Monte v. J. R. Christ Construction Co.

42 F.R.D. 17, 1967 U.S. Dist. LEXIS 11761
CourtDistrict Court, E.D. Pennsylvania
DecidedMarch 30, 1967
DocketCiv. A. No. 34430
StatusPublished

This text of 42 F.R.D. 17 (Monte v. J. R. Christ Construction Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monte v. J. R. Christ Construction Co., 42 F.R.D. 17, 1967 U.S. Dist. LEXIS 11761 (E.D. Pa. 1967).

Opinion

OPINION AND ORDER

WOOD, District Judge.

Plaintiffs are co-executors of the estate of John Monte and Robert Monte who traded as John Monte Co. (Monte). Monte was a construction company which secured a contract from the Southern Delaware County Authority for installation of a sewer system. It subcontracted certain aspects of the job to J. R. Christ Construction Co., Inc. (Christ). A performance bond was allegedly supplied by Aetna Casualty and Surety Co. (Aetna) which has moved for summary judgment.1

As to the basic dispute, plaintiffs assert that Christ walked off the job without cause and thereby breached its contract only ten days after commencing work. Monte then allegedly searched for the bond and was unable to locate it. The record shows that Aetna was in possession of the bond through some means unknown to Monte.

The policy contained a contractual limitation clause on the right to sue:

“PROVIDED, HOWEVER, that no action, suit or proceeding shall be had or maintained against the Surety on this instrument unless the same be brought or instituted and process served upon the Surety within two years after completion of the work mentioned in said contract, whether such work be completed by the Principal, Surety or Owner; but if there is any maintenance period provided in the contract for which said Surety is liable, an action for maintenance may be brought within two years from the expiration of the maintenance period, but not afterwards.”

Suit was not filed until October 31, 1963, more than three years after October, 1960, the alleged completion date. Aetna’s motion of course is based on the fact that the limitation period expired before suit was filed and therefore the action is barred. Generally, provision for some reasonable time within which action must be brought is valid and enforceable and the beneficiary is subject to all the limitations of the policy. Selden v. Metropolitan Life Ins. Co., 354 Pa. 500, 502, 47 A.2d 687 (1946) (two-year period). Since plaintiff has not controverted the reasonableness of the two-year period, we will accept it as reasonable, for the purposes of this motion.

Monte’s first response to the motion is that there is an issue of fact as to the date of completion of the work. It argues that the completion date involves a mixed question of fact and law because it was an issue in pending litigation with the Authority and could be determined to be as late as 1962 when the Authority was repairing allegedly defective work of Monte, including work covered by the Christ subcontract.

Monte’s position in this regard is not well taken. The deposition of Harold B. Forsythe, general superintendent for Monte and in direct charge of Monte’s performance of its contract with the Authority shows quite clearly that Monte’s position is and always has been that the completion date was October, 1960. Forsythe testified as follows: “I might point out at this time that the project had been finished and accepted in 1960 by the owner * * * ” (Forsythe Dep., page 117) and later on page 119: “Then we would have to come back and take care of that complaint and so forth, until finally there was nothing else they could find wrong and they had to accept the project in October of 1960. But it didn’t take near that long to do the project * * * ” These statements were reinforced by Monte’s counsel who stated as follows: “[A]s to the completion date [19]*19* * * it is our contention that it was finished in October of 1960.” (p. 117).

Monte has produced no evidence to substantiate its claim of another completion date. Whatever “completion of the work” might mean in the bond, in this case on this record, it is clear the work was completed. What were the contentions in another litigation is neither pertinent nor even persuasive herein. We know almost nothing about the issues. It is interesting to note however that in one suit, Monte claims completion date as October, 1960, and on this motion argues for a later date.

Monte attempts to excuse its inaction by claiming that the bond was stolen from Monte’s office by Christ with the full knowledge and complicity of Aetna. Since Monte was unaware of the limitation period, Aetna thereby prevented it from fulfilling a condition, suit within two years, and is thereby barred from asserting it as a defense. Aetna denies theft, alleging that the policy was never delivered to Monte, and that Monte was in no way misled or deceived as to Aetna’s position nor in any way lulled into any sense of false security.

Monte on this motion has the burden of producing some credible evidence to support its reason for delay. If some evidence is produced, summary judgment for defendant is precluded. The rule is not intended to be a vehicle to resolve disputed questions of fact. However, mere suspicion or conjecture is not sufficient, where discovery should have been made. Robin Construction Co. v. United States, 345 F.2d 610, 614 (3rd Cir. 1965).

The relevant facts which we must accept as true as recited by Harold Forsythe, an official of Monte, are as follows : The bond was signed and delivered to Forsythe in his office in July, 1959 in the presence of five employees by Christ. Forsythe noted that the bond form was peculiar and then placed it in the filing cabinet in his office. Everyone observed this because of the comment he had made. On August 14, 1959, the day Christ began to remove his equipment from the job site, Forsythe looked for the bond and discovered its absence. He looked in the Christ folder and found the contract and certain insurance certificates, but no bond. The cabinet was kept locked and only he and his employees had keys. He knew of no one who had given the policy to Christ.

A letter was written by Monte to Aetna advising them that Monte knew that the bond was in their possession and requesting it forthwith. Aetna’s reply was that the bond had never been delivered and that they could show that the bond was never in Monte’s possession.

The evidence as to theft is obviously not very persuasive and in our opinion will not eventually prevail. However, on this motion, all reasonable inferences of fact must be drawn in favor of respondent plaintiffs. For several reasons, we are reluctant not to draw an inference of some wrongdoing on Aetna’s part. First, the record in its present state is incomplete and leaves too many items to conjecture. We do not know Christ’s position nor that of the five so-called witnesses nor that of the employees who had possession of the file key. The accepted facts leave room for doubt. Secondly, it appears somewhat unlikely that if the bond were delivered and properly executed as Forsythe says, that Monte would return it to Christ or allow Christ to proceed with construction without a performance bond.

Assuming that an issue of fact is established, it must be material in order to preclude summary judgment. Excuses for delay in suing within the contractual period are many and have resulted in varying results.2 Generally, in [20]*20Pennsylvania ignorance of the contractual period or of other facts has not been held to be a legally effective excuse.3 However, a court will look somewhat harshly at the technical defense and in certain eases demand more than dealing at arms’ length.4

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fratto v. Northern Insurance Company of New York
242 F. Supp. 262 (W.D. Pennsylvania, 1965)
Monte v. Southern Delaware County Authority
212 F. Supp. 604 (E.D. Pennsylvania, 1963)
Selden v. Metropolitan Life Insurance
47 A.2d 687 (Supreme Court of Pennsylvania, 1946)
Fedas v. Insurance Co. of Pennsylvania
151 A. 285 (Supreme Court of Pennsylvania, 1930)
Faulks v. Unity L. A. Ins. Assn.
30 A.2d 121 (Supreme Court of Pennsylvania, 1942)
Faulks v. Unity Life & Accident Insurance Ass'n of Syracuse
346 Pa. 346 (Supreme Court of Pennsylvania, 1943)

Cite This Page — Counsel Stack

Bluebook (online)
42 F.R.D. 17, 1967 U.S. Dist. LEXIS 11761, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monte-v-j-r-christ-construction-co-paed-1967.