Montano v. City of Watervliet

47 A.D.3d 1106, 850 N.Y.S.2d 273
CourtAppellate Division of the Supreme Court of the State of New York
DecidedJanuary 17, 2008
StatusPublished
Cited by16 cases

This text of 47 A.D.3d 1106 (Montano v. City of Watervliet) is published on Counsel Stack Legal Research, covering Appellate Division of the Supreme Court of the State of New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montano v. City of Watervliet, 47 A.D.3d 1106, 850 N.Y.S.2d 273 (N.Y. Ct. App. 2008).

Opinion

Spain, J.

Appeal from an order of the Supreme Court (McCarthy, J.), entered October 16, 2006 in Albany County, which granted a motion by defendants City of Watervliet, City of Watervliet Board of Appeals and Mark R. Gilchrist for summary judgment dismissing the complaint against them.

Plaintiff is the owner of a large commercial building located in the City of Watervliet, Albany County, in a manufacturing zone. In early 2000, defendant Starfire Systems, Inc., a business engaged in the manufacturing of ceramic and ceramic compos[1108]*1108ites, and its president, defendant Walter Sherwood, entered into negotiations to lease the building from plaintiff, who was then under contract to purchase it. Sherwood hired defendant William Bradley, president of defendant Brunswick Research, Inc., to advise him on the feasability of a relocation to this site and with respect to the process of obtaining any permits. In June 2000, apparently due to the fact that the subject property was located within 200 feet of a residential district, plaintiff and Starfire jointly applied to defendant City of Watervliet Board of Appeals (hereinafter the Board) for a use variance to use the building for polymer synthesis and manufacturing of ceramics and its composites, processes which reportedly produce hazardous chemicals requiring storage and removal. After a hearing, the Board granted the variance, subject to specified conditions relating to compliance with fire, building code and city ordinances requirements and related inspections.

Thereafter, plaintiff purchased the property, made extensive improvements, and entered into a five-year lease with Starfire, contingent upon Starfire obtaining necessary governmental approval and giving both parties the right to terminate the lease if such approval were not timely obtained. As later amended, the rent commencement date under the lease was January 2001. Starfire paid a security deposit and a few monthly lease payments, but never occupied the building and instead continued to pursue alternative sites with Bradley’s assistance, ultimately determining that this site was not feasible.

In April 2001, Bradley and Starfire’s staff arranged a meeting with city officials, including defendant Mark R. Gilchrist, the City’s zoning officer and fire inspector, and an emergency response team leader and an engineer. Bradley, who had from the outset viewed the subject property as unsuitable for Starfire’s business, presented more detailed information regarding the scope of Starfire’s intended use of chemicals and the dangers of hypothetical chemical spills and fires, and other “worst case scenarios” were considered with regard to the nearby residential neighborhood. Thereafter, Gilchrist sent Starfire a letter dated May 10, 2001 indicating that the preconstruction planning meeting with Bradley and others had brought to the City’s attention “the exact nature of the proposed occupancy [and] [d]ue to health, safety and welfare issues for the residents living in the area around [the subject building], the Building Department will not issue a permit for renovations. Even with all the proposed safeguards and planning, an accident at this site could very well be disastrous to the resident population.” Notably, there was no pending permit or certificate of occupancy applica[1109]*1109tion; the record does not reflect that any form of building permit was sought or that any administrative appeal from Gilchrist’s decision was pursued. Starfire thereafter ceased paying rent under the lease and relocated its business to another county, and plaintiff, after several unsuccessful attempts, ultimately obtained a variance allowing it to lease the premises to another entity.

Plaintiff commenced this action and filed an amended verified complaint alleging, as relevant to this appeal, various claims against the City, the Board and Gilchrist (hereinafter collectively referred to as the city defendants), for tortious interference with its contract, as well as violations of plaintiff’s constitutional rights, illegal spot zoning, and diminution in its property value. Supreme Court granted the city defendants’ motion for summary judgment dismissing the complaint against them. Plaintiff reportedly settled all claims—including breach of contract, fraud and tortious interference—against defendants Starfire, Sherwood, Brunswick Research and Bradley, which are not before us.

On plaintiff’s appeal, we affirm Supreme Court’s award of summary judgment to the city defendants largely for the reasons stated in the court’s written decision. With regard to plaintiffs claim of tortious interference against the City and Gilchrist, under settled law, this cause of action sounds in tort (see Alvord & Swift v Muller Constr. Co., 46 NY2d 276, 281 [1978]. As against the City, this claim is subject to notice of claim requirements (see General Municipal Law § 50-e [1] [a]; § 50-i [1]; see also Brown v City of New York, 95 NY2d 389, 392-393 [2000]). Given plaintiffs failure to file a notice of claim (or to request permission to file a late notice), plaintiff is precluded from recovery against the City for this cause of action (see Smith v Town of Long Lake, 40 AD3d 1381, 1384 [2007]; Hallett v City of Ithaca, 8 AD3d 870, 871 [2004], lv denied 3 NY3d 608 [2004]).

Plaintiff’s tortious interference claim against Gilchrist was properly dismissed because, even viewing the evidence most favorably to plaintiff, the nonmoving party, and giving him the benefit of every favorable inference (see Gadani v Dormitory Auth. of State of N.Y., 43 AD3d 1218, 1219 [2007]), there is no reasonable view of the evidence that Gilchrist intentionally and unjustifiably—as opposed to merely negligently—procured the breach of the plaintiff-Starfire lease (see Lama Holding Co. v Smith Barney, 88 NY2d 413, 424-425 [1996]; Harris v Town of Fort Ann, 35 AD3d 928, 929 [2006]; Bradbury v Cope-Schwarz, 20 AD3d 657, 659-660 [2005]), i.e., that Gilchrist’s conduct was “solely malicious” (Rosario-Suarz v Wormuth Bros. Foundry, [1110]*1110233 AD2d 575, 577 [1996] [internal quotation marks omitted]; see Williams Oil Co. v Randy Luce E-Z Mart One, 302 AD2d 736, 738-739 [2003]; see also Murray v SYSCO Corp., 273 AD2d 760, 761-762 [2000]). Further, the proof could not support a finding that “the contract would not have been breached but for [Gilchrist’s] conduct” (Lana & Samer v Goldfine, 7 AD3d 300, 301 [2004]; see Northeast Wine Dev., LLC v Service-Universal Distribs., Inc., 23 AD3d 890, 893 [2005], affd 7 NY3d 871 [2006]). Plaintiff failed to offer proof that Gilchrist’s conduct was not in furtherance of his official duties and not motivated by genuine municipal/public health and safety concerns (regardless of their merit), or was “motivated by malice, personal gain or a desire to injure plaintiff’ in any respect or to unjustifiably procure Starfire’s breach of its contract with plaintiff (Rosario-Suarz v Wormuth Bros. Foundry, 233 AD2d at 577). Also, the record clearly reflects that Bradley and Sherwood had determined that the site was not suitable prior to the arranged meeting with Gilchrist, and plaintiff did not submit proof capable of establishing that “but for” Gilchrist’s subsequent action, Starfire would not have breached its contract with plaintiff. Thus, the tortious interference cause of action was correctly dismissed as against the City and Gilchrist.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Deitrich v. Binghamton Rd. Elec., LLC
2026 NY Slip Op 00557 (Appellate Division of the Supreme Court of New York, 2026)
Matter of Haunted Forest, LLC v. Town of Wilson
2025 NY Slip Op 04361 (Appellate Division of the Supreme Court of New York, 2025)
Matter of Buenos Hill, Inc. v. City of Saratoga Springs
2024 NY Slip Op 00111 (Appellate Division of the Supreme Court of New York, 2024)
Altman v. DiPreta
2022 NY Slip Op 02774 (Appellate Division of the Supreme Court of New York, 2022)
Blackmon v. City of Syracuse
2020 NY Slip Op 4254 (Appellate Division of the Supreme Court of New York, 2020)
O'Connor v. Shultz
2018 NY Slip Op 7380 (Appellate Division of the Supreme Court of New York, 2018)
Conte v. Emmons
Second Circuit, 2018
Ripka v. County of Madison
2018 NY Slip Op 4624 (Appellate Division of the Supreme Court of New York, 2018)
Abramoski v. State of New York
146 A.D.3d 1063 (Appellate Division of the Supreme Court of New York, 2017)
Loskot-D'Souza v. Town of Babylon
137 A.D.3d 751 (Appellate Division of the Supreme Court of New York, 2016)
Zito v. New York City Office of Payroll Administration
130 A.D.3d 1326 (Appellate Division of the Supreme Court of New York, 2015)
Schmidt & Schmidt, Inc. v. Town of Charlton
103 A.D.2d 1011 (Appellate Division of the Supreme Court of New York, 2013)
Rowe v. NYCPD
85 A.D.3d 1001 (Appellate Division of the Supreme Court of New York, 2011)
Potter v. Atarien
31 Misc. 3d 846 (New York Supreme Court, 2011)
Sonne v. Board of Trustees of Village of Suffern
67 A.D.3d 192 (Appellate Division of the Supreme Court of New York, 2009)
State v. International asset Recovery Corp.
56 A.D.2d 849 (Appellate Division of the Supreme Court of New York, 2008)

Cite This Page — Counsel Stack

Bluebook (online)
47 A.D.3d 1106, 850 N.Y.S.2d 273, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montano-v-city-of-watervliet-nyappdiv-2008.