Moldovan v. Prestige Construction NY, LLC

CourtDistrict Court, E.D. New York
DecidedMarch 31, 2025
Docket1:20-cv-04699
StatusUnknown

This text of Moldovan v. Prestige Construction NY, LLC (Moldovan v. Prestige Construction NY, LLC) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Moldovan v. Prestige Construction NY, LLC, (E.D.N.Y. 2025).

Opinion

UNITED STATES DISTRICT COURT EASTERN DISTRICT OF NEW YORK ------------------------------------x

MIKLOS MOLDOVAN,

Plaintiff, MEMORANDUM & ORDER 20-cv-4699(EK)(VMS)

-against-

PRESTIGE CONSTRUCTION NYC, LLC, 635 ROCKAWAY, LLC, AND TFK ELECTRIC CORP.,

Defendants.

------------------------------------x ERIC KOMITEE, United States District Judge: Miklos Moldovan fell off a ladder while working at a Brooklyn construction site, injuring his left hand, back, and neck. Invoking the Court’s diversity jurisdiction, he sued the site owner, general contractor, and one subcontractor, arguing that they violated their duty to maintain a safe workplace. Notably, he did not sue the subcontractor that actually employed him. The parties have cross-moved for partial summary judgment on two of plaintiff’s causes of action: New York Labor Law Sections 240(1) and 200. Among other contentions, all defendants seek summary judgment because no reasonable jury could conclude (i) that they failed to supply proper protection to Moldovan, or (ii) that anyone other than Moldovan himself was the proximate cause of his injuries. Additionally, defendant TFK Electric argues that it is not a proper defendant to the Section 240(1) claim, and all three defendants argue the same contention as to Section 200.

For the reasons that follow, the plaintiff’s and defendants’ motions are granted in part and denied in part. Background The following facts are taken from the parties’ Rule 56.1 Statements of Material Facts and the documents incorporated by reference therein. They are undisputed unless otherwise noted. We draw any inferences in favor of the non-moving party. See Tenenbaum v. Williams, 193 F.3d 581, 593 (2d Cir. 1999). The Parties. Moldovan sued three defendants. Defendant 635 Rockaway Avenue LLC owned a property located at its namesake location in Brooklyn, New York. Def. R. 56.1 Statement (“Def. 56.1”) ¶ 1, ECF No. 79.1 635 Rockaway hired

defendant Prestige Construction NY, LLC as the general contractor to remodel the building. Id. ¶¶ 2, 26. Prestige Construction, in turn, hired defendant TFK Electric Corporation to perform electrical work. Id. ¶ 3; Pl. Counter R. 56.1 Statement (“Pl. Counterstatement 56.1”) ¶ 3, ECF No. 85. TFK then subcontracted with plaintiff Moldovan’s employer, AS HH Enterprises Corporation, to run wiring

1 The parties also refer to the property as 589 Rockaway Avenue, Brooklyn, New York. See Def. 56.1 ¶ 1; Pl. R. 56.1 Statement (“Pl. 56.1”) ¶ 1, ECF No. 83. throughout the building. Def. 56.1 ¶¶ 4, 19. The division of labor between TFK and AS HH is not entirely clear, but TFK’s principal stated that TFK’s remit extended to “whatever is

connected with electrical work,” including running or implementing wiring and installing light fixtures. Torok Dep. Tr. 69:7-70:5, Def. Ex. B, ECF No. 77-2. Moldovan worked as an electrician for AS HH Enterprises. Def. 56.1 ¶ 5; Pl. Counterstatement 56.1 ¶ 5 (agreeing that AS HH was plaintiff’s employer). Moldovan has not sued AS HH Enterprises in this action.2 The Accident. On July 23, 2020, Moldovan was working at the site. Def. 56.1 ¶ 6. His job was to “wire the rooms, put up outlet housings and switch[] housings, pull lines through the housings[,] and run lines going to the electric box.” Id. ¶ 7. AS HH Enterprises owned six-foot and eight-foot ladders that

were available at the site. Pl. Counterstatement 56.1 ¶ 8. Moldovan’s accident occurred on the sixth floor of the building, in a “tiny room . . . similar to a utility room,” which had a metal frame ceiling. Id. ¶ 11. At the time, Moldovan was installing a “ceiling bar box” — that is, an electrical housing for a light fixture. Id. To install the box, Moldovan brought a 6-foot A-frame ladder into the utility

2 635 Rockaway and Prestige Construction brought a third-party complaint against AS HH. See ECF No. 30. They voluntarily dismissed that complaint on September 2, 2021. See ECF No. 34. room. Def. 56.1 ¶ 12. Moldovan did not request any other equipment “that could have been used instead of the ladder.” Id. ¶ 18.

Moldovan set up the ladder by “placing it in the center of the room, unlock[ing] it ma[king] sure the two metal clamps were fully extended, and ma[king] sure all four of the legs were touching even ground.” Id. ¶ 12. He placed the ladder on level ground made of roughed-out concrete, which was clean and free of debris. Id. The ladder’s four feet were covered in rubber. Id. ¶ 13. It had eight steps and was tall enough to reach the center of the ceiling where plaintiff planned to install the bar box. Id. Once the ladder was set up, Moldovan confirmed that it was locked on both sides, steady, and undamaged. Id. ¶ 14. Moldovan climbed the ladder, then steady, to the

seventh rung and began installing the bar box. Pl. Counterstatement 56.1 ¶ 15. Before the accident, he had a screw gun in his right hand and was holding part of the exposed “grid of metal frames” above him. Def. 56.1 ¶ 15; see also Moldovan Dep. Tr. 96:21-25, 98:4-8, Def. Ex. A, ECF No. 77-1 (Moldovan testifies that the grid was attached to the ceiling). As Moldovan reached downward to retrieve a screw from his pouch, the “ladder shifted” and Moldovan “had to hold onto the [ceiling] frame because [he] became unstable.” Moldovan Dep. at 99:3-24. Asked what caused the ladder to shift, Moldovan replied: “I don’t know. It just did.” Id. at 99:25-100:5; Def. 56.1 ¶ 16. The ladder did not fall. Def. 56.1 ¶ 16. Moldovan,

however, fell off the ladder onto his lower back and cut his left hand on the ceiling frame. Pl. 56.1 ¶ 18. On-Site Supervision. Jack Wolcowitz, a member of 635 Rockaway LLC, periodically visited the site to check in on the project’s progress, as did Constanine Gubareff, a “project manager” who worked for a non-party. Pl. Counterstatement 56.1 ¶ 27. Still, in his deposition, Wolcowitz noted that 635 Rockaway did not have anyone “on site in and around July 2020.” Wolcowitz Dep. Tr. 23:10-12, Def. Ex. D, ECF No. 77-4. Wolcowitz and Gubareff were in charge of the site on behalf of the owners. Pl. Counterstatement 56.1 ¶ 27. If Wolcowitz observed work that was dangerous or unsafe, he had the authority

to stop it by speaking to the general contractor, Prestige Construction. Id. Gerber Blanco, Prestige Construction’s safety supervisor, was on site on the day of the accident. Def. 56.1 ¶ 22. Moldovan’s supervisor told Blanco about the accident soon after it occurred and Blanco went to investigate. He saw a bent lamp, the ladder, and blood on the floor. Id. ¶ 23-24. Jozsef Torok, a TFK principal, was not at the site on the day of the accident. Def. 56.1 ¶ 20. When deposed, Torok testified that he was at the worksite once or twice a week and that “if [he] saw something on the job site when [he] was there that was either dangerous or could have caused harm to an

employee” he could “stop[] that work from continuing.” Torok Dep. Tr. 13:11-17, 24:10-15, Pl. Ex. D, ECF 82-4. Legal Standard Summary judgment is appropriate if the record demonstrates that “there is no genuine dispute as to any material fact and the movant is entitled to judgment as a matter of law.” Fed R. Civ. P. 56. “A fact is material for these purposes if it might affect the outcome of the suit under the governing law. An issue of fact is genuine if the evidence is such that a reasonable jury could return a verdict for the nonmoving party.”3 Lovejoy–Wilson v. NOCO Motor Fuel, Inc., 263 F.3d 208, 212 (2d Cir. 2001).

The moving party has the burden of demonstrating the absence of a question of material fact. Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 256 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Anderson v. Liberty Lobby, Inc.
477 U.S. 242 (Supreme Court, 1986)
Heublein, Inc. And Subsidiaries v. United States
996 F.2d 1455 (Second Circuit, 1993)
Jaramillo v. Weyerhaeuser Co.
536 F.3d 140 (Second Circuit, 2008)
Blake v. Neighborhood Housing Services of New York City, Inc.
803 N.E.2d 757 (New York Court of Appeals, 2003)
Cahill v. TRIBOROUGH
823 N.E.2d 439 (New York Court of Appeals, 2004)
Rizzuto v. L.A. Wenger Contracting Co.
693 N.E.2d 1068 (New York Court of Appeals, 1998)
Ross v. Curtis-Palmer Hydro-Electric Co.
618 N.E.2d 82 (New York Court of Appeals, 1993)
Noor v. City of New York
130 A.D.3d 536 (Appellate Division of the Supreme Court of New York, 2015)
Marquez v. L & M Development Partners, Inc.
141 A.D.3d 694 (Appellate Division of the Supreme Court of New York, 2016)
Haidhaqi v. Metropolitan Transportation Authority
2017 NY Slip Op 6525 (Appellate Division of the Supreme Court of New York, 2017)
Russin v. Louis N. Picciano & Son
429 N.E.2d 805 (New York Court of Appeals, 1981)
McCarthy v. Turner Construction, Inc.
52 A.D.3d 333 (Appellate Division of the Supreme Court of New York, 2008)
Chowdhury v. Rodriguez
57 A.D.3d 121 (Appellate Division of the Supreme Court of New York, 2008)
Weber v. Baccarat, Inc.
70 A.D.3d 487 (Appellate Division of the Supreme Court of New York, 2010)
Grochowski v. Ben Rubins, LLC
81 A.D.3d 589 (Appellate Division of the Supreme Court of New York, 2011)
Auriemma v. Biltmore Theatre, LLC
82 A.D.3d 1 (Appellate Division of the Supreme Court of New York, 2011)
Melchor v. Singh
90 A.D.3d 866 (Appellate Division of the Supreme Court of New York, 2011)
Samaroo v. Patmos Fifth Real Estate, Inc.
102 A.D.3d 944 (Appellate Division of the Supreme Court of New York, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Moldovan v. Prestige Construction NY, LLC, Counsel Stack Legal Research, https://law.counselstack.com/opinion/moldovan-v-prestige-construction-ny-llc-nyed-2025.