Mondakota Gas Co. v. Becker

445 P.2d 745, 151 Mont. 513, 1968 Mont. LEXIS 342
CourtMontana Supreme Court
DecidedSeptember 27, 1968
DocketNo. 11329
StatusPublished
Cited by3 cases

This text of 445 P.2d 745 (Mondakota Gas Co. v. Becker) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Mondakota Gas Co. v. Becker, 445 P.2d 745, 151 Mont. 513, 1968 Mont. LEXIS 342 (Mo. 1968).

Opinion

MR. CHIEF JUSTICE JAMES T. HARRISON

delivered the Opinion of the Court.

This is an appeal from the district court of Fallon County. The ■ action- stems from an agreement made in 1941 between the plaintiff-appellant and the defendant-respondent. The com[514]*514plaint was filed in 1956, fifteen years after the agreement was made, and the cause finally brought to trial in October, 1966. At the conclusion of plaintiff’s case in chief the trial court granted defendant’s motion to dismiss and entered judgment for the defendant. The plaintiff moved to have the trial judge make findings of fact and conclusions of law under Rule 41(b), M.R.Civ.P. Plaintiff also moved for a new trial. Plaintiff now appeals from the denial of those motions, and here contends that the findings of fact and conclusions of law were not specific enough to meet the requirements of Rule 41(b), M.R.Civ.P.

The plaintiff in its complaint alleged that the original agreement was made in 1941 whereby the defendant agreed to drill two gas wells, guaranteeing that each would produce 100,000 cubic feet of gas per day. It appears that the wells were completed in 1941, however, plaintiff alleged that they did not meet the guarantee made by the defendant. It was also alleged that the plaintiff paid the defendant for the cost of drilling the wells and made royalty payments on gas produced by the wells between 1941 and 1954. Plaintiff’s theory of action in the district court was that there was a breach of contract when the wells failed to meet the guarantee and that since the money was mistakenly paid to the defendant, the defendant should make restitution on the grounds of unjust enrichment.

The only two wells in dispute here are the Becker-Foster and the Becker-State wells located in Fallon County, Montana. Plaintiff in his brief has also attempted to include the N.P. well in Fallon County but was in error to try to do so because the original complaint covered only the Becker-Foster and the Becker-State wells, and no amendments were allowed to that complaint. Certain evidence pertaining to the N.P. well was allowed in by the good graces of the trial court, but such evidence was clearly extraneous and cannot be considered on this appeal.

[515]*515The plaintiff makes four specifications of error, but then went on to say in its brief that the entire case hinges on one of those specifications: Whether the findings of fact and conclusions of law were specific enough to comply with Rule 41(b), M.R.Civ.P.

Rule 41(b) provides, in part: “After the plaintiff, in an action tried by the court without a jury, has completed the presentation of his evidence, the defendant, without waiving his right to offer evidence in the event the motion is not granted, may move for a dismissal on the ground that upon the facts and the law the plaintiff has shown no right to relief. The court as trier of the facts may determine them and render judgment against the plaintiff or may decline to render any judgment until the close of all the evidence. If the court renders judgment on the merits against the plaintiff, the court shall make findings as provided in Rule 52(a). Unless the court in its order for dismissal otherwise specifies, a dismissal under this subdivision and any dismissal not provided for in this rule, other than a dismissal for lack of jurisdiction or failure to join a party under Rule 19, operates as an adjudication upon the merits.”

From a reading of the record of the district court proceedings it is apparent that the district court dismissed because the plaintiff had “shown no right to relief.” However, because that court did not state otherwise the dismissal and judgment acted as an adjudication upon the merits and it became necessary for the court to make findings of fact and conclusions of law.

The only evidence on the production of the two wells in question was testimony given by John Wight, who at one time was manager of Mondakota Gas Company and also manager of its predecessor, Mondakota Development Company. During the' testimony of Wight, plaintiff’s attorney attempted to qualify him as somewhat of an expert in the drilling and testing of oil and gas wells by showing his many years of [516]*516experience in the oil and gas business. We say “somewhat of an expert” because Wight admitted he was not an engineer.

Wight testified that he was personally present on different occasions when he had engineers run tests on all the wells Becker drilled for the plaintiff. On direct examination Wight never once testified that production in the two wells in question was never the guaranteed minimum. Wight did testify that the pressure in one of the wells in question was so low it “wouldn’t put any gas in the line.” The line he was referring to was one owned by Montana-Dakota Utilities Company (MDU) and which the plaintiff had succeeded in having declared to be a common carrier in order that it might transport its own gas to market. It was later brought out that the reason plaintiff’s well would not “put any gas in the line” was because MDU had subsequently increased the pressure in its line. So in the direct examination of Wight by plaintiff’s attorney it was never shown that the wells would not produce 100,000 cubic feet of gas per day; it was merely shown that pumping became- necessary in order to make use of the MDU line.

In cross examination Wight’s direct testimony was impeached in two respects. First, Wight admitted that he made statements in 1951 and 1953 at Mondakota Gas Company shareholders’ meetings to the effect that the wells in question were producing and that Mondakota still owed Becker money. The weight of that cross examination completely nullified any claim by the plaintiff that Becker was overly compensated and unjustly enriched.

Second, in 1949 in a deposition taken in connection with a suit filed by plaintiff against MDU, Wight stated that the two wells in question were each capable of producing over 300,000 cubic feet per day. Wight tried to justify that statement by contending he relied on statements made- by Becker. He so Contended even in view of the fact that he, on direct examination, admitted to having the wells tested several times by [517]*517engineers of his own choosing. It is also well to remember that in the trial of the instant case the plaintiff never introduced any of the reports made by engineers hired by Wight. It would seem that if those reports had shown production to be below 100,000 cubic feet per day the plaintiff would have lost no time in seeing they were introduced.

To reiterate, the plaintiff’s entire case rested on two contentions : Plaintiff claims the wells would not produce 100,000 cubic feet of gas per day yet Wight in 1949 contended that each well was capable of producing in excess of 300,000 cubic feet per day. Second, plaintiff claims Becker was unjustly enriched because the wells did not meet the guarantee; that is, the unjust enrichment claim rested on whether the wells met the guarantee. Since Wight’s testimony that they did not meet the guarantee was totally impeached by his 1949 deposition we are left with no evidence at all on whether they met the guarantee. In such a situation it is impossible to tell whether there was any unjust enrichment of Becker.

Even if it is admitted that plaintiff’s proof failed, the plaintiff still contends that the findings of fact and conclusions of law were not detailed enough to meet the requirements of Rules 41(b) and 52(a). The pertinent portion of the judgment below held: “*

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Wheeler v. Carlson Transport
704 P.2d 49 (Montana Supreme Court, 1985)
Holloway v. University of Montana
582 P.2d 1265 (Montana Supreme Court, 1978)
Montana Mobile Home Tourist Court, Inc. v. Finley
514 P.2d 762 (Montana Supreme Court, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
445 P.2d 745, 151 Mont. 513, 1968 Mont. LEXIS 342, Counsel Stack Legal Research, https://law.counselstack.com/opinion/mondakota-gas-co-v-becker-mont-1968.