Molly Jessie Company

CourtArmed Services Board of Contract Appeals
DecidedFebruary 5, 2020
DocketASBCA No. 62134
StatusPublished

This text of Molly Jessie Company (Molly Jessie Company) is published on Counsel Stack Legal Research, covering Armed Services Board of Contract Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Molly Jessie Company, (asbca 2020).

Opinion

ARMED SERVICES BOARD OF CONTRACT APPEALS

Appeal of -- ) ) Molly Jessie Company ) ASBCA No. 62134 ) Under Contract No. FA440719PA002 )

APPEARANCE FOR THE APPELLANT: Mr. Greg Ryan Principal

APPEARANCES FOR THE GOVERNMENT: Jeffrey P. Hildebrant, Esq. Air Force Deputy Chief Trial Attorney Lawrence M. Anderson, Esq. Lt Col Scott A. Van Schoyck, USAF Trial Attorneys

OPINION BY ADMINISTRATIVE JUDGE SHACKLEFORD

This is an appeal from a final decision terminating the subject contract for cause. The appellant has elected Board Rule 12.3, Accelerated Procedure, and the parties have agreed to a record submission under Board Rule 11. Each party filed an initial brief. Appellant filed a reply brief and the government answered that reply. In addition to the briefs, the record includes the government's Rule 4 file (R4, tabs 1-74), two documents submitted by appellant with its initial brief (exs. A-1, -2) and an affidavit from Mr. Ryan. Also included are several photographs from the government's Rule 4 file upon which appellant has added commentary. Only the propriety of the termination for cause is before us.

FINDINGS OF FACT

1. On February 27, 2019, the Air Force, on behalf of Cardinal Creek Golf Course (government) awarded Contract No. F A4407 l 9PA002 ( contract) to Molly Jessie Company (appellant or MJC) to perform three line items of work. Item No. 001 was to perform tree removal, root pruning and canopy pruning in accordance with the contract's Statement of Work (SOW) in the amount of$17,100. (R4, tab 3 at 4-5)

2. Item No. 0002 was to perform Option No. 2, remove all trees behind the third tee including driving range side of fence - hole # 3 in accordance with the SOW for the amount of $1,700. Item No. 0003 was to perform Option No. 3, Remove 3 Cotton Wood Trees behind the 15th green and other work near holes 5, 6, 7, 11, 14 and 15 for the amount of $2,500. (R4, tab 3 at 4-5) 3. The- period of performance set forth in the contract was February 20, 2019 to March 20, 2019 for Item Nos. 1, 2 and 3 (R4, tab 3 at 10).

4. The contract included Paragraph 13, Termination for Cause. which provided:

a. The NAFI may, subject to paragraphs c. and d. below, by written notice of cause to the Contractor, terminate this contract in whole or in part if the Contractor fails to-

( 1) Deliver the supplies or perform the service within the time specified within this contract or any extension; (2) Make progress, so as to endanger performance of this contract (however, see paragraph b. below); or (3) Perform any of the other provisions of this contract (however see paragraph b. below).

b. The NAFI's right to terminate this contract under paragraph a. 2. and a. 3. above, may be exercised if the Contractor does not cure such failure within 10 days (or more if authorized in writing by the Contracting Officer) after receipt of notice from the Contracting Officer specifying the failure.

c. If the NAFI terminates this contract in whole or in part, it may acquire, under the terms and in the manner the Contracting Officer considers appropriate, supplies or services similar to those terminated, and the Contractor will remain liable to the NAFI for any excess costs for those supplies or services. However the Contractor must continue the work not terminated.

d.... The Contractor shall not be liable for any excess costs if the failure to perform the contract arises from causes beyond the control and without the fault or negligence of the Contractor. Examples of such causes include: (1) Acts of God or of the public enemy (2) Act of the NAFI in either its sovereign or contractual capacity (3) Fires (4) Floods (5) Epidemics (6) Quarantine restrictions

2 (7) Strikes (8) Freight embargoes (9) Unusually severe weather

g. If, after termination, it is determined that the cause by the Contractor was excusable, the rights and obligations of the parties shall be the same as if the termination had been issued for convenience of the NAFI.

h. The rights and remedies of the NAFI in this clause are in addition to any other rights and remedies provided by law or under this contract.

(R4, tab 3 at 15-16)

5. The contract also included paragraph 3, Claims, which provided in part:

b. "Claims," as used in this clause, means the inability of a Contractor and the Contracting Officer to reach a mutual agreement related to contractual issues in controversy resulting in the filing of a written demand or assertion seeking payment of money, adjustment or interpretation of contract, or other relief, and issuance of a Contracting Officer's final decision ....

e. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any request for relief, claim, appe~l, or action arising under the contract, and comply with any decision of the Contracting Officer.

(R4, tab 3 at 13-14)

6. The SOW included the following:

Work should be performed when the soil is firm enough to support any equipment used in the execution of this work.

3 Any turf damage (i.e. tire ruts) are the responsibility of the contractor to repair back to same or improved condition.

(R4, tab 3 at 5)

7. Appellant's employees arrived on site on or around March 6, 2019 (R4, tab 6 at 3). From that point forward, some work was performed and the government made one or more partial payments to appellant, but the work was not completed by the March 20, 2019 contract due date. Thus the parties had discussions (e.g., R4, tab 12, tab 23 at 1), and on April 25, 2019, bilateral contract modification POOOO 1 was issued extending the period of performance to June 30, 2019, providing as follows:

The purpose of this modification is for the following:

A. Cancel any previous requested modifications ... by the Government B. Change the completion date from 20 March 2019 to an estimated completion date of 30 June 2019. Any additional delays for weather will be coordinated, approved, and agreed to between Molly Jessie and the Government. C. Partial Payments will be authorized. D. Contract price be increased by $1,700.00 for remobilization and the contract price is increased from $21,300.00 to $23,000.00 for this modification. E. All other terms and conditions remain unchanged. In consideration of the modification agreed to herein as complete equitable adjustment for time and cost associated. The contractor hereby releases the Government from any and all liability under this modification for further equitable adjustments.

(R4, tab 39 at 3) Bilateral contract modification POOOOl also established a contract completion date for each line item of June 30, 2019, none of which included the modifier "estimated."

8. Thereafter, on or about May 13, 2019, appellant's crews resumed tree removal, root pruning and canopy pruning at the golf course (R4, tab 42 at 2). For May 14, 2019, appellant reported that they had completed seven stump grindings, but that due to ground conditions they could make only limited work towards completion. MJC said that the soil was wet and support for its equipment was not favorable. Moreover, continuing heavy rain was expected over the next several days. For May 15, 2019, site conditions were wet and poor but some work was accomplished.

4 No work was performed on May 16 or 17 as appellant was changing out its equipment. (Id.) On May 18, 2019, appellant reported weather was coming in, that the wind was too strong and it was not safe to work on tree work above ground. The grounds were also in poor shape. (Id.) Some work was performed on May 20, 2019, but the "area was extremely wet." Poor weather conditions prevented any work on May 21, 2019.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lisbon Contractors, Inc. v. The United States
828 F.2d 759 (Federal Circuit, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
Molly Jessie Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/molly-jessie-company-asbca-2020.