Montague Compressed Air Co. v. City of Fulton

148 S.W. 422, 166 Mo. App. 11, 1912 Mo. App. LEXIS 511
CourtMissouri Court of Appeals
DecidedJune 4, 1912
StatusPublished
Cited by7 cases

This text of 148 S.W. 422 (Montague Compressed Air Co. v. City of Fulton) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Montague Compressed Air Co. v. City of Fulton, 148 S.W. 422, 166 Mo. App. 11, 1912 Mo. App. LEXIS 511 (Mo. Ct. App. 1912).

Opinion

REYNOLDS, P. J.

— This is an action, the petition in which contains three counts.

The first count alleges a contract between plaintiff and defendant city, the plaintiff a manufacturing corporation, one of the defendants the city of Fulton, a city of this state, the others certain of its officers. For brevity we will hereafter refer to the defendants in the singular, intending by that the city. The contract is in the form of a proposal from plaintiff, accepted by defendant city, and all in writing, under which plaintiff proposed to furnish to the city “two Obear Air Lift Displacement Pumps of the aggregate [18]*18guaranteed capacity of 300 gallons of water per minute when lifting water from a nine inch and six inch cross sectional diameter wells any height with eighty pounds air pressure, conditioned of course that the wells will furnish 300 gallons of water per minute.” Plaintiff was also to furnish an air compressor of specified size and make, “all for the sum of $2900 f. o. b. cars Pulton, Missouri. Payment to be made to us thirty days after installation and operation of the compressor and pumps and determined to be satisfactory.” This is followed by specifications in detail as to the capacity of the proposed plant and for the purposes of this case unnecessary to be here set out. The first count prays for judgment for this amount with interest from December 31, 1907, and for costs.

The second count charges that after the installation and acceptance of the pumps and air compressor plaintiff, for the purpose of reinstalling the pumps at a lower working point in the well, at the instance and request and understanding with defendant, selected, ordered and caused to be shipped to defendant the necessary mechanism and materials for installation of the pumps at a cost of $643.40. Itemizing this account, plaintiff asks judgment for that amount.

There is a further count in the petition, setting up an equitable cause of action, which it is unnecessary to notice as it was disregarded at the trial and no error is assigned upon it one way or the other.

The answer, admitting the execution of* the contract set out in the petition for the installation of the pumping plant, avers that that was the only contract entered into between the city and plaintiff; admits that under that contract plaintiff proceeded to install the'pumping machinery; that by the terms of it plaintiff obligated itself that the plant would pump 300 gallons of water per minute when both pumps were operated at the same time and when the lift of the water would not exceed 500 ’ feet, but denies that plaintiff [19]*19carried out and performed its contract according to its provisions and denies that the installation of the pumping machinery was made and the operation of the compressor and pumps was satisfactorily determined on the 27th of November, 1907, or at any other time; denies that they were ever accepted or that on December 31, 1907, plaintiff presented its bill to the city and demanded payment thereof in- any sum. To the contrary, defendant avers that after the pumping’ plant had been installed in November and the pumps failed to give and furnish 300 gallons of water per minute but furnished not more than 125 gallons of water per minute, the agent of plaintiff claimed that the pumps were not deep enough and had them lowered and they again failed to give an increase in the amount of water furnished; that they were operated for a considerable time under the direction of plaintiff’s agent and failed to produce more than 125 gallons of water per minute; that plaintiff failed to operate both pumps at the same time and when they were both operated at the same time the two pumps gave no more water than when the larger of the two pumps was worked alone; that the pumps continued to be used from the time of the installation until sometime in March following, they being operated at the direction of plaintiff’s agent, and that neither plaintiff nor its agent ever reported to the officers of the city that plaintiff was ready to make a test nor did he request during that whole time that the test be made of the pumps, but on the contrary the agent knew that at no time had the pumps given the amount of water required by the contract; that at the reque.st of plaintiff’s agent the pumps were removed so that agent could examine the valves; that in the attempt to remove the pipes under the direction of this agent of plaintiff, the piping and pumps broke away from the tackle and fell about 700 feet into the well; that at great expense defendant had the piping removed and the well [20]*20cleared out and made 420 feet deeper and notified plaintiff that the well was ready for replacing of the pump according to the contract and plaintiff refused to replace it. Setting up the representations alleged to have been made by plaintiff’s agent prior to entering into the contract and a failure of these representations, the answer to this first count alleges nonperformance of the conditions of the contract. Averring that after the well was cleared of the pipe and deepened, the well “at all times both before and after it was deepened furnished a sufficient quantity of water and at all times the said pump had a greater submergence than the plaintiff required, and that by reason of the facts herein pleaded as defense to the first count of .the petition the defendant, the city of Fulton, owes the plaintiff nothing on said contract, and prays judgment against the plaintiff on said first count of the petition.”

The answer to the second count denies generally the averments of that count, and after a more specific denial of the correctness of the items in this count, pleads that the city, by a resolution duly adopted by its council, offered to pay plaintiff the sum of $295 to cover the repair of the pump on condition that plaintiff would replace the destroyed pumps and make the pumps work when operated together and at the same time according to the terms of the contract, it being provided in the resolution to this effect that nothing in it was intended to change or alter the terms and provisions of the original contract. It is also averred that plaintiff refused this, wherefore it is claimed that defendant is not liable.

A counterclaim is also interposed by another count in the answer, the city claiming $3681.62 by way of expenditures made and damage to the city for breach of contract by plaintiff.

It appears by the recitals of the abstract of the record proper that after a hearing of the evidence of [21]*21plaintiff, defendant demurred to the second count of the petition and the court sustained • it, whereupon plaintiff took a nonsuit as to this second count with leave to move to set it aside, afterwards filing this motion and saving exception on its being overruled. At the close of defendant’s testimony defendant took a nonsuit on the counterclaim with leave to move to set that aside, but no further action on this appears.

The jury returned a verdict on the first count of plaintiff’s petition in favor of defendant; judgment followed and plaintiff filed a motion for new trial, one in arrest of judgment and one to set aside the nonsuit on the second count of the petition. The only motion for new trial before us and as set out in the abstract as having been filed by plaintiff, after assigning that the verdict is against the evidence and the weight thereof and against the law as applied to the evidence and against the law as set out in the instructions given by the court, reads as follows:

“3.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Donovan v. Kansas City
175 S.W.2d 874 (Supreme Court of Missouri, 1943)
Fleshner v. Kansas City
156 S.W.2d 706 (Supreme Court of Missouri, 1941)
Kavli v. Leifman
292 N.W. 210 (Supreme Court of Minnesota, 1940)
Hawkins v. Cox
66 S.W.2d 539 (Supreme Court of Missouri, 1933)
Wright v. Quattrochi.
49 S.W.2d 3 (Supreme Court of Missouri, 1932)
Metz v. Warrick
269 S.W. 626 (Missouri Court of Appeals, 1925)
Likes v. City of Rolla
167 S.W. 645 (Missouri Court of Appeals, 1914)

Cite This Page — Counsel Stack

Bluebook (online)
148 S.W. 422, 166 Mo. App. 11, 1912 Mo. App. LEXIS 511, Counsel Stack Legal Research, https://law.counselstack.com/opinion/montague-compressed-air-co-v-city-of-fulton-moctapp-1912.