Monadnock Construction, Inc. v. Westchester Fire Insurance Co.

186 F. Supp. 3d 269, 2016 U.S. Dist. LEXIS 64925, 2016 WL 2868688
CourtDistrict Court, E.D. New York
DecidedMay 16, 2016
Docket16-CV-0420
StatusPublished

This text of 186 F. Supp. 3d 269 (Monadnock Construction, Inc. v. Westchester Fire Insurance Co.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Monadnock Construction, Inc. v. Westchester Fire Insurance Co., 186 F. Supp. 3d 269, 2016 U.S. Dist. LEXIS 64925, 2016 WL 2868688 (E.D.N.Y. 2016).

Opinion

MEMORANDUM AND ORDER

JACK B. WEINSTEIN, Senior United States District Judge

Table of Contents

I. Introduction ,. .270

II. Facts... 271

III. Complaint and Motion to Dismiss ...273

IV. Law ... 274

A. Motion to Dismiss .. .274

B. New York General Obligations Law Section 17-103 .. .274

V. Application of Law to Facts .. .275

VI. Conclusion .. .277

I. Introduction

This breach of contract action arises out of defendant Westchester Fire Insurance Company’s (‘WFIC”) refusal to pay on performance bonds it issued in favor of plaintiff Monadnock Construction, Inc. (“Monadnock”). The legislative limitations period on a breach of contract claim on the bonds would be six years. The parties contracted for a two-year limitations period. They have a sharp disagreement with respect to the validity of a contractual tolling provision and its application to the contractual two-year limitations period.

[271]*271WFIC insists that, pursuant to General Obligations Law . section 17-103, the contractual tolling provision must be strictly construed in the same way that a provision tolling a statutory limitation period- is. It contends that the tolling provision is invalid, and the two-year-.contractual limitation period bars Monadnock’s claim. It moves to dismiss the complaint.

WFIC’s motion is denied.

Because the complaint was filed within two years of the notice of default upon which the complaint is partially .based, it is within the contractual limitations period without the need for any tolling.

With respect to the portion of the complaint that is based on an earlier notice of default, plaintiff may benefit from either the contractual tolling provision or from equitable estoppel as a result of WFIC’s activities. Either theory has sufficient col- or to warrant denial of WFIC’s motion.

While the court has found no cases from this circuit that have discussed the distinction between a provision that tolls a contractual limitations period and one that tolls a statutory limitations period, and the parties have not presented any, it is concluded that the application of normal contractual interpretive rules designed to reveal the parties’ intentions, is appropriate in this situation. The strict construction of General Obligations Law section 17-103 typically given, by New York courts is not essential in this case, where the toll was of a shortened contractual limitations period, rather than the, standard statutory period, and is tied to definitive events. The public policy the New York. Court of Appeals sought to protect in adopting a strict interpretation of the statute is not offended by this result. Applying standard rules of contract interpretation, it is found that the contractual tolling provision is enforceable and Monadnock’s claims are timely.

The implication of WFIC’s position would be to force parties to commence an action before their claims have fully ripened. Public policy is best served by permitting parties to wait. Often, delay will avoid the necessity of a suit with full discovery and trial.

II. Facts

Monadnock was the contractor for two mixed use projects in the Hunters Point South section of Long Island City. On January 3, 2013, Monadnock entered into two contracts with Glasswall for the design and supply of a curtain wall system including windows, doors, storefronts and other materials for the two projects. Complaint, Mar. 1, 2016, ECF No. 9 (“Compl”), at ¶ 8. The first contract was for $8,412,502 and required the production and delivery of 5,836 windows. The second contract was for $4,587,498 and required the production and delivery of 3,120 widows. Id. at ¶ 11. Both contracts required Glasswall to obtain payment and performance bonds, which it did from WFIC. Id. at ¶ 12. The performance bonds required any legal action to be taken within two years of a notice of default. Id. at Ex. A at § 11.

The contracts required Glasswall to ship completed windows to one of the projects starting on July 1, 2013, and to the second project starting on September 1, 2013. Id. at ¶ 13. On March 15, 2013, the project schedule was changed to require delivery of windows to begin on August 7, 2013, and August 29, 2013, for the first and second projects, respectively. Id. at ¶ 14. On August 16, 2013, after the delivery of windows was to have begun, Glasswall’s attorney sent Monadnock a letter stating that “completed window assemblies” would be ready to ship by September 1, 2013. Mo-nadnock alleges that no windows were delivered by September 1, 2013. Id. at ¶ 15.

[272]*272On November 20, 2013, Glasswall issued another production schedule representing that part of the order for the first project would be complete by December 6, 2013, and part of the order for the second project would be complete by December 12, 2013. According to Monadnock, Glasswall did not meet these deadlines. Id. at ¶ 16.

In addition to the delays in delivery, Monadnock alleges that the product that Glasswall supplied was defective. Id. at ¶¶ 25-26.

On September 16, 2013, Monadnock sent Glasswall and WFIC a notice of default under the contracts; notices of continuing default were sent on October 23, 2013, and December 31,2013. Id. at ¶ 30.

On January 13, 2014, Monadnock terminated Glasswall’s contracts and provided WFIC with the required notice under the performance bonds. Monadnock demanded that WFIC take action pursuant to Section 5 of the bonds, which required WFIC to arrange for Glasswall to complete the contracts, complete the contract itself or through another contractor, pay Monadnock an amount in damages, or disclaim liability under the bonds. Id. at ¶¶ 32-33, Ex. A at § 5. Monadnock alleges that WFIC refused to act in response to the demand. Id. at ¶ 34.

On March 6, 2014, as required by Section 6 of the bonds, Monadnock sent WFIC a notice demanding WFIC act within seven days or be in default. Id. at ¶ 35, Ex. A at § 6. Monadnock alleges that WFIC again failed to act in response to the notice. Id. at ¶ 36.

On April 4, 2014, the parties entered into an agreement to amend the contracts (“Amendment Agreement”). Id. at ¶37. The drafting of the Amendment Agreement was careful, with WFIC participating fully. Hr’g Tr., May 11, 2016, at 6:5-9 (“It’s a very carefully negotiated agreement. Westchester took a lead in putting that agreement together when it looked like the parties were, the deal, the contract, was coming apart. The notice of default had already been issued. Every word in that agreement was sweat over.”).

The Amendment Agreement permitted Glasswall to complete the contracts, requiring delivery of windows to begin the week of March 24, 2014, and to be complete by June 7, 2014. Deck of Howard Kleinhendler in Opp’n to Def.’s Mot. to Dismiss, Apr. 18, 2016, ECF No. 25 (“Kle-inhendler Deck”), at Ex. C at § 5.

There are two clauses in the Amendment Agreement that are relevant to the instant motion. The first clause withdraws Monadnock’s first termination of the contracts and claims on the bonds:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
186 F. Supp. 3d 269, 2016 U.S. Dist. LEXIS 64925, 2016 WL 2868688, Counsel Stack Legal Research, https://law.counselstack.com/opinion/monadnock-construction-inc-v-westchester-fire-insurance-co-nyed-2016.