Monongahela West Penn Public Service Co. v. Albey

31 F.2d 85, 1929 U.S. App. LEXIS 3397
CourtCourt of Appeals for the Sixth Circuit
DecidedFebruary 15, 1929
DocketNo. 5069
StatusPublished
Cited by4 cases

This text of 31 F.2d 85 (Monongahela West Penn Public Service Co. v. Albey) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monongahela West Penn Public Service Co. v. Albey, 31 F.2d 85, 1929 U.S. App. LEXIS 3397 (6th Cir. 1929).

Opinion

HICKS, Circuit Judge.

Defendant entered (1) a general denial, and for further defense the defendant entered the plea of (2) assumption of risk and (3) contributory negligence.

Plaintiff had verdict and judgment, and defendant brought a writ of error and assigned errors. The principal assignments are: (1) That there should have been a directed verdict for defendant, and (2) that the court took from the jury the defense of assumption of risk.

The physical situation was this: Plaintiff in error furnished electric power to the. steel company through six wires in two series of -three each, one series over the other, carried on wooden poles and coming into the plant .to a transformer at a substation. The top series were insulated and the lower ones were hare, but these wires carried 25,000 volts of electricity, and insulation was said to be insufficient protection from contact. The substation was fenced and carried a sign which read “22,000 VOLTS, DANGEROUS.” Between it and the first pole to the east and under the wires was a small shanty where defendant in error worked. The steel corporation desired to erect a larger building for the welders, and to do this it became necessary to remove the shanty and this pole. The new building, entirely of steel, was about 56 feet long by 15 feet wide, running east and west, and was of shed-like construction built against the machine shop. The roof sloped from the machine shop and was about 11 feet from the ground at its outer edge. During its erection plaintiff in error, at the re[86]*86quest of the steel company, on February 28, 1925, removed the old pole and erected another of the same height (35 feet) about 15 feet eastwardly and against the east end of the new shed and attached the six wires thereto on cross-arms at the same height from the ground as they were originally. The plaintiff in error had a supply of longer poles, and the wires might have been still further elevated. By the new arrangement the wires were actually brought about 10 inches closer to the roof of the new shed than they were originally. The roof of the new building was higher than that'of the old by something like 3 feet, and the wires ran east and west with the roof, sloping from the cross-arms on the pole at the east of the building to the pole at the transformer. The elevation of the wires at the east pole was 25 feet 11 inches and at the transformer 14 feet 7 inches. It was variously testified to that at the point where defendant in error was injured the lower wires were from 40% to 62 inches from the roof and 17 to 18 feet from the ground. The location of the wires at the transformer was not disturbed. To have done so would have necessitated an entire rearrangement at the substation. This whole electrical plant and equipment on the steel company’s property was owned, operated, and controlled by plaintiff in error. The changes indicated were made by plaintiff in error at the request of the steel company. The witness Zurich, then division manager for plaintiff in error, at the request of the steel company, went to the plant with his foreman, one Roberts,' and instructed Roberts to do the work. He testified: “I told him to ‘get the pole out of there and get the wires up in the clear.’ ”

He further testified that with reference to high-tension wires this expression: “ ‘Get the wires up in the clear’ means to get it out of the reach of any person so that they may not come in contact with it, so that if a man happened to have a saw or bar or hammer that he would not hit that if he should happen to be on a roof somewhere working. We figure around 10 feet for a clearance above a roof. I knew nothing whatever about these wires after the job was ordered done. I didn’t know the condition of them whatever after that. If it should develop that these wires were only 4 or 5 feet above the west end of this shanty which, is a steel building, built on a steel frame and steel metal on the outside, I would condemn the work with reference to its being proper or safe construction. I mean by condemn that if I saw a piece of construction of that kind with high-tension wires within 4 or 5 feet of any building where there was any work on it, I would, either stop the work until those wires were raised or vice versa. In other words, it absolutely would not be proper or safe construction.”

At the time the changes were made, the new building had not been completed. Roberts testified that he knew that the building was yet in process of construction, that the roof was not on, and that it would be necessary to put the roof on and for men to go upon the building, and while the roof was being put on the plaintiff in error at the request of the steel company shut off the power.

From the above recapitulation of the material evidence, it is clear that the question ’of negligence or due care upon plaintiff in error’s part was one of fact for the jury.

In Reynolds v. Iowa Southern Utilities Co., 21 F.(2d) 958 (C. C. A. 8), at page 960, it is said: “As stated in Joyce on Electric Law, § 445: ‘A company maintaining electrical wires, over which a high voltage of electricity is conveyed, rendering them highly dangerous to others, is under the duty of using the necessary care and prudence at places where others may have the right to go, either for work, business, or pleasure, to prevent injury.’ ”

In Perham v. Portland Electric Co., 33 Or. 451, at page 478, 53 P. 14, 23 (40 L. R. A. 799, 72 Am. St. Rep. 730) it is said: “Electric companies, of course, are not bound to have perfect apparatus or perfect construction, but they are required to exercise a degree of care and prudence in the construction and maintenance of their wires commensurate with the danger; and where their wires are designed to carry a strong and powerful current of electricity, so that persons coming in contact with them are certain to be seriously injured, if not killed, the law imposes upon' the company the duty of exercising the utmost care and prudence to prevent such injury; and whether such care-has been exercised in a given case is ordinarily for the jury. Cr os well, Electricity, § 234.”

In Daltry v. Electric Light, etc., Co., 208 Pa. 403, 409, 57 A. 833, 835, it is said: “Electricity when of sufficient voltage for lighting purposes is well known by electricians and others familiar with its properties to be most dangerous and likely to cause death to those who come in contact with its current. Those who deal with it or supply it, to the public are therefore required to recognize this fact and to exercise care eommeusu-[87]*87rate with the danger. A party responsible for an injury by reason of a failure to observe such care is guilty of negligence. As said in Fitzgerald v. Edison Electric Co., 200 Pa. 540 [50 A. 161, 86 Am. St. Rep.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Overland Const. Co. v. Sydnor
70 F.2d 338 (Sixth Circuit, 1934)
Hawthorne v. International-Great Northern R.
63 S.W.2d 243 (Court of Appeals of Texas, 1933)
King Cotton Mills, Inc. v. Wilson
61 F.2d 1004 (Fourth Circuit, 1932)

Cite This Page — Counsel Stack

Bluebook (online)
31 F.2d 85, 1929 U.S. App. LEXIS 3397, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monongahela-west-penn-public-service-co-v-albey-ca6-1929.