Monks v. United States

79 Ct. Cl. 302, 1934 U.S. Ct. Cl. LEXIS 295, 1934 WL 2016
CourtUnited States Court of Claims
DecidedMay 7, 1934
DocketNo. D-44
StatusPublished
Cited by6 cases

This text of 79 Ct. Cl. 302 (Monks v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monks v. United States, 79 Ct. Cl. 302, 1934 U.S. Ct. Cl. LEXIS 295, 1934 WL 2016 (cc 1934).

Opinion

Littleton, Judge,

delivered the opinion of the court:

The principal items, upon which the claim presented in this suit is based, are (1) the amount of $31,130.28, increased cost of labor due to defendant’s increases in wages paid for labor at the Charleston Navy Yard and increased cost for cement, sand, and stone over the price thereof at the date of the contract and over the price upon which plaintiff based his bid; (2) deduction of $6,000 from the contract price for elimination of waterproofing of basement against surface drainage after this work had- been performed in accordance with the contract; (3) deduction of $6,225 from the contract price as a result of the elimination of the furnishing and installation by plaintiff of freight entrance doors; and (4) deduction of $14,850 from the amount due under the contract as penalty for delay. Other items involving amounts claimed for alleged extra work, etc., will be hereinafter set forth.

Upon the issuance by the Navy Department of the advertisement for bids, accompanied by the specifications for the storehouse at Charleston, plaintiff, Arnold, who had been engaged in the building-construction business for a number of years, visited the site of the building for the purpose of [333]*333ascertaining the existing local conditions at the Charleston Navy Yard as to the acquisition and cost of materials, availability for his use of facilities and equipment at the yard, and the rentals therefor. After such investigation and the receipt of certain information with reference thereto from Public Works Officer Chambers in charge of the navy yard at that time, plaintiff concluded to submit his proposal for the construction of the building in question. During this investigation and the conference with Public Works Officer Chambers, the latter advised plaintiff of the yard rates for labor and furnished him a schedule of such yard rates; he also advised plaintiff of the yard rates for rental of yard equipment, furnishing a schedule thereof, and stated that the Government was in a position to supply him with such yard equipment and trackage facilities as might be needed for the work, such as traveling cranes for excavating, dump and flat cars, and gondola cars for handling materials, etc., in the yard and away from the site of the work. Material-men were, not permitted to deliver materials at the site of the building, all materials being delivered to the plaintiff at the wharf or on the railroad siding at the yard entrance and thereafter brought to the site of the work from the general delivery point by yard equipment. The public works officer also advised plaintiff that the Government had a contract for, and had on hand in the yard,- a supply of cement, sand, and stone; furnished plaintiff with the Government prices for the cement, sand, and stone, which prices were specified by plaintiff as the basis for his bid, and advised him that the yard would be glad to furnish these materials to him at the Government prices on his contract for the building. As a result of this investigation, and upon the information thus obtained, plaintiff submitted to the Bureau of Yards and Docks his proposal to construct the building, setting forth therein the terms and conditions upon which the amount thereof and the time for completion were based, as set forth in finding III. The Bureau of Yards and Docks accepted plaintiff’s proposal as made and made the terms and conditions thereof a part of the contract subsequently executed by incorporating the same in paragraph 8 of the contract.

[334]*334About October 3, 1917, plaintiff received for execution the formal contract as drawn by the Bureau of Yards and Docks. Prior to this date the plaintiff’s conference with Public Works Officer Smith, preparatory to commencement of the work, had taken place, as set forth in the findings. Labor was scarce and costs therefor were increasing due to war conditions. In order to guard against any misunderstanding with reference to the statement incorporated in the contract, that the amount of the contract price was based upon the present market price of labor, plaintiff returned the contract unsigned to the Chief of the Bureau of Yards and Docks for a more specific statement with reference to plaintiff’s right to reimbursement in the event of increases in wages for labor at the Charleston Navy Yard. The Bureau in a conference with plaintiff advised that the terms of his proposal had been made a part of the contract, thereby taking care of the matter of labor costs, and construed the contract as drawn, as providing, in paragraph 8, for an increase in the amount paid for labor in the event the Government increased the rates for labor in the Charleston Navy Yard. The contract was thereupon executed by plaintiff and the defendant.

We are of opinion that plaintiff’s written statement of September 4, 1917, which was incorporated in the contract, became a part of the contract terms and must be given effect. Charles Ward Engineering Works v. United States, 73 C.Cls. 557. That the terms and conditions of such statement formed a part of the contract clearly appears from a consideration of paragraph 191 of Specification no. 2469 and paragraphs first, seventh, and eighth of the contract. In specifying these terms and conditions plaintiff was complying with paragraph 191 of the specifications. The first paragraph of the formal contract provides for construction of the building complete in accordance with the specifications, as contemplated in item 1, paragraph 191 thereof, except as thereinafter modified, and paragraph 8 of the contract modified the specifications by making plaintiff’s statement a part of the contract. This further clearly appears, we think, from the seventh paragraph of the contract which [335]*335provides that the Government reserves the right to reduce the amount of $217,300 stated in the contract, or such other amount as might be payable thereunder, in such a manner as to obtain a credit based on the difference between the price for construction materials, i.e., cement, sand, and stone, stated by plaintiff in his proposal, and the cost at which such materials might be secured for plaintiff by the Government. Charles Ward Engineering Works v. United States, supra. In other words, if the Government had been able to secure these materials and furnish them to plaintiff at prices less than those specified by plaintiff in his statement accompanying his bid, the Government would have obtained a reduction in the contract price. If the terms of the statement made a part of paragraph 8 are not to be given effect, the incorporation thereof in the contract and the provision of paragraph 7 are purposeless.

In these circumstances plaintiff is entitled to recover the increased cost for labor independently of addendum no. 1 to the General Provisions, as to the construction of which by the Bureau we have some doubt, and the increased costs for cement, sand, and stone in excess of the prices upon which the amount stated in the contract was based. These amounts are: Labor, $27,763.71; cement, $1,588.89; sand and stone, $1,777.68. Counsel for defendant contend that if any amounts are allowable on account of these items, only the increased cost to February 8, 1918, the expiration date of the period of one hundred and twenty days for completion of the work, should be allowed because of plaintiff’s failure to complete the work on time. In view of the remission of the penalty deducted by the defendant, hereinafter mentioned, the total increased costs are allowable. The findings show that defendant was responsible for many of the delays.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

George H. Whike Construction Co. v. United States
140 F. Supp. 560 (Court of Claims, 1956)
Spencer v. United States
102 F. Supp. 774 (Court of Claims, 1952)
W. E. Callahan Construction Co. v. United States
91 Ct. Cl. 538 (Court of Claims, 1940)
Wharton Green & Co. v. United States
86 Ct. Cl. 100 (Court of Claims, 1937)

Cite This Page — Counsel Stack

Bluebook (online)
79 Ct. Cl. 302, 1934 U.S. Ct. Cl. LEXIS 295, 1934 WL 2016, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monks-v-united-states-cc-1934.