Montana-Dakota Utilities Co. v. Public Service Commission

874 P.2d 236, 1994 Wyo. LEXIS 59, 1994 WL 178145
CourtWyoming Supreme Court
DecidedMay 12, 1994
DocketNo. 93-141
StatusPublished
Cited by1 cases

This text of 874 P.2d 236 (Montana-Dakota Utilities Co. v. Public Service Commission) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montana-Dakota Utilities Co. v. Public Service Commission, 874 P.2d 236, 1994 Wyo. LEXIS 59, 1994 WL 178145 (Wyo. 1994).

Opinion

THOMAS, Justice.

At issue in this case is the effect of a partial reversal by this court of an order entered by the Public Service Commission of Wyoming (PSC) in a proceeding to adjust gas purchase prices. In Montana Dakota Utilities Co. v. Pub. Serv. Comm’n of Wyoming, 847 P.2d 978 (Wyo.1993) (MDU I), this court reversed an order of the PSC to the extent it adjusted the non-gas component of the rates charged by Montana-Dakota Utilities Co. (MDU), and it approved the portion of the order permitting an increase of rates due to the pass-on of wholesale gas rates. After remand, the PSC conducted further proceedings that still failed to include notice of, or a proper hearing on, the non-gas components of the rates charged by MDU. Despite our partial reversal, the PSC adopted a stance that it could not adjust retroactively the rates approved in the order it entered in the prior proceeding. The opinion of this court was not mysterious, and we have some difficulty relating to the interpretation of the opinion espoused by the PSC. The February 12,1992 order, to the extent it was reversed, was void and of no effect and could not in any way adjust the non-gas component of the rates charged by MDU. We reverse the Findings, Conclusions and Order on Oral Argument Issues entered by the PSC on May 21, 1993, and the case is remanded to the PSC with instructions to maintain in effect the non-gas component of MDU rates existing prior to its order of February 12, 1992 and to permit MDU to impose a surcharge on its billings to recoup the amounts it was denied pursuant to the February 12, 1992 order.

In its Appellant’s Brief, MDU articulated the following issues:

1. Are the Wyoming Public Service Commission’s Findings, Conclusions and Order on Oral Argument issued May 21, 1993, arbitrary and capricious, unsupported by substantial evidence and unlawful?
2. Is Montana-Dakota Utilities Co. entitled to charge retail gas customer rates which reflect the increase in the gas cost element approved by the Wyoming Public Service Commission in its Final Order issued February 12, 1992 and the pre-Feb-ruary 12,1992 level for the non-gas component?
3.Is Montana-Dakota Utilities Co. entitled to levy a surcharge upon its customers for amounts lawfully owed but not charged or collected due to the Wyoming Public Service Commission’s illegal adjustment in its Final Order to the non-gas component of the utility’s customer rates?

In its Brief of Appellees, the PSC chooses to articulate the issues in this way:

1. Did the Wyoming Public Service Commission act in accordance with Wyoming law when it denied a refund to appellant MDU?
2. Did the Wyoming Public Service Commission act in accordance with Wyoming law when it denied appellant’s request to reinstate the non-gas component of the rate?

The PSC posture in this case is that, by precedent from this court, its treatment of the case upon remand was justified and lawful.

The complete factual background of this case is set forth in MDU I. For our purposes, the summary begins on August 29, 1991, when the PSC issued a notice and order setting a public hearing for October 29, 1991. The purpose of the noticed hearing was to address an application by MDU to increase its retail rate on gas purchased from Williston Basin Interstate Pipeline Company (WBI), its wholesale gas supplier. The Federal Energy Regulatory Commission (FERC) had authorized WBI to increase its wholesale gas rate, and MDU sought authorization to pass the increased cost of gas on to its retail consumers. A refund apportionment to MDU customers throughout the state was also heard at the same time, but that aspect of the case is not in issue. The notice of the hearing by PSC failed to apprise MDU that any adjustment in the non-gas component of MDU’s charges to its customers would be considered at the hearing.

Following the notice, the PSC secretary sent a letter, dated September 4, 1991, to [238]*238MDU in which he stated his concern with possible over-earnings by MDU from its gas operations based on its last two annual reports. The secretary requested detailed information from MDU on both its gas and electric operation, the latter making up the non-gas component of the rate MDU charges its customers. This letter did not apprise MDU of the fact that the PSC intended to consider the non-gas component of its rate at the hearing scheduled for addressing the pass-on of MDU’s increased wholesale gas costs.

The hearing was held on October 29,1991, and the parties then submitted briefs. Thereafter, the PSC entered its order of February 12, 1992 in which, in addition to adjusting the refund apportionment, the PSC reduced the non-gas component of MDU’s rates by $0.0972 per dekatherm, which was to correct what the PSC perceived to be over-earnings. Following a denial of a request for a rehearing by MDU, MDU took the appeal, which resulted in this court’s decision in MDU I. The thrust of our holding in MDU I is that the PSC, by the notice it gave for the hearing, was entitled to adjust MDU rates only to accomplish the pass-on of the increase in the cost of gas. We held it would be possible for the PSC to encompass a general rate-making proceeding in connection with a pass-on gas proceeding, although we noted there would be an awkward delay by virtue of combining such issues. We held, however, unless the PSC furnished notice to the utility of its intention to consider the pass-on proceeding as a general rate-making proceeding, it could not so expand the nature of the proceedings. We held the notice given by the PSC to MDU in this case was not effective to expand the scope of the proceedings, and we reversed the PSC’s adjustment of the non-gas portion of the customer rates.

The case was remanded to the PSC for further proceedings consistent with the court’s opinion. Conceptually, that could include furnishing a notice of a general rate-making proceeding, but it was also clear the PSC needed to amend its order to delete the reduction of the non-gas component while entitling MDU to charge the rate justified by the increase in the cost of its gas. It is obvious a surcharge was required to make MDU whole because of the delay in permitting implementation of the increased rate.

After the case was remanded, the PSC ordered the parties to file briefs on any appropriate adjustment of the non-gas component of MDU’s customer rates. On April 20, 1993, the PSC heard oral arguments, but did not receive any evidence relating to the non-gas component of the rates. It considered only the arguments of the parties and a stipulation that essentially was discounted in its order. The PSC then entered another order on May 21, 1993 in which it mandated the $0.0972 per dekatherm reduction in MDU’s non-gas component rate be continued in effect until MDU produced substantial evidence in a general rate-making case that a greater rate was required. MDU was ordered to file a general rate-making case on or before July 1,1993. MDU filed a petition for review of that order with the district court, and the district court then certified the case to this court.

What occurred on remand is interesting and even amazing. The PSC did not order any further evidentiary hearing nor was any hearing conducted; instead, it reviewed the matter upon oral arguments by attorneys for MDU and for the Intervenor Consumer Representative Staff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cook v. Wyoming Oil & Gas Conservation Commission
880 P.2d 583 (Wyoming Supreme Court, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
874 P.2d 236, 1994 Wyo. LEXIS 59, 1994 WL 178145, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montana-dakota-utilities-co-v-public-service-commission-wyo-1994.