, Employers Group of Insurance Companies; Pittman Construction Company, Inc. and its insurer Bituminous Casualty Corporation and the Board of Levee Commissioners of the Orleans Levee District. Another Company and its insurer were named but were subsequently dismissed on joint motion and are not before this court.

On October 22, 1963 a supplemental petition was filed wherein it was alleged that Pittman Construction Company, Inc. caused their portion of the plaintiff’s damages between September of 1961 and August of 1962; that the damages caused by Boh Brothers Construction Co. Inc. occurred between June, 1961 and March, 1962, and Williams-McWilliams Industries Inc. contributed to her damages between March, 1961 and June 1961, and between August, 1961 and February, 1962. This petition also charged the Board of Levee Commissioners of the Orleans Levee District with responsibility regardless of any question of negligence.

A second supplemental and amended petition dated November 27, 1964 stated that “the acts of negligence hereinbefore alleged against the said Boh Bros Construction Company, Inc. took place during two periods of time, that is, between April 30, 1962 and June 28, 1962, and also between October, 1960 and September, 1961” and further alleged on information and belief that the negligence of this defendant took place over a continuous period between October, 1960 through July, 1962.

Boh Brothers Construction Company, Inc. excepted on the grounds of prescription. This exception was apparently never disposed of.

Issue was joined in this case and the Civil District Court transferred the case for hearing by the Commissioner for the Civil District Court for the Parish of Orleans pursuant to R.S. 13:1171. The Commissioner’s findings and opinion were favorable to the position of the defendants and he recommended judgment dismissing them from the plaintiff’s demands. Exceptions were taken to the Commissioner’s report by the plaintiff and argued before the Judge below.

The Court rendered judgment in favor of the defendants and against the plaintiff, dismissing the plaintiff’s suit, and gave the following written reasons for judgment:

“The Court has studied the record and find that it supports the report and conclusions of the Commissioner in every material respect.
“It is the Court’s opinion from the evidence presented that the plaintiff has. failed to prove by a preponderance of evidence that the alleged damage she sustained was the result of either the construction of the Orleans Marina by the Board of Levee Commissioners, Orleans. Levee District, or any negligence on the part of the several defendants.
“Further, the Court is of the opinion that if any of the alleged damage sustained by Mrs. Monteleone occurred during the period of the construction of the Marina that said damage was not a consequence of the construction of the Marina or the activities on the part of any of the defendants, but rather was the result of natural soil subsidence, traffic passing in front of her residence, the normal attrition of time, or other factors not shown to have been in any way related to the construction of the Orleans Marina or the activities of the several defendant contractors.”

As the reasons indicate, the construction activity complained of in this case was the erection of the Orleans Marina on Lake Pontchartrain.

There does not appear to be strict proof in the record of the Board of Levee Commissioners of the Orleans Levee District’s ownership of the property on which the Marina was constructed, but it seems to> [405]*405be a foregone conclusion among the parties. If this be the case, the alleged liability of the Board of Levee Commissioners stands on a different footing than that of the contractor-defendants and their insurors. The Levee Board as the owner of the property on which the Marina was constructed commissioned the work to be done. Unlike the burden of proof that must be borne by the plaintiff to establish the liability of the construction companies, negligence need not be proved in order to hold the Levee Board in damages. This is the effect of Article 667 of the Louisiana Civil Code as seen by our Courts. Selle v. Kleamenakis, 142 So.2d SO (La.App.1962).

In order to recover at all, though, the plaintiff bore the burden of proving that the damages sustained by her were at least caused by the construction activity alleged in her petition as amended. The Commissioner and the Court below concluded that the causality was not shown by a preponderance of the evidence, and our attention at the outset is directed to the correctness of this finding, taking into consideration that this is a fact finding which is not to be disturbed in the absence of manifest error.

The evidence established that Williams-McWilliams Industries, Inc. contracted with the levee board on February 15, 1961 for putting in sheet pilings which job was completed by May 12, 1961. On August 17, 1961 a second contract was entered into by Williams-McWilliams Industries, Inc. for anchoring the sheet piling with pole piles driven into the ground, capped with concrete, and cabled to the bulkhead. This contract was completed December 12, 1961. All of this pile-driving was done parallel to Lake Avenue or East-West.

Pittman Construction Company, Inc. contracted on September 22, 1961 and their work was accepted on June 20, 1962. Their work' was to construct the Harbor Master Building at the East end of the Marina and the wharves and piers and included the driving of a.few additional piles on the land side of the bulkhead.

Boh Brothers Construction Company Inc.’s contract was from April 30, 1962 through June 28, 1962 and their job consisted of paving the parking area and the street on Lake Avenue and the sewerage and drainage installation. June 28, 1962 marked the cessation of all construction. The procedure in these contracts was for work to actually begin within a short time after the contract was entered into.

The jobsite itself abutted Lake Avenue on one side, and Mrs. Monteleone’s property abutted the Avenue on the opposite side, parallel to a portion of the jobsite frontage.

The testimony indicates that no tests to measure the effect of vibration were ever conducted by anyone connected with the project. Mr. Willoz, the chief engineer for the Board of Levee Commissioners of the Orleans Levee District, testified that the jobsite was very muddy and rough because it was a dirt terrain. Mr. McNamara, the assistant chief engineer of the Board of Levee Commissioners also testified, and he stated that the sheet piles driven by Williams-McWilliams were forty feet in length and the piles driven under the second Williams-McWilliams contract on the land side of the bulkhead were from sixty to seventy feet long. These were driven in clusters generally running East to West across the jobsite. The clustered piles were in groups of four, two of which were angled toward Lake Avenue under the ground. Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williamson v. Gulf Coast Line Contracting Co., Inc.
301 So. 2d 657 (Louisiana Court of Appeal, 1974)
Monteleone v. Boh Bros. Construction
217 So. 2d 754 (Louisiana Court of Appeal, 1969)
Monteleone v. BOH Bros. Construction
202 So. 2d 661 (Supreme Court of Louisiana, 1967)

Cite This Page — Counsel Stack

Bluebook (online)
200 So. 2d 402, 1967 La. App. LEXIS 5256, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monteleone-v-boh-bros-construction-co-lactapp-1967.