Montana Power Co. v. Public Service Commission

692 P.2d 432, 214 Mont. 82, 1984 Mont. LEXIS 1120
Montana Supreme Court·Decided December 12, 1984·No. 84-290·Published·Cited by 7 cases

Opinion

MR. JUSTICE WEBER

delivered the Opinion of the Court.

Montana Power Company (MPC) requested that this Court assume original jurisdiction of a petition for declaratory judgment, mandate or other appropriate relief. This Court assumed jurisdiction to decide whether the certificate issued by the Board of Natural Resources and Conservation (BNRC) is conclusive and binding on the Public Service Commission (PSC). On this narrow legal question, we hold that the certificate is not conclusive and binding on the PSC.

*84 The issues as stated more broadly for analysis are:

1. Did passage of the Montana Facility Siting Act of 1973 (Siting Act), section 75-20-101, et seq., MCA, impliedly repeal or otherwise limit the PSC’s express statutory rate-making authority under section 69-3-109, MCA to determine in a rate case whether public utility property is “actually used and useful for the convenience of the public”?

2. Does the doctrine of collateral estoppel preclude the PSC from considering whether Colstrip Unit 3 is “actually used and useful” under section 69-3-109, MCA?

3. Does the doctrine of promissory estoppel require the PSC to include in the rate base MPC’s share of costs for Colstrip Unit 3?

As enacted in 1973 and amended in 1975, the Siting Act provided that a power facility may not be constructed or operated within Montana without a certificate of environmental compatibility and public need. The Siting Act requires a comprehensive study, hearings, and evaluation of any proposed facility before a certificate may be issued.

In 1973, MPC and several other utilities filed with the Department of Natural Resources and Conservation (DNRC) an application for a certificate of environmental compatibility and public need for Colstrip Units 3 and 4. We are concerned here only with Colstrip Unit 3. After extensive hearings, debate and study, the BNRC granted the certificate to MPC on July 22, 1976.

That certificate was based upon the BNRC’s findings of fact of which the following are pertinent:

- By the time Colstrip 3 is completed there will be a need for the energy produced.
- The facilities will serve the public interest, convenience and necessity.
- The loads and resources forecast by the utilities indicate an energy deficit in future years.
- The utility forecasts support a conclusion that Colstrip 3 will be needed.
- MPC studies show that Colstrip 3 is the lowest cost al *85 ternative for the consumer and the best choice available for future power needs.
- Availability of the additional energy will be beneficial to the population of Montana and the Pacific Northwest.

The certificate was also based upon extensive and detailed findings concerning the environmental and social impacts of Colstrip Units 3 and 4.

In its conclusions of law, the BNRC concluded that there was a need for the energy that would be produced by Col-strip Units 3 and 4 and that these facilities would serve the public interest, convenience and necessity. The BNRC ordered that a certificate of environmental compatibility and public need issue to the applicant utilities for Colstrip Units 3 and 4 and associated facilities.

The decision of the BNRC was appealed twice to this Court. Northern Plains Resource Council v. Board of Natural Resources and Conservation (1979), 181 Mont. 500, 594 P.2d 297; Northern Plains Resource Council v. Board of Natural Resources and Conservation (1979), 183 Mont. 540, 601 P.2d 27. These opinions did not address the BNRC’s determination that the energy produced by Col-strip Units 3 and 4 was needed, and did not consider changes in electricity rates to consumers which might result from the construction of Colstrip Units 3 and 4.

After completion of Colstrip 3 in 1983, MPC filed with the PSC an application to increase electric service rates to reflect the inclusion of Colstrip 3 and associated facilities in its rate base. The PSC conducted hearings which included extensive evidence regarding whether Colstrip 3 was “actually used and useful” to ratepayers. MPC moved the PSC to strike all portions of the testimony concerning the “used and useful” issue, contending that the PSC was precluded by the BNRC’s certificate from considering that matter. The PSC took MPC’s motion under advisement. MPC then filed its original application with this Court. The PSC later denied the MPC motion and concluded that Colstrip 3 was *86 not actually used and useful and therefore could not be included in MPC’s rate base.

I

Did passage of the Siting Act impliedly repeal or otherwise limit the PSC’s express statutory rate-making authority under section 69-3-109, MCA to determine whether public utility property is “actually used and useful for the convenience of the public”?

The purposes of the Siting Act are stated in section 75-20-102, MCA:

“(1) It is the constitutionally declared policy of this state to maintain and improve a clean and healthful environment for present and future generations, to protect the environmental life support system from degradation and prevent unreasonable depletion and degradation of natural resources, and to provide for administration and enforcement to attain these objectives.
“(2) The legislature finds that the construction of additional power or energy conversion facilities may be necessary to meet the increasing need for electricity, energy, and other products and that these facilities have an effect on the environment, an impact on population concentration, and an effect on the welfare of the citizens of this state. Therefore, it is necessary to ensure that the location, construction, and operation of power and energy conversion facilities will produce minimal adverse effects on the environment and upon the citizens of this state by providing that a power or energy conversion facility may not be constructed or operated within this state without a certificate of environmental compatibility and public need acquired pursuant to this chapter.”

The purposes of the Siting Act may be characterized as environmental in a broad sense.

Section 75-20-211, MCA required MPC to file with the DNRC and the Department of Health an application for a certificate containing a description of the facility to be *87 built, a summary of environmental impacts, a statement of need for the facility, a description of alternate locations and their comparative merits, and other relevant information. The Department of Health and the DNRC were then required to study the proposed facility. The determination of the Department of Health or Board of Health is acceptable in lieu of an environmental impact statement under the Montana Environmental Policy Act. Section 75-20-216, MCA.

Free access — add to your briefcase to read the full text and ask questions with AI

Montana Power Co. v. Public Service Commission, 692 P.2d 432, 214 Mont. 82, 1984 Mont. LEXIS 1120 (Mo. 1984).

692 P.2d 432 (Montana Power Co. v. Public Service Commission) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Robinson v. First Wyoming Bank, NA
909 P.2d 689 (Montana Supreme Court, 1995)
Taggart v. Rutledge
657 F. Supp. 1420 (D. Montana, 1987)
Hammer v. Justice Court
720 P.2d 281 (Montana Supreme Court, 1986)
State Ex Rel. Greely v. Water Court of State
691 P.2d 833 (Montana Supreme Court, 1985)